Renewal of Corporate Gas Contract (Notice of Decisions Ref: 655)

Approved Executive 1 paper

Cabinet approved this item on Tuesday 17 January 2017. Below is the council's own wording, with the papers it was decided on.

Item122

Resolved

That Cabinet approve option 1 to utilise the Yorkshire Purchasing Organisation (YPO) Gas Framework Agreement for the supply of gas to City Council establishments for the period 1 st April 2017 to 31 st March 2021. 2. That Cabinet give approval to entering into a contract with the agreed future options under the Framework Agreement with the appointed supplier Corona Energy. 3. That Cabinet give approval approval for the Yorkshire Purchasing Organisation (YPO) to purchase gas under that contract on behalf of the City Council using a flexible purchasing approach.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 6 pages

Open Report

Cabinet

17th January 2017

Renewal of Corporate Gas Contract

Report of Acting Director of Place, Growth and Prosperity Contact officer(s) David Hughes - Assistant Director - Investment, Planning & Regeneration Theresa Bill – Category Manager – Corporate Procurement Andrew Briggs – Client Manager Energy Type of Decision Executive Key Decision – Notice of Decisions Ref: 655 Cabinet Member Councillor Terry Follows – Cabinet Member for Greener City, Development and Leisure Wards Affected No Ward Implications

What is the report about? How will it fit with the Council’s priorities? 1.1 The purpose of the report is to obtain approval for the City Council to utilise the Yorkshire Purchasing Organisation (YPO) Gas Framework Agreement for the supply of gas to City Council establishments for the period 1st April 2017 to 31st March 2021 and to enter into a contract under the Framework Agreement with the appointed supplier Corona Energy.

1.2The utilisation of the Yorkshire Purchasing Organisation Gas Framework Agreement supports the strategic priority of:  A commercial council, well governed and fit for purpose, driving efficiency in everything we do.

1.3Whilst the utilisation of the Yorkshire Purchasing Organisation (YPO) Gas Framework will provide an immediate solution to ensure cost effective gas supply, the City Council will continue to develop concurrently, alternative energy options that will be brought on line during the life of the Framework. Negotiations took place with the YPO to try and build flexibility into the Corona Energy contract to ensure that these alternative energy options can be utilised at the appropriate time. See Section 5.4.

Page 1 Version 2 : 13/12/16 What are we recommending? 2.1 That Cabinet approve to utilise the Yorkshire Purchasing Organisation (YPO) Gas Framework Agreement for the supply of gas to City Council establishments for the period 1st April 2017 to 31st March 2021.

2.2That Cabinet approve to enter into a contract with the agreed future options under the Framework Agreement with the appointed supplier Corona Energy.

2.3That Cabinet approval for the Yorkshire Purchasing Organisation (YPO) to purchase gas under that contract on behalf of the City Council using a flexible purchasing approach.

How much will it cost and how will it be paid for? 3.1 The City Council’s anticipated spend on gas in 2016/2017 is £823k based on a consumption of 31,636,934 kilowatt hours (kWh). This covers a portfolio of 128 meter points over 108 sites under the corporate gas contract. All commercial and residential gas supplies and supplies under a PFI (i.e., Schools and Bentilee District Centre) are managed separately. The cost of the gas is met from the budgets of the individual ordering establishments. 3.2 The YPO are estimating an overall reduction of 14% on current pricing from the start of the new framework in April 2017, but this will depend on the gas trades prior to delivery (under the flexible purchasing approach detailed in paragraph 3.3). This should achieve the following saving:

Total Cost (including Gas Consumption management fee) (Annual Quantity)

2016/17 31,636,934 £ 823,428 2017/18 31,636,934 £ 708,148 Saving £ 115,279

Whilst this represents a 14% saving overall, the management fee element will reduce by some 68.29% under the new framework from the current level of 0.07p per kilowatt hour (kWh) to 0.0222p per kilowatt hour (kWh).

3.3The YPO operates a flexible purchasing approach under the gas framework agreement. Flexible purchasing means buying the annual requirement for gas in regular amounts in advance over a period of time. This enables purchases to be timed to avoid unusual market price spikes and also spreads the risk of price fluctuations. It does not guarantee that all energy is purchased at the lowest possible price available during a particular period but experience during the

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Renewal of Corporate Gas Contract (Notice of Decisions Ref: 655)Decisions 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stoke-on-Trent

Search all
  1. Renewal of Corporate Gas Contract (Notice of Decisions Ref: 655)This decision
  2. Renewal of Corporate Electricity Contract (Notice of Decisions Ref: 429)Approved
  3. Renewal of Corporate Gas ContractApproved
  4. IT System - PSe (Human Resources and Payroll Corporate System)(Renewal of Contractual Arrangements for PSe System)Agreed

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies