Stoke-on-Trent City Council
Cabinet, Tuesday 6 October 2015 at 1.00pm

Spode Works – Enabling Works (Notice of Decisions Ref: 584)

Approved Executive 1 paper

Cabinet approved this item on Tuesday 6 October 2015. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

That Cabinet recommend that City Council approve an increase of £1,665,000 to the 2015/16 to 2019/20 Capital Programme. 2. Cabinet request that the revenue budget to fund the borrowing costs of the scheme (between £86,000 - £92,000) and the revenue funding to undertake the work to the rose garden and preparatory work for the development site (£112,000) are incorporated into the 2016/17 – 2020/21 Medium Term Financial Strategy. 3. That the Executive Director (Place) in consultation with the Cabinet Member for Regeneration, Transport and Heritage be authorised to implement the programme of works described in the report, including submitting and obtaining the necessary permissions to do the works and obtain consent for appropriate uses, plus enter into associated contracts and agreements to deliver the various packages of work. 4. That the Executive Director (Place) in consultation with the Cabinet Member for Regeneration, Transport and Heritage undertake further work into the potential and cost benefits of letting the Elenora Street Warehouses and Building 8A in the medium term and, if this should prove beneficial, agree as to whether to proceed with demolition or implement short term lets, in which case any initial costs to be taken from the proposed capital allocation. 5. That the Executive Director (Place) be given the authority to sell, and/or dispose of, the moulds on the site that are considered not worthy of retention.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 14 pages

Open Report

Cabinet

06 October 2015

Spode Works – Enabling Works

Report of Executive Director - Place Contact officer(s) Joanne Tyzzer, Assistant Director (Regeneration, Planning and Development) Peter Thompson, Development Programme Manager Type of Decision Executive Key Decision (Notice of Decisions Ref: 584) Cabinet Member Councillor Jack Brereton - Cabinet Member for Regeneration, Transport and Heritage Wards Affected Penkhull and Stoke

What is the report about? How will it fit with the Council’s priorities? 1.1 The report seeks approval for £1,777,000 of capital and revenue expenditure on infrastructure and building works with the Spode site. The works will primarily involve the provision of infrastructure to assist with the development of the Spode Works site, the demolition of buildings at the eastern end of the site, refurbishment of the buildings around the front courtyard, external repairs to the former Directors Block and some small scale building/repair work.

1.2The proposed works will :  Help progress the regeneration of this important site, by removing some of the development constraints.  Assist in bringing vacant historic buildings on the site back into use, in particular those around the historic entrance courtyard.  Externally refurbish the former Directors Block, stopping further deterioration of a building judged to be of high heritage significance  Reduce the City Council’s annual holding costs for the site and provide the opportunity to generate rental income.

1.3The overall development of the site will create jobs, secure investment, bring back historic buildings back into use and support regeneration of Stoke Town centre.

Report Page 1 Version 8 : 21/09/2015 What are we recommending? 2.1 That Cabinet recommend that City Council approve an increase of £1,665,000 to the 2015/16 to 2019/20 Capital Programme.

2.2Cabinet request that the revenue budget to fund the borrowing costs of the scheme (between £86,000 - £92,000) and the revenue funding to undertake the work to the rose garden and preparatory work for the development site (£112,000) are incorporated into the 2016/17 – 2020/21 Medium Term Financial Strategy.

2.3That the Executive Director (Place) in consultation with the Cabinet Member for Regeneration, Transport and Heritage be authorised to implement the programme of works described in the report, including submitting and obtaining the necessary permissions to do the works and obtain consent for appropriate uses, plus enter into associated contracts and agreements to deliver the various packages of work.

2.4That the Executive Director (Place) in consultation with the Cabinet Member for Regeneration, Transport and Heritage undertake further work into the potential and cost benefits of letting the Elenora Street Warehouses and Building 8A in the medium term and, if this should prove beneficial, agree as to whether to proceed with demolition or implement short term lets, in which case any initial costs to be taken from the proposed capital allocation.

2.5That the Executive Director (Place) be given the authority to sell, and/or dispose of, the moulds on the site that are considered not worthy of retention.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Spode Works: Enabling Works (Notice of Decisions Ref: 584)Decisions 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stoke-on-Trent

Search all
  1. Spode Works – Enabling Works (Notice of Decisions Ref: 584)This decision
  2. Appointment of Capital and Centric as Development Partner for the Spode Works site (Notice of Decisions Ref: 2268)Agreed
  3. Spode Works : Conservation Management PlanApproved
  4. Creative Village - Former Spode WorksApproved

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies