Agreed ( i ) - To authorise the Corporate Director of Housing, Regeneration and Operations to secure maximum grant funding from Historic England to deliver a programme of repairs to both Burslem Indoor Market and the Wedgwood Institute. Agreed (ii) - To authorise the match funding from Schools Capital Programme funding for Wedgwood Institute only if grant funding from Historic England is secured. Agreed (iii) - That, subject to receipt of grant funding from Historic England, approval is given to begin a procurement exercise to identify a contractor to undertake refurbishment works to the roof and external envelope of Burslem Indoor Market. Agreed (iv) - That approval is given to begin a procurement exercise to identify a contractor to undertake safeguarding works to the Wedgwood Institute. Agreed (v) - That approval to appoint the preferred contractors resulting from the procurement exercises referred to in (iii) and (iv) above, is delegated to the Corporate Director of Housing, Regeneration and Operations in consultation with the Cabinet Member for Transport, Infrastructure and Regeneration. Agreed (vi) - That, subject to receipt of grant funding from Historic England and confirmation of Schools Capital Programme funds, approval is given to begin a procurement exercise to identify a contractor to undertake refurbishment works to the ground floor of the Wedgwood Institute for an education provider. Agreed (vii) - That approval to appoint the preferred contractors resulting from the procurement exercise referred to in (vi) above, is delegated to the Corporate Director of Children and Families, in consultation with the Corporate Director of Housing, Regeneration & Operations and the Cabinet Member for Education and Anti-poverty as appropriate.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Burslem Indoor Market and Wedgwood Institute Emergency Works and Refurbishment
Report of Corporate Director of Housing, Regeneration and Operations - Carol Gibbs Cabinet Member for Transport, Infrastructure and Regeneration
Purpose of Report To obtain approval to procure contractors to undertake refurbishment and safeguarding works to Burslem Indoor Market and Wedgwood Institute, subject to successful grant applications to Historic England.
1.0Recommendations 1.1 To authorise the Corporate Director of Housing, Regeneration and Operations to secure maximum grant funding from Historic England to deliver a programme of repairs to both Burslem Indoor Market and the Wedgwood Institute. 1.2 To authorise the match funding from Schools Capital Programme funding for Wedgwood Institute only if grant funding from Historic England is secured. 1.3 That, subject to receipt of grant funding from Historic England, approval is given to begin a procurement exercise to identify a contractor to undertake refurbishment works to the roof and external envelope of Burslem Indoor Market. 1.4 That approval is given to begin a procurement exercise to identify a contractor to undertake safeguarding works to the Wedgwood Institute. 1.5 That approval to appoint the preferred contractors resulting from the procurement exercises referred to in 1.3 and 1.4 above, is delegated to the Corporate Director of Housing, Regeneration and Operations in consultation with the Cabinet Member for Transport, Infrastructure and Regeneration. 1.6 That, subject to receipt of grant funding from Historic England and confirmation of Schools Capital Programme funds, approval is given to begin a procurement exercise to identify a contractor to undertake refurbishment works to the ground floor of the Wedgwood Institute for an education provider. 1.7 That approval to appoint the preferred contractors resulting from the procurement exercise referred to in 1.6 above, is delegated to the Corporate Director of Children and Families, in consultation with the Corporate Director of Housing, Regeneration & Operations and the Cabinet Member for Education and Anti-poverty as appropriate.
2.0Background and Introduction 2.1 Both Burslem Indoor Market and Wedgwood Institute are in an extremely poor condition and remain prone to further degradation, primarily due to water ingress. There is a need to undertake emergency works that ensure that any further decline in the condition of both properties is halted. 2.2 With regards to the Wedgwood Institute, an education provider is showing strong interest in taking on a lease (initially to the ground floor front rooms) to expand provision that is currently in place at the Burslem School of Art opposite. The rooms require extensive refurbishment work. 2.3 Funds are in place for the emergency works to Wedgwood Institute through Historic England grants and LUP funds and the works are to be done immanently. 2.4 With regards the works to the Indoor Market roof/external envelope and the Wedgwood Institute potential education use, Historic England are encouraging Stoke-on-Trent City Council to submit grant applications towards the costs. However, if successful, the grant funds must be spent by 31 March 2026 with any match funding spent by 31 July 2026. There is therefore a need to expedite City Council procedures hence the need to gain approval to procure the works as a matter of urgency if the grant applications are successful. This will be known in June 2025. 2.5 Stoke-on-Trent City Council can contribute funds towards the roof/external envelope of the Indoor Market through LUP funds and can contribute funds towards the education provision of the Wedgwood Institute through the Schools Capital Programme
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.