Resolved

That the Local Transport Plan (LTP) Capital Delivery Programme for 2012/13 be approved. 2. That approval is given to the advertising of Highways Act, Section 90(c) Notices relevant to all schemes within the 2012/13 Capital Delivery Programme which propose to include road humps, in order to ensure compliance with the relevant legislation. 3. That authority be delegated to the Assistant Director Technical Services, in consultation with the Cabinet Member for Planning and Transportation, to review the progress of scheme delivery throughout the year within each of the delivery package areas and respond to changing priorities throughout the year, and to reallocate funding between delivery package areas subject to approved key threshold limits as set out within the City Council’s Constitution. Any changes greater than these limits would need to be approved by Cabinet. 4. That approval is given to the delegation of authority to the Assistant Director Technical Services, in consultation with the Cabinet Member for Planning and Transportation, to approve and use additional developer contributions secured through Section 106, Section 278 and other sources in the delivery of improvements to the transport network.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet

Projects Project Description Project Stage Ward

Supporting the economy

Phase 2 Highway Imp'ts associated Quadrant Road Zebra Crossing Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Stafford Street Zebra Crossing Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Pall Mall Zebra Crossing Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Quadrant Road Bus Lane including carriageway widening Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Trinity street bus access improvements Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Marsh Street/Newhall Street junction improvement Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Marsh Street/Trinity Street contraflow bus lane Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Stafford Street Bus Gate Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Extension of City Centre Pedestrian Zone (Stafford Construction/Handover Etruria and Hanley with new City Centre Bus Station Street/Old Hall Street) 12/13

Phase 2 Highway Imp'ts associated Cycle Routes Improvements - city centre Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Appendix 1 Phase 2 Highway Imp'ts associated Amendments to Disabled Parking Provision Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13 Projects Project Description Project Stage Ward

Phase 2 Highway Imp'ts associated Amendments to loading provisions - City Centre Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Provision of amended taxi ranks - city centre Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Hinde Street bus Layover facilities Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Amendments to on-street Pay and Display Parking Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated City Centre traffic management changes Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated City Centre Bus stop improvements Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Stafford street/Albion square bus access improvement Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Phase 2 Highway Imp'ts associated Lower Bethesda Street bus gate Construction/Handover Etruria and Hanley with new City Centre Bus Station 12/13

Lichfield St Improvements Corridor improvement scheme aimed at reducing congestion Prelim Design Joiners Square and improving bus, pedestrian & cyclist access. These 13/14 &14/15 smaller scale Traffic Management measures will improve traffic flow along this key approach corridor into the City Centre and improve the sustainable transport offer. Projects Project Description Project Stage Ward

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
220312 LocalTransport Plan 2012-13 CapitalProgramme Appendix 1.docAppendix 74 KB DownloadRead as text
PDF
Local Transport Plan: 2012/13 Capital Programme (Forward Plan Item 342)Forward_plan 125 KB Download

At this meeting

Whole meeting

On this subject at Stoke-on-Trent

Search all
  1. Local Transport Plan - 2012/13 Capital Programme (Forward Plan Item 342)This decision
  2. 2026-29 Local Transport Settlement and Local Transport Delivery Plan (Notice of Decisions Reference: 2369)Agreed
  3. Local Transport Plan – 2024/25 Capital Programme and Supporting Highways Capital Programme (Notice of Decisions Reference: 2141)Agreed
  4. Local Transport Plan - 2023/24 Capital Programme and Supporting Highways Capital Programme (Notice of Decisions Ref: 2098)Agreed
  5. Local Transport Plan – 2022/23 Capital Programme and Supporting Highways Capital Programme (Notice of Decisions Ref: 1094)Agreed
  6. Local Transport Plan - 2017/18 Delivery Programme and Supporting Highways Capital Programme (Notice of Decisions Ref: 680)Approved

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies