That the General Fund forecast outturn of £86.455m for 2012/13 as at month 6 (a predicted over spend of £1.958M) be noted. 2. That the Housing Revenue Account forecast surplus of £4.864m (an improvement of £1.103m against the revised budget) be noted. 3. That the forecast capital investment for the year of £197.455m compared to the revised approved budget of £235.806m, be noted.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Financial Performance Report as at the end of September 2012 Date 29 November 2012 Report of S151 Officer and Assistant Director, Financial Services Contact officer(s) Peter Bates Assistant Director - Financial Services Kerry Cartlidge Finance and Commercial Manager Cabinet Member Councillor Shotton Cabinet Member for Commissioning Procurement and Finance Type of Decision For information Wards Affected No Ward Implications
1. Purpose of Report 1.1 To summarise the financial position of the General Fund, Housing Revenue Account and Capital Programme as at the end of September 2012 and provide a forecast outturn for 2012/13.
2. Recommendation(s) 2.1 That the General Fund forecast outturn of £86.455m for 2012/13 as at month 6 (a predicted overspend of £1.958m) be noted. 2.2 That the Housing Revenue Account forecast surplus of £4.864m (an improvement of £1.103m against the revised budget) be noted. 2.3 That the forecast capital investment for the year of £197.455m compared to the revised approved budget of £235.806m, be noted.
3. Options Considered 3.1 There are no options associated with this report.
Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business Support and develop existing business Work with people to promote independence and healthy lives Make Stoke-on-Trent a great city to live in An effective and confident council
Report Page 1 Other Implications to be taken into consideration: Legal None
Financial See report detail
Human Resources None
Equality Impact / None Human Rights considerations
Public Health None
Environmental None Impact
Impact on Customers/Partners Services are being delivered in accordance with the MTFS agreed in February 2012.
Background papers and information sources Budget Setting Report 2012/13 – City Council 23 February 2012
Enclosures Appendix Ai 2012/13 General Fund financial position to the end of September (Month 6) Appendix Aii Savings plans Appendix Aiii Investment plans Appendix B 2012/13 HRA financial position to the end of September (Month 6) Appendix C Capital Programme Appendix D Risk Register
Report Page 2 Report Detail Financial Performance Report as at the end of September 2012 1. Background 1.1 The City Council agreed the 2012/13 Housing Revenue Account Budget and the General Fund Revenue Budget in February 2012. The Capital Programme was updated in July 2012 at City Council to take account of changes which had taken place since the budget was set in February; predominantly the commitment to become the anchor tenant for the Central Business District. 1.2 The scale of the unprecedented financial challenge faced by the city has been well documented since the announcement of the Comprehensive Spending Review (CSR) 2010. In summary, the City Council received a two year provisional settlement from the Government which placed the City Council as the 8th worst treated of all unitary authorities in the country. The City Council has proved its ability to deliver by responding proactively to the challenges faced with the majority of the savings (£36m in 2011/12 and £20m in 2012/13) being implemented or alternatives secured. 1.3 This report outlines the financial performance as at the end of September 2012 and the forecast outturn for 2012/13. 2. Policy Context 2.1 This financial performance is reported as part of the Budget and Policy Framework.
3. Proposal 3.1 Members are requested to note the forecast outturn for the General Fund, Housing Revenue Account and Capital Programme for 2012/13. Exploration of options to further improve the financial position for the remaining months of the year will be undertaken to provide the best possible platform for budget development for 2013/14 – 2015/16. 4. Consultation 4.1 Stakeholder consultation was undertaken with both the public and Members as part of the budget setting process prior to the budgets being presented to City Council for approval in February 2012. 5. Executive Summary
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.