What the committee will consider, in order, with every paper attached to its item. Quarterly Business Review Quarter 1 2014-15 is the main business.
Decision: Agreed – That the minutes of the previous meeting of the Cabinet held on 31 July 2014 be approved as a true and correct record of the proceedings. Decision page
Decision: To receive the Quarterly Business Review (QBR) Quarter 1 2014/15 This item is for information only and is therefore not subject to call in. Decision page
Decision: That the General Fund forecast outturn of £73.508mfor 2014/15 as at month 3 (a potential overspend of £5.499m) be noted. 2. That the Housing Revenue Account forecast underspend of £0.197m be noted. 3. That the Capital Investment Programme forecast for 2014/15 is £119.586m against the budget (including carry forward) of £135.263m be noted 4. That Directors and portfolio holders continue to implement action plans where pressures exist to reduce the impact of any potential overspends. 5. That the... Decision page
Decision: That in respect of individual debts of £25,000 and over, a total of £92,080.77 irrecoverable debt be written off against the appropriate provision. 2. That it be noted that the Section 151 Officer has written off the following amounts in respect of individual debts under £25,000 in accordance with the financial regulations approved delegations and agreed limits: • £679,956.30 in respect of business rates (NDR) • £26,694.6 in respect of former tenant arrears • £92,985.76 in respect of sundry... Decision page
Decision: That approval is given to utilise the Health Trust Europe (HTE) Management Consultancy Framework for the further engagement of PWC LLP to accelerate the delivery of savings from the business cases under development. 2. That authority is delegated to the Chief Executive in consultation with the Leader, Chief Operating Officer and the Cabinet Member for Finance, Procurement and Commissioning to agree the level of engagement with PWC, and to negotiate final terms of the financials within the... Decision page
Decision: That Cabinet support Option 1 and give approval for the relocation of the existing Children Centre, staff and resources to Stoke Local Centre. Decision page
Decision: That Cabinet note the intention to regenerate a number of dilapidated heritage buildings in Stoke Town Centre in conjunction with English Heritage and private sector partners, subject to due diligence around the market demand as part of the project development. 2. That Cabinet give delegated authority to the Director of Place in consultation with the Section 151 Officer and relevant Cabinet Member to submit (and if approved formally accept) an application to English Heritage for a Partnership... Decision page
Decision: That additional resources be made available to: Increase the section 75 agreement with North Staffordshire Combined Healthcare Trust so that additional Best Interest Assessors can be recruited to conduct the assessments o 4.5 permanent full time equivalent BIAs o Will need to include training costs Provide additional administration support to process both the referrals and the authorisations o One additional administrator within Combined Healthcare to process incoming referrals (as part of the... Decision page
View the declarations of interest for item 542.
Decision: That approval is given to commence a procurement process for the provision of an end to end postal service, based on a two year contract with an option to extend for a further year (Option3). It is anticipated that this process will be started as soon as approval is received. 2. That approval is also given to commence a separate procurement process for the provision of a hybrid mail service, based on a two year contract with an option to extend for a further year (Option3). It is anticipated... Decision page
Item 535 is where most of this meeting's papers sit: 2 papers, about 5.8 MB.
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 13 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 31 July 2014. 5 of its items lead into this meeting; 5 items are new. Point at any item to follow a thread. Procedural items are left out.
Notification of a completed review by the Adults and Neighbourhoods Overview and Scrutiny Committee, Stoke-on-Trent's Local Government Association childhood obesity peer challenge feedback and next steps, Delivery of Etruria Valley Infrastructure Connectivity Works do not return this time.
See the 31 July meetingEvery Cabinet meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Stoke-on-Trent, Cabinet
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.