That Cabinet recommend to City Council that the capital programme is amended to include the additional £5m in respect of preventative/reactive maintenance on the City’s unclassified pavements and roads. 2. That Cabinet grant delegated authority to the Executive Director (Place) in consultation with the Cabinet Member for Regeneration, Transport and Heritage to approve the schemes as appropriate giving consideration to the priorities established within the Local Transport Plan (LTP3).
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Report of Executive Director - Place Contact officer(s) Barry Brockbank – Assistant Director (Operational Management) Malcolm Dawson, Strategic Manager (Roads and Engineering) Type of Decision Executive Key Decision (Notice of Decisions Ref:588) Cabinet Member Councillor Jack Brereton - Cabinet Member for Regeneration, Transport and Heritage Wards Affected All Wards
What is the report about? How will it fit with the Council’s priorities? 1.1 The report seeks approval to invest an additional £5m in respect of preventative/reactive maintenance on the City’s unclassified pavements and roads towards the end of financial year 2015/16 and up to the end of the 2019/20 financial year. The works enabled by the investment will be broadly targeted in residential areas on Non-Principal roads and footways (i.e., on the roads where most residents live).
1.2This investment will support the policy aspirations contained within the Local Transport Plan (LTP3), of supporting the economy, and improving the environment in the City.
What are we recommending? 2.1 That Cabinet recommend to City Council that the capital programme is amended to include the additional £5m in respect of preventative/reactive maintenance on the City’s unclassified pavements and roads.
2.2That Cabinet grant delegated authority to the Executive Director (Place) in consultation with the Cabinet Member for Regeneration, Transport and Heritage to approve the schemes as appropriate giving consideration to the priorities established within the Local Transport Plan (LTP3). How much will it cost and how will it be paid for? 3.1 The total expenditure to be incurred is £5 million, which is due to be spent in line with the profile in the table below.
Financial Year Amount
£’000
2015/16 300
2016/17 3,950
2017/18 250
2018/19 250
2019/20 250
TOTAL 5,000
This will be funded from Treasury Management savings in 2015/16, the release of the Transformation reserve and bad debt over-provision in 2016/17 and Treasury Management savings for the remaining three years.
When are we doing it? 4.1 The works programme will commence once approval has been granted and staff have been appointed. It is anticipated that works will be completed by 31st March 2020.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.