194 principal councils228,996 meetings since 20002.8 million official papers archivedStraight from each council's own publication system
Sep14Wednesday
Planning Committee - Development Management
Stoke-on-TrentHeldPapers from moderngov.stoke.gov.uk
Wednesday 14 September 2016, 10.00amHeld 3721 days ago.
Civic CentreGlebe Street, Stoke-on-Trent. Open to the public.
5 items, 3 papersAbout 1.8 MB, led by Installation of fifty standby diesel powered generator sets and associated equipment (including fuel storage tanks and 3m high compound security fencing) for the generation of Short Term Operating Reserve (STOR) electricity of up to 20MW fo.
No exempt items listedEvery item is due to be heard in public.
What the committee will consider, in order, with every paper attached to its item.
30
Procedure
Apologies for absence
31
Procedure
Disclosure of Interests
32
Report
Construction and operation of an emergency standby electricity generation facility, comprising diesel generators, electricity transformers, fuel tanks, combined control and switch room, welfare unit, CCTV poles, and acoustic fencing and gat
es at Land adjacent Outclough Farm, Chatterley Whitfield, Stoke-on-Trent, ST6 8UW (58734/FUL) View the declarations of interest for item 32.
ReportConstruction and operation of an emergency standby electricity generation facility, comprising diesel generators, electricity transformers, fuel tanks, combined control and switch room, welfare unit, CCTV poles, and acoustic fencing and gates at Land adjacent Outclough Farm, Chatterley Whitfield, St675 KBDownload
33
Report
Installation of fifty standby diesel powered generator sets and associated equipment (including fuel storage tanks and 3m high compound security fencing) for the generation of Short Term Operating Reserve (STOR) electricity of up to 20MW fo
r the local distribution network at Land adjacent Chatterley Whitfield Enterprise Centre, Stoke-on-Trent, ST6 8UW (59709/FUL) View the declarations of interest for item 33.
ReportInstallation of fifty standby diesel powered generator sets and associated equipment (including fuel storage tanks and 3m high compound security fencing) for the generation of Short Term Operating Reserve (STOR) electricity of up to 20MW for the local distribution network at Land adjacent Chatterley783 KBDownload
All 3 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
PaperSizeOur copy
Construction and operation of an emergency standby electricity generation facility, comprising diesel generators, electricity transformers, fuel tanks, combined control and switch room, welfare unit, CCTV poles, and acoustic fencing and gates at Land adjacent Outclough Farm, Chatterley Whitfield, StItem 32, Construction and operation of an emergency standby electricity generation facility, comprising diesel generators, electricity transformers, fuel tanks, combined control and switch room, welfare unit, CCTV poles, and acoustic fencing and gat
Installation of fifty standby diesel powered generator sets and associated equipment (including fuel storage tanks and 3m high compound security fencing) for the generation of Short Term Operating Reserve (STOR) electricity of up to 20MW for the local distribution network at Land adjacent ChatterleyItem 33, Installation of fifty standby diesel powered generator sets and associated equipment (including fuel storage tanks and 3m high compound security fencing) for the generation of Short Term Operating Reserve (STOR) electricity of up to 20MW fo
The committee last met on 17 August 2016. 1 of its items lead into this meeting; 2 items are new. Point at any item to follow a thread. Procedural items are left out.
Partial change of use of ground floor from dwelling to retail unit within Use Class A1, new shopfront and alteration to first floor window on front elevation at 18 Snow Hill, Shelton, Stoke-on-Trent, ST1 4LT (59968/FUL)View the declarations of interest for item 20.
21
Installation of two radar towers for testing and demonstration of radar systems at Unit 1, Jubilee Business Unit, off Ivy House Road, Stoke-on-Trent, ST1 3NW (59785/FUL)View the declarations of interest for item 21.
22
Proposed extension to the Etruria Marl workings to the south and west of permitted working area, including ancillary works, landscaping and the restoration of the site to nature conservation following completion of the workings at Land at Copshurst Quarry, Lightwood Road, Longton, Stoke-on-Trent (58703/FUL)
32
Construction and operation of an emergency standby electricity generation facility, comprising diesel generators, electricity transformers, fuel tanks, combined control and switch room, welfare unit, CCTV poles, and acoustic fencing and gates at Land adjacent Outclough Farm, Chatterley Whitfield...
33
Installation of fifty standby diesel powered generator sets and associated equipment (including fuel storage tanks and 3m high compound security fencing) for the generation of Short Term Operating Reserve (STOR) electricity of up to 20MW foNew this time
34
Proposed Changes to the Planning Code of ConductNew this time
The threads
Installation of two radar towers for testing and demonstration of radar systems at Unit 1, Jubilee Business Unit, off Ivy House Road, Stoke-on-Trent, ST1 3NW (59785/FUL) leads to item 32, Construction and operation of an emergency standby electricity generation facility, comprising diesel generators, electricity transformers, fuel tanks, combined control and switch room, welfare unit, CCTV poles, and acoustic fencing and gat
Not carried over
Partial change of use of ground floor from dwelling to retail unit within Use Class A1, new shopfront and alteration to first floor window on front elevation at 18 Snow Hill, Shelton, Stoke-on-Trent, ST1 4LT (59968/FUL), Proposed extension to the Etruria Marl workings to the south and west of permitted working area, including ancillary works, landscaping and the restoration of the site to nature conservation following completion of the workings at Land at C do not return this time.
Follow the Planning Committee - Development Management
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
What should we tell you?
Stoke-on-Trent, Planning Committee - Development Management
Planning Committee - Development Management: 3 kinds of updateStoke-on-Trent, sent the same day
PDF
3 papers published for 14 SeptemberInstallation of fifty standby diesel powered generator sets and associated equipment (including fuel storage tanks and 3m high compound security fencing) for the generation of Short Term Operating Reserve (STOR) electricity of up to 20MW fo and 2 more papers
DAT
Meeting dates updatedAny date added, moved or dropped
DEC
Decisions from 14 SeptemberThe committee's resolutions, the day they are recorded
ABC
"installation" found in 1 paperInstallation of fifty standby diesel powered generator sets and associated equipment (including fuel storage tanks and 3m high compound security fencing) for the generation of Short Term Operating Reserve (STOR) electricity of up to 20MW for the local distribution network at Land adjacent Chatterley
Each update links to the paper and the council's own copy
// POST to your endpoint, signed, the moment it happens
{
"event": "papers.published",
"council": "stoke-on-trent",
"committee": "Planning Committee - Development Management",
"meeting": "2016-09-14",
"papers": 3,
"items": 5,
"source": "moderngov.stoke.gov.uk"
}
Free: one weekly alert. Pro: every option, the same day. Pro Plus: straight into your own systems.
PlanProPrice£99 per user a monthStartsToday, full access straight away
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.