Agreed (i) - That Members note the content of the new Procurement Bill 2022-23, and welcome the opportunity to re-draft the City Council’s Contract Procedure Rules and to prepare a new Procurement Strategy once the Bill has received Royal Assent; Agreed (ii) - That Members approve the publication of the City Council’s initial Procurement Pipeline, which forms Appendix 2 to this report.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
PROCUREMENT BILL 2023: Summary of Provisions as they are likely to impact on the City Council
Introduction This Appendix is intended to give a brief summary of the main provisions of the Procurement Bill 2023 as they are likely to affect the City Council. They are correct as of the end of January 2023. Please note that some of these provisions could change prior to the Bill receiving Royal Assent (estimated timeline for which is April/May 2023). Most of the principles of existing regulations have been retained albeit with some differences (transparency, equal treatment, non-discrimination and proportionality). The notes below therefore focus on where there have been changes from existing regulations. The majority of the provisions (except where stated) relate to procurements with a value over a threshold set by Government. The thresholds change annually or bi-annually but currently are as follows: Goods and Services - £213,477 Light-touch Services (largely social care, health, education) - £633,540 Works (largely through the Capital Programme) - £5,336,937 The above thresholds include any VAT which is applicable.
Summary Provisions 1. Coverage. The Bill will replace not only the Public Contract Regulations 2015, but also a number of associated pieces of legislation including legislation relating to Concessions, Utilities and other commercial activities undertaken by the public sector.
2. Supporting SMEs and VCSE Organisations. The Bill introduces a number of measures to remove barriers SMEs face in bidding for, and securing, public sector contracts. This includes allowing smaller suppliers to provide alternative evidence where the audited accounts are not available, and to only put the required insurance cover in place when a contract is awarded to them, rather than incurring the costs upfront In addition the Bill will place a duty on local authorities to consider ways of removing or reducing any barriers faced by SMEs and VCSE Organisations from bidding [NB The City Council has been implementing these objectives for some time, e.g. by only insisting that minimum insurance levels are purchased following award of contract; and by replacing its previous e-Procurement platform with a simpler, more streamlined equivalent].
3. Enabling local authorities to “buy local”. One of the main barriers preventing the City Council from reserving lower value contracts for local suppliers is not actually procurement legislation, but Section 17 (1) of the Local Government Act 1988 and other legislation covering issues such as state aids/subsidies. Government has announced its intention committed to publish secondary legislation to effectively amend this section. In theory this may allow the Council to reserve below threshold contracts for local suppliers but this remains to be confirmed;
4. Transparency. Ensuring that public procurement is transparent is a key theme of the new legislation, and the Council will be required to undertake considerably more work to ensure compliance. This will take a number of forms. Firstly, the City Council will be obliged to publish an annual Procurement Pipeline notice (of all contracts during the forthcoming 18 months with an estimated value £5M+); secondly, certain contracts awarded will have to be published on the Council’s website (although some commercial in confidence data can be redacted); thirdly more detailed feedback to unsuccessful bidders; fourth, a contract implementation notice to update on performance against KPIs (see below); fifth the publication of a contract change notice in advance of implementing amendments; and sixth a contract termination notice ahead of the expiry or termination of a contract; and finally there are certain requirements around Transparency Notices and Market engagement for which we are still awaiting detail.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.