Agreed ( i ) That Cabinet grant approval to extend the current contract (contract ref: PGP/2019/727 ) to the current Service Provider (Galliford Try) until 04 November 2024. Agreed (ii) - That Cabinet approves commencement of a procurement exercise in accordance with the corporate procurement strategy to replace the existing Term Contract Minor Works with a new framework agreement for highways, landscape and civil engineering permitting third party use for a period of four years from appointment in late 2024. Agreed (iii) - That Cabinet grant delegated authority to the Director of Housing, Development and Growth Directorate in consultation with the Cabinet Member for City Pride, Enforcement and Sustainability to determine the award of any subsequent contract.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
1.1That Cabinet grant approval to extend the current contract (contract ref: PGP/2019/727) to the current Service Provider (Galliford Try) until 04 November 2024.
1.2That Cabinet approves commencement of a procurement exercise in accordance with the corporate procurement strategy to replace the existing Term Contract Minor Works with a new framework agreement for highways, landscape and civil engineering permitting third party use for a period of four years from appointment in late 2024.
1.3That Cabinet grant delegated authority to the Director of Housing, Development and Growth Directorate in consultation with the Cabinet Member for City Pride, Enforcement and Sustainability to determine the award of any subsequent contract.
2.0Background and Introduction
2.1Approval is sought to extend the current contract and given the value of the potential works to be awarded, the amount of expenditure will be in the region of £2m. This extension is necessary to ensure schemes currently at design stage or where the contractor is engaged on an Early Contractor Involvement basis can be taken forward to successful implementation.
2.2A new contract for a further period of four years is necessary to allow future transport schemes funded via the Bus Service Improvement Plan, Transforming Cities Fund, Active Travel Fund, Local Transport Plan. The value of these works is anticipated to be £18m.
2.3The Department of Transport have announced additional funding via Local Transport Fund (Network North), which gives additional emphasis in procuring the new contract. 2.4 With the overall value of potential works being in excess of the current Find a Tender procurement threshold of £5,312,609, which has replaced Official Journal of the European Union (OJEU) process, a compliant procurement exercise will be undertaken.
3.0Report Details
3.1Works issued under the Term Contract Minor Works (“the contract”) falls into three main categories:-
Highway and bridge improvement works utilising grant funding.
Individual works contracts funded by various sources, e.g., City Council Capital Programme; Transforming Cities Fund; Levelling Up; Bus Service Improvement Plan and other programmes. No work is guaranteed, nor guaranteed to a specific contractor as it would at the discretion of the responsible programme lead to determine the optimal procurement route.
Works contracts commissioned by eligible third-party organisations within the Stoke-on- Trent and North Staffordshire area as outlined in the contract Prior Information Notice (PIN), which could include Newcastle-under-Lyme Borough Council, Staffordshire Moorlands District Council, Staffordshire and Keele Universities, Local Colleges, Staffordshire Fire and Rescue Service, Staffordshire Police and the University Hospital of North Staffordshire.
Therefore, the value of ‘core’ works in 1) above is estimated to be approximately £8m. The value of the potential works in 2) above to be issued under this contract is estimated to be £10m. The estimated value of works in 3) above is estimated to be £2m. This gives a total potential contract value of approximately £20m over the contract period.
The total value of works anticipated is the combination of works to be delivered via the extension of the current contract and new contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.