Our Work, Your City Programme

Approved Executive 1 paper

Cabinet approved this item on Thursday 5 March 2015. Below is the council's own wording, with the papers it was decided on.

Item43

Resolved

That Cabinet: · approve Option 2 as set out in paragraph 3.2 of the report submitted to Cabinet to amend the Our Work, Your City (OWYC), logistic and furniture, fittings and equipment order date to after the handover certificate (practical completion) is agreed; · grant delegated authority the Assistant Chief Executive and/or Executive Director of Place, following consultation with the appropriate Cabinet Members(s) to deal with any consequential effects of changes to the OWYC Programme; · approve the use of the contingency budget to fund any additional legal costs in 2015/16; · note the progress of the OWYC Programme; · note the appointment of Taylor Wessing and external experts.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 7 pages

Purpose of report

1.1To brief Cabinet on the latest developments in the development by Genr8 of the 2 Smithfield buildings the council will be occupying and seek approval to amend plans appropriately.

2 Recommendation(s)

2.1That Cabinet  approve Option 2 as set out in paragraph 3.2 of the report to amend the Our Work, Your City (OWYC), logistic and furniture, fittings and equipment order date to after the handover certificate (practical completion) is agreed;  grant delegated authority the Assistant Chief Executive and/or Executive Director of Place, following consultation with the appropriate Cabinet Members(s) to deal with any consequential effects of changes to the OWYC Programme;  approve the use of the contingency budget to fund any additional legal costs in 2015/16;  note the progress of the OWYC Programme;  note the appointment of Taylor Wessing and external experts.

Page 1 Options Considered

3.1Option 1 – to continue to plan the, logistics and furniture, fittings and equipment on the basis of a provisional practical completion and building handover date(s). This approach would see orders placed prior to practical completion and the occupation programme commenced approximately 3 weeks after building handover. In light of the circumstances described in paragraph 4.2 of the report there is a risk that the council may face additional storage costs which cannot at this stage be quantified.

3.2Option 2 – to align the Programme and plan the, logistic and furniture, fittings and equipment to coincide with and commence after Practical Completion to avoid any potential storage costs. The occupation programme will now commence 8 to 12 weeks after Practical Completion.

Reason for Decision - how the proposal supports the Mandate for Change  Make Stoke-on-Trent the place to bring business  Support and develop existing business  Work with people to promote independence and healthy lives  Make Stoke-on-Trent a great city to live in X  An effective and confident council X

Other Implications to be taken into consideration: Legal There are no direct legal implications arising out of this report.

Financial The OWYC budget includes a range of professional services such as procurement and legal support. The unforeseen legal costs described in paragraph 4.3 of the report can be met from the 2014/15 OWYC budget. Any further costs will have to be met from the council’s contingency budget in 2015/16.

Human Resources Staff locations will be subject to consultation with Trade Unions and employees. Human Resource protocols will need to be followed where this also involves staffing reductions, different opening hours, and any equality and diversity issues. Human Resources are contributing to the other initiatives mentioned in this paper, such as Agile Working; Asset Rationalisation etc. and as such are working with the project teams across the City Council

Equality Impact / None directly produced by this report, but the consultation Human Rights recommended will seek to highlight any relevant matters considerations for later consideration.

Page 2 Public Health None produced by this report.

Environmental None directly produced by this report. Impact

Public Services None directly produced by this report. (Social Value) Act 2012

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Our Work, Your City ProgrammeReport 7 pages DownloadRead as text

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open