Resolved
To approve utilisation of £900,140 from the endorsed Medium Term Financial Strategy 2010-13 for the delivery of Phase 2 of the City Gateways Programme and development of detailed designs for Phase 3 improvements.
Cabinet approved this item on Thursday 28 October 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
To approve utilisation of £900,140 from the endorsed Medium Term Financial Strategy 2010-13 for the delivery of Phase 2 of the City Gateways Programme and development of detailed designs for Phase 3 improvements.
CITY GATEWAYS - POTTERIES WAY IMPROVEMENTS APPENDICES to Cabinet Paper
28th October 2010 Potteries Way before works commenced….. Phase 1 works carried out so far…..
Poor quality tree and shrub planting, difficult to maintain with Removal of poor quality trees and shrubs replaced with instant hedgerows and semi mature boulevard problems of litter and vermin infestations. Utilitarian lighting columns tree planting. New lighting columns and banners to the central reservation which will also be and street furniture badly in need of renewal. resurfaced with a resin bound gravel treatment similar to the above image (Example: Milton Keynes) Proposed Layout Plan Existing site
The existing Bryan Street crossing creates a poor visual impression with aged surfacing and street furniture of mixed styles and little to signify a thoroughfare into the City Centre
High quality natural stone paving forming shared surface to create gateway space entering the City Centre
Gateway signage feature containing wayfinding and branding information for the City Centre
Wider more direct crossing for pedestrian movements to and from the City Centre
New macadam surfacing incorporating natural Resurfacing of central reserve to Existing tree and hedgerow stone colouring to match footpaths be carried out in Phase 1 planting carried out in Phase 1 emphasising pedestrian route improvements improvements
DRAWING TITLE: SKETCH LAYOUT PLAN - BRYAN STREET CROSSING DATE: SEPTEMBER 2009 DRAWN: SR/AM Proposed Layout Plan Existing site
The existing Hillchurch Street crossing creates a poor visual impression with aged walling and surfacing and sheep pen arrangement creating a convoluted route for pedestrians
New wider crossings with macadam surfacing incorporating natural stone colouring to match footpaths emphasising pedestrian route.
High quality natural stone paving forming shared surface to create gateway space entering the City Centre
Existing tree and hedgerow planting carried out in Phase 1 improvements
High quality natural stone paving Gateway signage feature New steps creating a Resurfacing of central reserve to forming shared surface to create containing wayfinding and more direct access route be carried out in Phase 1 gateway space entering the City branding information for the City for pedestrians improvements Centre Centre
DRAWING TITLE: SKETCH LAYOUT PLAN – HILLCHURCH STREET CROSSING DATE: SEPTEMBER 2009 DRAWN: SR/AM Falcon Works Retaining Wall Precedent Images
Before and after photomontages showing proposed cladding, lighting columns and reservation resurfacing
DRAWING TITLE: FALCON WORKS RETAING WALL – ILLUSTRATION OF PROPOSED CLADDING TREATMENT DATE: SEPTEMBER 2009 DRAWN: SR/AM Town Road Dudson Gateway
Before and after photomontage showing proposed gabion cladding
Huntbach Street Crossing
Precedent Images
DRAWING TITLE: PHASES 3 AND 4 - WORKS AT TOWN ROAD, DUDSON GATEWAY AND HUNTBACH STREET DATE: SEPTEMBER 2009 DRAWN: SR/AM
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
281010 CityGateways PotteriesWay Improvements Appendices.pdfReport | 7 pages | DownloadRead as text |
PDF |
City Gateways: Potteries Way Improvements (Forward Plan Item 201)Forward_plan | 6 pages | Download |
Follow Cabinet at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... | Agreed | Open |
| 3 Nov 2026 | Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... | Agreed | Open |
| 3 Nov 2026 | Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... | Agreed | Open |
| 3 Nov 2026 | Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... | Agreed | Open |
| 3 Nov 2026 | Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.