Cabinet, Tuesday 24 March 2026 at 1.00pm

Proposal to Appoint Contractors to Deliver a Major Refurbishment Programme to Two Council-Owned High Rise Apartment Blocks (Notice of Decisions Reference: 2383)

Agreed Executive 2 papers

AI summaryStoke-on-Trent Cabinet approves major refurbishment of two 12-storey Hanley high-rise blocks, appointing Novus Property Solutions at £6.086m and AtkinsRéalis at an estimated £0.5m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedMajor refurbishment of two HRA high-rise blocks
Money£6.086m contractor + £0.5m consultancyNovus appointed, AtkinsRéalis task order
What happens nextContract signing from Tue 07/04/26Mobilisation Thu 02/07/26, construction to Mon 04/12/28
Who it affectsResidents of Westwood and Wellington Courts92 apartments including 16 leasehold

What was decided

Cabinet approved delivery of a major refurbishment programme to two Housing Revenue Account-owned 12-storey residential blocks in Hanley, totalling 92 one and two bed apartments of which 16 are leasehold.

Novus Property Solutions was appointed as principal contractor at a contract value of £6.086m, following a successful mini-tender under the CHIC framework.

A task order with AtkinsRéalis UK Limited under the existing Professional Services Contract, estimated at £0.5m, was approved for consultancy support and to act as Employer's Agent.

Why

The two blocks require a major refurbishment programme; the recommendation was brought forward by the Cabinet Member for Housing, Planning, Improvement and Governance.

Novus was selected after a successful mini-tender under the CHIC framework; AtkinsRéalis will provide consultancy and act as Employer's Agent under the council's existing Professional Services Contract.

What happens next

The Corporate Director of Housing Regeneration and Operations is authorised to enter the necessary contractual agreements with both companies.

The project plan shows contract signing between Tue 07/04/26 and Mon 20/04/26, mobilisation from Thu 02/07/26 to Mon 21/06/27, and construction from Tue 08/06/27 to Mon 04/12/28. Report P2, P3

A Building Safety Regulator Gateway 2 application is part of the programme, with the latest forecast between 24 and 43 weeks. Report P2

The money

  • £6.086m Contract value for Novus Property Solutions as principal contractor
  • £0.5m Estimated value of task order to AtkinsRéalis UK Limited for consultancy and Employer's Agent role

Options considered

  • Chosen: Appoint Novus Property Solutions at £6.086m as principal contractor via CHIC framework mini-tender. Successful mini-tender under the CHIC framework
  • Chosen: Issue task order to AtkinsRéalis UK Limited at estimated £0.5m for consultancy and Employer's Agent. Use of existing Professional Services Contract

Implications

  • Financial: Spend of £6.086m on the principal contractor and an estimated £0.5m on professional services will be incurred under HRA arrangements.
  • Legal: Section 20 notices for leaseholders are part of the timeline, reflecting landlord consultation duties. Report P2
  • Risk: The programme includes a Building Safety Regulator Gateway 2 application period, forecast at 24 to 43 weeks, and a risk-related standalone mobilisation phase before BSR authorisation. Report P2
  • Staffing: The Corporate Director of Housing Regeneration and Operations is authorised to sign the contractual agreements.

Who and where

  • Tenants of the 92 apartments across Westwood Court and Wellington Court, Hanley
  • 16 leasehold owners within the two blocks
  • Housing Revenue Account as the funding stream

Timeline

  • Mon 23/09/24: Master programme start Report P2
  • Tue 24/03/26: Cabinet meeting Report P2
  • Thu 02/04/26: Permission to sign contract Report P2
  • Tue 07/04/26 to Mon 20/04/26: Contract signing (Gate 7) Report P2
  • Thu 02/07/26 to Mon 21/06/27: Mobilisation including tenant and leaseholder engagement Report P2
  • Tue 08/06/27 to Mon 04/12/28: Construction phase (78 weeks) Report P2

Plain English for the jargon

  • CHIC framework: A procurement framework used by the council to tender housing works; Novus was appointed via a mini-tender under it.
  • HRA (Housing Revenue Account): The ring-fenced account that funds the council's own housing stock and related works.
  • Employer's Agent: A consultant acting on the council's behalf to manage the contract, certify payments and oversee delivery.
  • Section 20 notice: A formal landlord consultation notice to leaseholders under the Landlord and Tenant Act 1985 for qualifying works.
  • Building Safety Regulator Gateway 2: A regulatory approval step for higher-risk building work before construction can proceed on a high-rise residential block.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item169

Resolved

Agreed ( i ) - That Cabinet approves the delivery of a major refurbishment programme to two Housing Revenue Account (HRA) owned 12-storey residential blocks, with a total of 92 apartments (1 and 2 bed) of which 16 are under leasehold ownership. Agreed (ii) - That Cabinet approve: i. the appointment of Novus Property Solutions as the principal contractor at a contract value of £6.086m to deliver all elements of the works following their successful mini-tender under the CHIC framework; and ii. the issue of a task order under the Council’s existing Professional Services Contract estimated at a value of £0.5m with AtkinsRéalis UK Limited to engage them to provide consultancy support for this project and to act as Employer’s Agent. Agreed (iii) - Subject to ( i ) and (ii) above, that Cabinet gives approval to the Corporate Director of Housing Regeneration and Operations, to authorise the necessary contractual agreements with these companies.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 1 pages

Westwood and Wellington Draft - (Incs Building Safety Regulator Application)

ID Name Duration Start Finish % Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Complete S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 0 Master Programme 212.4 wks Mon 23/09/24 Mon 04/12/28 24% 1 Westwood and Wellington Preconstruction 212.4 wks Mon 23/09/24 Mon 04/12/28 24% 2 Completed Preconstruction 13.8 wks Tue 25/03/25 Thu 03/07/25 100% 8 Section 20s and Cabinet Report Timeline 75.4 wks Mon 23/09/24 Thu 02/04/26 62% 9 Procurement Period - Original Works Package 13.2 wks Fri 21/02/25 Thu 29/05/25 100% 20 Phase 1 - Section 20 (Main Works Package) 70.8 wks Mon 23/09/24 Mon 02/03/26 61% 21 Completed 57.8 wks Mon 23/09/24 Tue 18/11/25 100% 30 Delay – Pending confirmation of the fluctuation value and completion of the review meeting prior 5.8 wks Wed 19/11/25 Fri 09/01/26 60% Sec 20 Main Lead in to issuance 31 Section 20 Notice of Estimates - for EWI, Render, Roof, Façade Structural, Cavity Wall 4.2 wks Mon 12/01/26 Mon 09/02/26 0% Sec 20 NOE Insulation Removal And Fill, Window Renewal, Door Renewal to communal, Ventilation works to apartments, external make good etc/enabling (prelims etc) 32 Section 20 Notice of Estimates - for OBSERVATION EWI, Render, Roof, Façade Structural, 3 wks Tue 10/02/26 Mon 02/03/26 0% Sec 20 NOE Cavity Wall Insulation Removal And Fill, Window Renewal, Door Renewal to communal, Ventilation works to apartments, external make good etc/enabling (prelims etc) 33 Phase 2 - Accelerated Works Section 20 (Lift Renewal) 37 wks Fri 04/07/25 Thu 02/04/26 48% 34 Completed 20 wks Fri 04/07/25 Fri 21/11/25 100% 43 Period of Pricing - Lifts Only 4 wks Mon 24/11/25 Fri 19/12/25 65% Lift Tender Prep 44 Overall Lift Procurement and Review Period 6 wks Mon 24/11/25 Thu 15/01/26 45% Procure Lifts 45 Earliest date of which Section 20 Notice of Estimates - for Lifts (30 working Days = 4.2 weeks) 4.2 wks Fri 16/01/26 Fri 13/02/26 0% Sec 20 NOE

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App. 3 Project Plan: IndicativeReport 1 pages DownloadRead as text
PDF
Proposal to Appoint Contractors to Deliver a Major Refurbishment Programme to Two Council-Owned High Rise Apartment Blocks (Notice of Decisions Reference: 2383)Decisions 7 pages Download

At this meeting

Whole meeting
156Minutes of Last Meeting (17/2/24 and 24/2/26)On the agenda 161Corporate Measures - Quarter 3 2025/26Agreed 162Statutory Biodiversity Report (Notice of Decisions Reference: 2384)Agreed 163Improving Education Strategy 2025-2030 (Notice of Decisions Reference: 2323)Agreed 164Youth Strategy (Notice of Decisions Reference: 2302)Agreed 165Annual Review of the Management of Risk PolicyAgreed 166Housing Renewal Assistance Policy - commissioning a specialist loans provider (Notice of Decisions Reference: 2382)Agreed 167Proposed Extension to the Current Seven Separate Call off Agreements for Materials Supply via the Communities and Housing Investment Consortium Limited (CHIC Ltd) Framework in Support of the Delivery of Repairs and Maintenance in Respect ofAgreed 168Proposed establishment of Two Contract Frameworks; One for Replacing External Doors and Associated Canopies and Cladding and One for Aids and Adaptations Internal and External Alterations (Notice of Decisions Reference: 2373)Agreed
169Proposal to Appoint Contractors to Deliver a Major Refurbishment Programme to Two Council-Owned High Rise Apartment Blocks (Notice of Decisions Reference: 2383)This decision
170To Obtain Delegated Authority to Procure and Award Contracts for All Major Projects and Routine Sourcing of Materials to Enable Service Delivery (Notice of Decisions Reference: 2390)Agreed 1712026-29 Local Transport Settlement and Local Transport Delivery Plan (Notice of Decisions Reference: 2369)Agreed 172Declaration of Council owned Surplus Sites (Notice of Decisions Reference: 2368)Agreed 173Draft Masterplan for Packmoor for approval and public consultation (Notice of Decisions Reference: 2347)Agreed 175Review of City Catering ServicePrivate

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies