Agreed ( i ) - That it be noted that as at the end of December 2017 the net forecast overspend is £0.564 million. Agreed (ii) - That action plans continue to be developed to manage the residual risks in order to minimise the impact on this and future years. Agreed (iii) - That the progress against 2017/18 General Fund saving proposals be noted. Agreed ( iv ) - That the position on the strategic contingency be noted. Agreed (v) - That the position on the Dedicated Schools Grant (DSG) be noted. Agreed ( vi ) - That the forecast outturn on the Housing Revenue Account be noted. Agreed (vii) - That the forecast outturn on the Capital Investment Programme be noted. N.B. This item is for information only and therefore not subject to call-in.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Report of Cabinet Member for Finance and Partnerships Report Author Nick Edmonds, Assistant Director – Finance Kerry Cartlidge, Strategic Manager – Corporate Finance Type of Decision For Information Wards Affected All Wards Stronger Together Priorities and how they are applicable: A commercial council, well governed and fit for purpose, driving efficiency in everything we do The budget is set based on delivering the city council’s priorities. This report summarises the financial position on the General Fund, Housing Revenue Account and Capital Investment Programme as at the end of December 2017 and provides forecasts for the financial year ended 31 March 2018.
1.0Purpose of Report: 1.1 To summarise the financial position of the General Fund, Housing Revenue Account and Capital Investment Programme as at the end of December 2017. 1.2 To highlight risks and mitigating actions. 1.3 To summarise the position of the 2017/18 saving proposals. 1.4 To summarise the position of the 2017/18 strategic contingency.
2.0Recommendation(s): 2.1 That it be noted that as at the end of December 2017 the net forecast overspend is £0.564 million. 2.2 That action plans continue to be developed to manage the residual risks in order to minimise the impact on this and future years. 2.3 That the progress against 2017/18 General Fund saving proposals be noted. 2.4 That the position on the strategic contingency be noted. 2.5 That the position on the Dedicated Schools Grant (DSG) be noted. 2.6 That the forecast outturn on the Housing Revenue Account be noted. 2.7 That the forecast outturn on the Capital Investment Programme be noted. 3.0 Summary of Main Points: 3.1 The General Fund Revenue Account has a net expenditure budget of £208 million (gross expenditure £542 million; gross income £334 million). Current risks of £24.333 million have been identified and mitigating actions have been instigated resulting in a residual risk of £0.564 million. The detail is shown at Appendix A. It is essential that all risks are managed and that robust plans are monitored to reduce the impact on this and future years. 3.2 Savings of £22.803 million were included in the budget. As at December 2017 it is forecast that £1.726 million are at risk. A detailed list showing the progress made against each of the saving proposals is shown at Appendix A, Annex A. 3.3 As at the end of December 2017 there was an uncommitted balance of £3.0 million in the strategic contingency. Details of commitments during the quarter against the contingency are shown at Appendix A. 3.4 The Local Authority receives £206.607 million of Dedicated Schools Grant (DSG) of which £28.970 million is within the High Needs Block. In 2017/18 the DSG reserve carried forward is £0.670 million which is committed to the school readiness programme, leaving no additional funding for the High Needs Block. As at December 2017 an unmitigated pressure of £6.2 million is forecast. Discussions are being held to determine the appropriate plan of action to manage this. Further details are shown in Appendix A. 3.5 The Housing Revenue Account (HRA) is forecasting a balanced budget for 2017/18. Further details are shown in Appendix A, Annex B. 3.6 The council is forecasting to invest £81.104 million in capital schemes during 2017/18. The key achievements can be found in Appendix A, and details in Appendix A, Annex C. Technical Appendix: List of Background papers/sources of information used for this report: Medium Term Financial Strategy 2017/18-2019/20 – City Council 23 February 2017 HRA Rent Setting Report 2017/18 – City Council 26 January 2017 List the appendices included as part of this report: Appendix A – Financial Performance Report 2017/18 as at the end of December 2017 (Month 9)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.