New Sheltered Housing Provision (Notice of Decisions Ref: 694)

Approved Executive 1 paper

Cabinet approved this item on Tuesday 4 April 2017. Below is the council's own wording, with the papers it was decided on.

Item158

Resolved

That Cabinet approves the proposal to demolish the sheltered scheme on Queen Elizabeth II Court and re-develop the site into a new scheme, (QEII), which would deliver 57 sheltered flats with communal facilities, subject to planning consent 2. That Cabinet approves the proposed rent and service charge calculations and the principles under-pinning them. 3. That cabinet delegates the authority, to Director of Housing and Customer Services, in consultation with the Cabinet Member for Housing, Communities and Safer City to:- · Review and accept Homes & Communities Agency (HCA) grant, allocated to the Council, and conditions thereof. · Review and accept necessary minor amendments to the proposed rent and service charge. · Review the accept the principle and detail of the Enhanced Housing Management service. · Authorise the expenditure, of grant allocated, to meet part of the overall capital cost of the QEII new-build replacement scheme. · To use Housing Revenue Account Capital to meet the balance of the cost of the new build programme within agreed parameters, as set out in 3.1 of this report
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 18 pages

Open Report

Cabinet

04 April 2017

New Sheltered Housing Provision

Report of Director of Housing and Customer Services Contact officer(s) Philip Brundrett Type of Decision Executive Key Decision - Notice of Decisions Ref: 694 Cabinet Member Councillor Randolph Conteh - Cabinet Member for Housing, Communities and Safer City Wards Affected Fenton West and Mount Pleasant What is the report about? How will it fit with the Council’s priorities? 1.1 The purpose of this report is to update Cabinet on the progress made around re-developing Queen Elizabeth II Court Sheltered Housing Scheme and set out the recommendation for future investment.

1.2The Stronger Together Strategic Plan sets out the following priorities:

 Support our residents to their full potential.  Support our businesses to thrive, delivering investment in our towns and communities.  Work with residents to make our towns and communities great places to live.  A commercial Council, well governed and fit for purpose, driving efficiency in everything we do.  Support vulnerable people in our communities to live their lives well.

To deliver on these priorities, this proposal supports the following City Council’s objectives :

 Work with residents to make our towns and communities great places to live.  Support vulnerable people in our communities to live their lives well.  A commercial Council, well governed and fit for purpose, driving efficiency in everything we do.

Report Page 1 What are we recommending? 2.1 That Cabinet approves the proposal to demolish the sheltered scheme on Queen Elizabeth II Court and re-develop the site into a new scheme, (QEII), which would deliver 57 sheltered flats with communal facilities, subject to planning consent

2.2That Cabinet approves the proposed rent and service charge calculations and the principles under-pinning them.

2.3That cabinet delegates the authority, to Director of Housing and Customer Services, in consultation with the Cabinet Member for Housing, Communities and Safer City to:-  Review and accept Homes & Communities Agency (HCA) grant, allocated to the Council, and conditions thereof.

 Review and accept necessary minor amendments to the proposed rent and service charge.

 Review the accept the principle and detail of the Enhanced Housing Management service.

 Authorise the expenditure, of grant allocated, to meet part of the overall capital cost of the QEII new-build replacement scheme.

 To use Housing Revenue Account Capital to meet the balance of the cost of the new build programme within agreed parameters, as set out in 3.1 of this report

How much will it cost and how will it be paid for? 3.1 The estimated total scheme cost, for the demolition and re-development of QEII with 57 new-build flats with communal facilities, is circa £8.7 million which compares favourably when benchmarked against industry standards.

It will be paid for by:-

 £2,565,000 grant allocation from the HCA  £6,135,000 from the Housing Revenue Account

Professional valuation advice has been commissioned and the scenarios financially appraised using the industry standard ProVal development appraisal software. It provides us with the crucial information to forecast the long term cash flow, value and likely returns from the proposed investment. These Financial viability appraisals have demonstrated that the scheme will pay back in 39 years. The building decant on the building is nearing completion and many units

Report Page 2 have been empty for a significant period of time. As a result of this, the HRA are incurring costs as detailed in the below table.

Rent Council Tax Total New (monthly) Homes Bonus (one off payment) QEII – Current building – 33 Units Loss to date (from date of void up until £65,290 £18,985 £85,275 23/2/17)

Future projected monthly loss £8,573 £2,624 £11,197

Re-developed QEII – 57 Units Projected £23,170 £4,660 £27,830 £48,000 income

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Sheltered Housing Provision (Notice of Decisions Ref: 694)Decisions 18 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stoke-on-Trent

Search all
  1. New Sheltered Housing Provision (Notice of Decisions Ref: 694)This decision
  2. Options for the Future of Newpak Sheltered Business (Forward Plan Item 269)Decided

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies