That Cabinet note the progress against the project timetable as originally set out in the 14 th October 2011 Cabinet Report. 2. That Cabinet note the process that has to be adhered to with regard to the Final Business Case development and submission. 3. That Cabinet award delegated authority to the s151 Officer and the Assistant Director – Regeneration, Planning and Transportation, in consultation with the Cabinet Member for Regeneration, Planning & Transportation to submit the Final Business Case as per the process outlined. This is an urgent decision and therefore not subject to call-in.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
CABINET Update on PFI5 housing for older people project and the submission of the Final Business Case
Date 25th April 2013 Report of Director of City Renewal Contact officer(s) Joanne Tyzzer, Assistant Director (Regeneration, Planning and Development) Debbie Hope, Strategic Manager (Housing Growth and PFI5) Cabinet Member Councillor Ruth Rosenau : Cabinet Member for Regeneration, Planning and Transportation Type of Decision Key Decision (Notice of Decisions Ref: 272) Wards Affected Blurton, Chell and Packmoor, Abbey Green
1. Purpose of Report 1.1 This report has two main functions: 1. To update the Cabinet on the progress that has been made since 14th October 2011 when the critical path and the key decision gateways were first set out to Cabinet.
2. To explain the process that has to be followed when submitting a Final Business Case (FBC) to the Homes and Communities Agency in support of the PFI5 project and the commercial potential that both remaining bidding consortia offer to the Council that needs to be set out in the FBC submission.
1.2As set out in the October 2011 Cabinet Report, the timetable for approval by the HCA ,DCLG and HM Treasury do not align with the Council’s decision making processes and there are points in the procurement process whereby the need for urgent decisions is required to enable the bid to progress as per the milestones set out in the original approvals. There is a clear dictat from Central Government in the letter of 18th July 2011 from the HCA, that if the PFI 5 Credit approvals is to be accessed, the procurement process is to take no more than two years. If there is no ability to introduce flexibility in to the Council’s own decision making processes, the requirement to procure an appropriate bidding consortia within two years will not be achievable.
Report Page 1 2. Recommendation(s) 2.1 Cabinet is recommended to: 1. Note the progress against the project timetable as originally set out in the 14th October 2011 Cabinet Report. 2. Note the process that has to be adhered to with regards the FBC development and submission 3. Delegate authority to the s151 Officer, the Chair of the PFI5 Project Board/Cabinet Member for Regeneration, Planning & Transportation and the Assistant Director for Regeneration, Planning and Development to submit the FBC as per the process outlined.
3. Options Considered 3.1 The submission of the minute in support of developing the FBC is a requirement stipulated by Central Government if it is the Council’s express wish to participate in the PFI5 process. Therefore, the options that could be considered relate to a fundamental review as to whether the PFI process is the correct procurement route to follow.
3.2In December 2009, a Cabinet Report was approved that supported the submission of the Outline Business Case. This report set out that the PFI5 route to procuring new homes for older people was beneficial because the PFI proposal contributes directly to the delivery of the City’s ten year plan in relation to older people, Ageing Well, Living Well, which comprises the strategic framework for provision in relation to older people. The accelerated, large scale provision of extra care housing, enabled through the PFI project, will particularly assist in providing a choice of good quality and appropriate housing for older people in the City and, within that, promoting independent living by helping people to be able to continue to live safely in their own homes, with appropriate support being made available to them as they get older. The proposal is fundamental to providing an alternative to residential care for older people wanting to live in the City. Other funding routes have been considered but do not offer the same Value for Money return or are simply not available in the scale that is required to supply the number of homes required. Not providing homes for older people of a suitable quality and type would be against the Council’s strategic aims and objectives.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.