That Cabinet approve: · That Delegated authority is granted to the Director of City Renewal, in consultation with the Section 151 Officer, the Monitoring Officer, and the relevant Cabinet Members(s) to conclude negotiations of terms and conditions and to obtain and accept revised funding offers. · That delegated authority is granted to the Director of City Renewal, in consultation with the Section 151 Officer, the Monitoring Officer and relevant Cabinet Member(s) to produce a detailed Procurement Strategy for the Project and to procure and award contracts for the necessary works and services to secure the delivery of the Etruria Valley Infrastructure Connectivity Project in accordance with the terms of the agreed Procurement Strategy, subject always to acceptance of the revised funding conditions and within the existing approved revenue funding of £348,000 · That delegated authority is granted to the Director of City Renewal, in consultation with the Section 151 Officer, the Monitoring Officer and the relevant Cabinet Member(s) to conclude negotiations with necessary land owners to enable the new highway infrastructure to be constructed on their land.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Cabinet Delivery of Etruria Valley Infrastructure Connectivity Works
Date 31st July 2014 Report of Director of City Renewal (Place) Contact officer(s) Joanne Tyzzer, Assistant Director (Regeneration, Planning and Development) Kevin Bell, Strategic Manager (Regeneration & Development) Martin Woodruff, Programme Manager Mark Collins, Development Programme Manager Cabinet Member Councillor Ruth Rosenau : Cabinet Member for Regeneration, Planning and Transportation Type of Decision Key Decision (Urgent Decision) Wards Affected Etruria and Hanley, Burslem Central and Moorcroft
1. Purpose of Report 1.1 Etruria Valley Infrastructure Connectivity Works forms part of the capital programme agreed in February 2014.
1.2Cabinet have previously considered a report on the 23 rd May 2013, in association with accepting the Regional Growth Funding (RGF) associated with this project. However, circumstances around the project have changed considerably and officers have been engaged in discussions with Government Officials in order to secure a more comprehensive funding package to enable delivery of the whole project, which include RGF and local pinch point (PP) and single local growth fund (SLGF).
1.3This report is therefore considered to be an urgent item, and Cabinet is asked to consider it on that basis. It is deemed to be urgent due to the very short timescale to enter into a procurement exercise in order to appoint the required consultants to complete preliminary design. If this exercise is not completed now the City Council will unfortunately not be in a position to be able to spend the £4m available from the Regional Growth Fund for this year and thus will be lost and may also impact on our ability to secure future years funding.
Report Page 1 Version 2: 25/07/14 1.4 There is a need to conclude and formalise the terms and conditions of the Regional Growth Fund (RGF) and Local Pinch Point (PP) funding previously offered to Stoke-on-Trent City Council for the Etruria Valley Infrastructure Connectivity Works. The original terms for RGF have elapsed and we are waiting for Cabinet Office to confirm that there will be a variation for both the RGF and PP funding. We are now awaiting for the Cabinet Office to inform the Department for Business, Innovation and Skills (BIS) and the Department for Transport (DfT), and that they will issue new offers to the City Council. It is expected that most of the conditions contained in the original offers will be contained in any new offers and there will be new timescales to be agreed. The Preliminary Conditions contained in the original RGF conditional grant offer are included in Appendix 2.
1.5We still await a formal offer on the PP funding. In light of this, delegated authority is being sought to agree and accept the terms and conditions contained in any new RGF and PP offers.
1.6Subject to confirmation of the authority’s acceptance of the terms and conditions of the first phase of funding, the authority will be required to spend the full £4m by 31st March 2015. In light of the tight timescales to deliver this piece of work, authority is being sought to commence procurement for the works as soon as the offer of funding is accepted.
1.7A further Cabinet Report will be presented for a future Cabinet setting out the detail of the project for future phases...
2. Recommendation(s) 2.1 Cabinet approve: That Delegated authority is granted to the Director of City Renewal, in consultation with the Section 151 Officer, the Monitoring Officer, and the relevant Cabinet Members(s) to conclude negotiations of terms and conditions and to obtain and accept revised funding offers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.