Resolved
Agreed - That approval be given to commence formal consultation on the building of a new facility for Abbey Hill School and Performing Arts College on the site of the former Longton High School at Box Lane, Longton .
Cabinet agreed this item on Thursday 26 July 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed - That approval be given to commence formal consultation on the building of a new facility for Abbey Hill School and Performing Arts College on the site of the former Longton High School at Box Lane, Longton .
Open
Cabinet Outcome of the Preliminary Consultation on transfer of location and the rebuild of Abbey Hill School and Performing Arts College
Date: 26 July 2012 Report of: Director of Children and Young People’s Services Contact officer(s): Geoff Catterall 01782 23(8812) Cabinet Member Councillor Alan Dutton: Cabinet Member for Education Type of Decision Key Decision (Forward Plan Ref: 352) Wards Affected: City wide
1. Purpose of the Report: 1.1 To consider the outcome of the preliminary consultation on the transfer of Abbey Hill School and Performing Arts College to a purpose built school on the site of the former Longton High School.
2. Recommendation(s) 2.1 That approval be given to commence formal consultation on the building of a new facility for Abbey Hill School and Performing Arts College on the site of the former Longton High School at Box Lane, Longton.
3. Context and Implications 3.1 Abbey Hill School and Performing Arts College caters for children across the City with autism, communication and interaction difficulties, and needs related to cognition and learning. The school is currently located at Greasley Road, Bucknall. It has been identified under the Building Schools for the Future Programme (BSF) to be appropriate for a new build on a larger site. This report seeks to undertake a formal consultation on a new build facility at Box Lane, Longton.
Other Implications to be taken into consideration: Legal: Guidance will be followed in bringing forward statutory proposals to move the school’s location and for it to be rebuilt.
Financial: A total funding allocation of £11.4m has been set aside by
Report Page 1 Council to provide a new build solution for Abbey Hill through the BSF programme, on the basis that this will provide best value for money and long term sustainability for the school.
Human Resources: -
Equality Impact and The proposal aims to provide all pupils with appropriate Human Rights permanent special school provision. considerations:
Public Health: The proposals aim to increase the sports facilities available to the school’s pupils and to the local community.
Environmental Impact:
Policy Context: how the proposal(s) fits the Councils aims and objectives (tick those appropriate)
New Existing Best City to Independent Effective and Business Business x live / work x Lives x confident Council
Impact on Customers/ Partners: The proposal seeks to address the concerns of the local community, both school users and others.
Background papers and information sources: Making Changes to a School (DfE) Cabinet Report: Options Appraisal for Holden Lane and Abbey Hill – 26th January 2012
Enclosures: Appendix A
Report Page 2 Report Detail Outcome of the Preliminary Consultation on transfer of location and the rebuild of Abbey Hill School and Performing Arts College. 1. Background 1.1 The aim of BSF is to establish a city where young people have the skills, qualifications and aspirations to take advantage of the new employment opportunities arising from the city’s regeneration. The key principles of the programme are to:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Outcome of the Preliminary Consultation on transfer of location and the rebuild of Abbey Hill School and Performing Arts College (Forward Plan Item 352)Forward_plan | 5 pages | DownloadRead as text |
Follow Cabinet at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... | Agreed | Open |
| 3 Nov 2026 | Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... | Agreed | Open |
| 3 Nov 2026 | Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... | Agreed | Open |
| 3 Nov 2026 | Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... | Agreed | Open |
| 3 Nov 2026 | Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.