Demolition of Bell House and Barker House (Notice of Decisions Reference: 2395)
AgreedExecutive1 paper
AI summaryCabinet approved a £0.410m increase to the HRA Capital Programme to demolish Bell House and Barker House in the Blurton ward, taking the total demolition budget to £1.274m for 2026/27.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDelegated authority granted to the housing director
Money£0.410m HRA increase, £1.274m totalFunded from sale of council housing capital receipts
What happens nextProcure demolition and professional servicesContracts to be awarded via compliant procurement
Who it affectsBlurton ward, council housing tenantsLeasehold buyouts and decant compensation included
What was decided
Cabinet approved the budget for demolishing Bell House and Barker House once the processes at section 3.2 of the report are complete.
Cabinet approved a £0.410m increase to the HRA Capital Programme and approved procurement of all required works and services through a compliant process. Report P1
Cabinet delegated authority to the Corporate Director of Housing, Regeneration and Operations, in consultation with the relevant cabinet member, to implement the decisions.
Why
Bell House and Barker House are decommissioned housing blocks identified for demolition as part of work to address low quality stock and high levels of anti-social behaviour. Report P12
The 2026/27 HRA Capital Programme already included £0.300m for vacant possession and decommissioning, and a £0.314m underspend from 2025/26 has been carried forward, but extra funding is needed. Report P1
What happens next
The Corporate Director of Housing, Regeneration and Operations will procure and award contracts for demolition works and professional services.
All leasehold interests and other interests on the site must be terminated before demolition, with legal support used to prepare the necessary documents. Report 7.2
Cabinet noted potential future options for the site as set out at section 3.5 of the report.
The money
£0.410m Proposed increase to HRA Capital Programme for demolition and decant compensation Report P1
£0.300m Existing 2026/27 HRA provision for vacant possession, decommissioning and security Report P1
£0.314m Underspend from 2025/26 carried forward into 2026/27 Report P1
£0.614m Total HRA budget for 2026/27 before the proposed increase Report P1
£1.274m Total HRA budget for 2026/27 after the proposed increase Report P1
Options considered
Chosen: Approve the demolition budget, HRA increase, procurement and delegated authority. Needed to progress demolition of the decommissioned blocks and use available capital receipts Report P1
Implications
Financial: The £0.410m increase is funded from usable capital receipts from council housing sales, so there is no extra impact on capital financing costs. Report P2
Financial: Holding costs will continue until the blocks are demolished; some may fall under revenue and be met from existing revenue budgets. Report P2
Legal: The council must follow procurement law and its procurement code, terminate all interests before demolition, and use legal support to prepare documentation. Report 7.2
Equalities: No Equality Impact Assessment is required and the proposals do not affect social inequalities, poverty, social exclusion or health. Report 8.2, 8.3
Climate: Demolition plans will consider dust suppression and sustainability; any future new build will aim for Biodiversity Net Gain. Report 8.4
Staffing: No human resources implications identified. Report 8.1
Who and where
Residents and leaseholders of Bell House and Barker House, Blurton ward Report P10, P1
Council housing tenants across the city (through use of capital receipts from council housing sales) Report P2
The local community in the Blurton ward, through rebalancing of the area and potential future new build homes Report P12
Timeline
2026/27: HRA Capital Programme to which the £0.410m increase applies, taking the total to £1.274m Report P1
2025/26: Underspend of £0.314m carried forward into 2026/27 Report P1
Plain English for the jargon
HRA: Housing Revenue Account, the ring-fenced account that holds income and spending on council housing.
Capital receipts: Money raised from the sale of council assets such as council houses, which can be used to fund new capital spending.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
Agreed ( i ) – That Cabinet approve the budget for the demolition of Bell House and Barker House following completion of processes as detailed within the report at 3.2. Agreed (ii) – That Cabinet approve the HRA Capital Programme increase by £0.410m as detailed within the report submitted. Agreed (iii) – That Cabinet approve the procurement, and award of contracts via a compliant procurement process for all works and professional services required. Agreed (iv) – That Cabinet approve the granting of delegated authority to the Corporate Director of Housing, Regeneration and Operations in consultation with the Cabinet Member for Safe and Resilient Communities and Housing to take all necessary actions to implement the above recommendations. Agreed (v) – That Cabinet note the potential options for the future of the site, as set out at 3.5 of the report submitted.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Report of Corporate Director of Housing, Regeneration and Operations - Carol Gibbs Cabinet Member for Safe and Resilient Communities and Housing
Purpose of Report The purpose of this report is to seek approval for the demolition of Housing Revenue Account Assets at Bell House and Barker House, following decommissioning of the blocks.
1.0Recommendations Cabinet approve: 1.1 The budget for the demolition of Bell House and Barker House following completion of processes as detailed within the report at 3.2. 1.2 The HRA Capital Programme is increased by £0.410m as detailed within the report 1.3 The procurement, and award of contracts via a compliant procurement process for all works and professional services required. 1.4 The granting of delegated authority to the Corporate Director of Housing, Regeneration and Operations in consultation with the Cabinet Member for Safe and Resilient Communities and Housing to take all necessary actions to implement the above recommendations.
Cabinet note: 1.5 The potential options for the future of the site, as set out at 3.5 of the report.
2.0Background and Introduction 2.1 Bell House and Barker House are both three storey blocks located on one site, constructed in the 1950’s with a total of 60 bedsit style flats. A stock grading exercise to inform the Housing Revenue Account (HRA) Asset Management Strategy evidenced that both Bell House and Barker House were the lowest asset grade available. There are also twenty two lock-up garages that sit within the curtilage of the site, in varying condition, with just half of them let. 2.2 As such, in April 2025 (NOD ref: 2287), Cabinet approved the decommissioning of Bell House and Barker House and subsequently work has been ongoing to obtain vacant possession of the site, including; the purchase of leasehold properties, cessation of garage agreements and rehousing of council tenants. Approval was also given at that time for the preferred option to dispose of the site to a third party Registered Provider for development of affordable housing. 2.3 However, the third party Registered Provider has since withdrawn their interest in the purchase and redevelopment of the site. No further interest has been registered. 3.0 Report Details 3.1 At the time of writing, the remaining leasehold property owners have agreed terms to voluntarily sell their properties to the Council and have instructed lawyers to conduct the conveyancing. There is one remaining Council tenant who is being supported to consider their options for alternative accommodation and legal advice is being taken on options for obtaining possession of the property. The Council should therefore shortly have vacant possession of the site. Whilst the future of the site is under consideration (see 3.5), it is recommended to progress the demolition of the blocks, in order to reduce the holding costs and potential security problems associated with empty buildings.
Budget and Costs 3.2 The estimated costs for the demolition have been prepared by internal teams and are forecast at £710,271. This includes a contingency of 30% for unforeseen costs. A copy of the full estimate, can be found at appendix A.
Element Estimated Cost Demolition Costs £523,285.97 Contingency at 30% £156,985.79 Professional fees (internal management) £30,000 Total £710,271.76
3.3The budget for this is identified and will be expended from the HRA Capital programme. 3.4 The procurement, and award of contracts for all works and professional services required to undertake the demolition would be conducted via a compliant procurement process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.