Proposal to Appoint Contractors to Deliver a Major Refurbishment Programme to Two Council-Owned High Rise Apartment Blocks (Notice of Decisions Reference: 2383)
AgreedExecutive2 papers
AI summaryStoke-on-Trent Cabinet approves major refurbishment of two 12-storey Hanley high-rise blocks, appointing Novus Property Solutions at £6.086m and AtkinsRéalis at an estimated £0.5m.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedMajor refurbishment of two HRA high-rise blocks
Money£6.086m contractor + £0.5m consultancyNovus appointed, AtkinsRéalis task order
What happens nextContract signing from Tue 07/04/26Mobilisation Thu 02/07/26, construction to Mon 04/12/28
Who it affectsResidents of Westwood and Wellington Courts92 apartments including 16 leasehold
What was decided
Cabinet approved delivery of a major refurbishment programme to two Housing Revenue Account-owned 12-storey residential blocks in Hanley, totalling 92 one and two bed apartments of which 16 are leasehold.
Novus Property Solutions was appointed as principal contractor at a contract value of £6.086m, following a successful mini-tender under the CHIC framework.
A task order with AtkinsRéalis UK Limited under the existing Professional Services Contract, estimated at £0.5m, was approved for consultancy support and to act as Employer's Agent.
Why
The two blocks require a major refurbishment programme; the recommendation was brought forward by the Cabinet Member for Housing, Planning, Improvement and Governance.
Novus was selected after a successful mini-tender under the CHIC framework; AtkinsRéalis will provide consultancy and act as Employer's Agent under the council's existing Professional Services Contract.
What happens next
The Corporate Director of Housing Regeneration and Operations is authorised to enter the necessary contractual agreements with both companies.
The project plan shows contract signing between Tue 07/04/26 and Mon 20/04/26, mobilisation from Thu 02/07/26 to Mon 21/06/27, and construction from Tue 08/06/27 to Mon 04/12/28. Report P2, P3
A Building Safety Regulator Gateway 2 application is part of the programme, with the latest forecast between 24 and 43 weeks. Report P2
The money
£6.086m Contract value for Novus Property Solutions as principal contractor
£0.5m Estimated value of task order to AtkinsRéalis UK Limited for consultancy and Employer's Agent role
Options considered
Chosen: Appoint Novus Property Solutions at £6.086m as principal contractor via CHIC framework mini-tender. Successful mini-tender under the CHIC framework
Chosen: Issue task order to AtkinsRéalis UK Limited at estimated £0.5m for consultancy and Employer's Agent. Use of existing Professional Services Contract
Implications
Financial: Spend of £6.086m on the principal contractor and an estimated £0.5m on professional services will be incurred under HRA arrangements.
Legal: Section 20 notices for leaseholders are part of the timeline, reflecting landlord consultation duties. Report P2
Risk: The programme includes a Building Safety Regulator Gateway 2 application period, forecast at 24 to 43 weeks, and a risk-related standalone mobilisation phase before BSR authorisation. Report P2
Staffing: The Corporate Director of Housing Regeneration and Operations is authorised to sign the contractual agreements.
Who and where
Tenants of the 92 apartments across Westwood Court and Wellington Court, Hanley
Thu 02/07/26 to Mon 21/06/27: Mobilisation including tenant and leaseholder engagement Report P2
Tue 08/06/27 to Mon 04/12/28: Construction phase (78 weeks) Report P2
Plain English for the jargon
CHIC framework: A procurement framework used by the council to tender housing works; Novus was appointed via a mini-tender under it.
HRA (Housing Revenue Account): The ring-fenced account that funds the council's own housing stock and related works.
Employer's Agent: A consultant acting on the council's behalf to manage the contract, certify payments and oversee delivery.
Section 20 notice: A formal landlord consultation notice to leaseholders under the Landlord and Tenant Act 1985 for qualifying works.
Building Safety Regulator Gateway 2: A regulatory approval step for higher-risk building work before construction can proceed on a high-rise residential block.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item169
Resolved
Agreed ( i ) - That Cabinet approves the delivery of a major refurbishment programme to two Housing Revenue Account (HRA) owned 12-storey residential blocks, with a total of 92 apartments (1 and 2 bed) of which 16 are under leasehold ownership. Agreed (ii) - That Cabinet approve: i. the appointment of Novus Property Solutions as the principal contractor at a contract value of £6.086m to deliver all elements of the works following their successful mini-tender under the CHIC framework; and ii. the issue of a task order under the Council’s existing Professional Services Contract estimated at a value of £0.5m with AtkinsRéalis UK Limited to engage them to provide consultancy support for this project and to act as Employer’s Agent. Agreed (iii) - Subject to ( i ) and (ii) above, that Cabinet gives approval to the Corporate Director of Housing Regeneration and Operations, to authorise the necessary contractual agreements with these companies.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Westwood and Wellington Draft - (Incs Building Safety Regulator Application)
ID Name Duration Start Finish % Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Complete S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 0 Master Programme 212.4 wks Mon 23/09/24 Mon 04/12/28 24% 1 Westwood and Wellington Preconstruction 212.4 wks Mon 23/09/24 Mon 04/12/28 24% 2 Completed Preconstruction 13.8 wks Tue 25/03/25 Thu 03/07/25 100% 8 Section 20s and Cabinet Report Timeline 75.4 wks Mon 23/09/24 Thu 02/04/26 62% 9 Procurement Period - Original Works Package 13.2 wks Fri 21/02/25 Thu 29/05/25 100% 20 Phase 1 - Section 20 (Main Works Package) 70.8 wks Mon 23/09/24 Mon 02/03/26 61% 21 Completed 57.8 wks Mon 23/09/24 Tue 18/11/25 100% 30 Delay – Pending confirmation of the fluctuation value and completion of the review meeting prior 5.8 wks Wed 19/11/25 Fri 09/01/26 60% Sec 20 Main Lead in to issuance 31 Section 20 Notice of Estimates - for EWI, Render, Roof, Façade Structural, Cavity Wall 4.2 wks Mon 12/01/26 Mon 09/02/26 0% Sec 20 NOE Insulation Removal And Fill, Window Renewal, Door Renewal to communal, Ventilation works to apartments, external make good etc/enabling (prelims etc) 32 Section 20 Notice of Estimates - for OBSERVATION EWI, Render, Roof, Façade Structural, 3 wks Tue 10/02/26 Mon 02/03/26 0% Sec 20 NOE Cavity Wall Insulation Removal And Fill, Window Renewal, Door Renewal to communal, Ventilation works to apartments, external make good etc/enabling (prelims etc) 33 Phase 2 - Accelerated Works Section 20 (Lift Renewal) 37 wks Fri 04/07/25 Thu 02/04/26 48% 34 Completed 20 wks Fri 04/07/25 Fri 21/11/25 100% 43 Period of Pricing - Lifts Only 4 wks Mon 24/11/25 Fri 19/12/25 65% Lift Tender Prep 44 Overall Lift Procurement and Review Period 6 wks Mon 24/11/25 Thu 15/01/26 45% Procure Lifts 45 Earliest date of which Section 20 Notice of Estimates - for Lifts (30 working Days = 4.2 weeks) 4.2 wks Fri 16/01/26 Fri 13/02/26 0% Sec 20 NOE
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Proposal to Appoint Contractors to Deliver a Major Refurbishment Programme to Two Council-Owned High Rise Apartment Blocks (Notice of Decisions Reference: 2383)Decisions
169Proposal to Appoint Contractors to Deliver a Major Refurbishment Programme to Two Council-Owned High Rise Apartment Blocks (Notice of Decisions Reference: 2383)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.