Procurement of an E-Bike Hire Scheme for Stoke-on-Trent (Notice of Decisions Reference: 2454)

Agreed Executive 1 paper

AI summaryCabinet approved procurement of an e-bike hire scheme for Stoke-on-Trent, with a fleet of around 800 to 1,000 e-bikes run by an external operator under a five-year concession worth about £5 million. The scheme could launch in spring or summer 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedConcession-style model with external operator
Moneyapproximately £5 millionEstimated total contract value to operator over five years
What happens nextLaunch spring or summer 2027Procurement process to commence during 2026
Who it affectsAll wards in Stoke-on-TrentResidents, visitors and the city transport network

What was decided

Cabinet approved running a competitive procurement exercise for an e-bike hire scheme for the city. Report 1.0

Cabinet supported a concession-style delivery model, with the appointed operator responsible for provision, operation and maintenance. Report 1.0

Authority was delegated to the Corporate Director of Housing, Regeneration and Operations, in consultation with the Cabinet Member for Transport, Infrastructure, Planning and Regeneration, to run the procurement, award and mobilise the contract. Report 1.0

Why

Officers want to widen sustainable, accessible and affordable transport choices, particularly for short journeys, and support decarbonisation, air quality and public health objectives. Report 2.0

E-bikes are seen as a practical way to overcome Stoke-on-Trent's topography, perceived travel time and accessibility barriers, making cycling more inclusive. Report 2.0

A concession model is judged to give the best balance of control, accountability and risk transfer, while offering the chance of a revenue stream for the Council. Report 3.0

What happens next

Officers will commence the competitive procurement process during 2026, in line with the Procurement Act 2023 and the Council's Procurement Code. Report 3.0

Further market engagement will inform the final specification, including trials of e-bike models in local conditions. Report 3.0

Subject to procurement and any regulatory approvals, the scheme is expected to launch in spring or summer 2027. Report 3.0

The money

  • approximately £5 million Estimated total contract value or opportunity to the operator over the five-year contract term Report 8.1
  • £5,193,000 Current VAT inclusive threshold for a services concession contract under the Procurement Act 2023 Report 8.2

Options considered

  • Chosen: Concession-style delivery model with an appointed operator. Provides the most appropriate balance of control, accountability and risk transfer, with the potential for Council income. Report 3.0
  • Rejected: Operator permit or licensing model. Would give less control over service standards, fleet size, coverage, performance management and data sharing. Report 7.0
  • Rejected: Memorandum of Understanding with an operator. Would offer limited contractual protection and insufficient enforcement of service standards or data sharing. Report 7.0
  • Rejected: Property leasing of highway or Council land. Could generate income but would not give sufficient control over operational performance, user experience, data or coverage. Report 7.0
  • Rejected: Do nothing. Would not support the Council's transport, environmental, public health or economic objectives. Report 7.0

Implications

  • Financial: The Council is not providing an ongoing subsidy; its contribution is mainly officer time for procurement, contract management and any Traffic Regulation Orders. Income from a revenue-sharing or concession arrangement is expected to offset Council costs. Report 8.1
  • Legal: The contract is likely to be a services concession under the Procurement Act 2023. The Council must also meet highways duties under the Highways Act 1980, the Traffic Management Act 2004, road traffic regulation requirements, and consider TUPE on expiry of the concession. Report 8.2, P15, P17
  • Equalities: An Equality Impact Assessment screening found no significant adverse impacts; accessibility, digital inclusion and user safety will be built into the contract. Footway obstructions that could affect wheelchairs and pushchairs will need ongoing attention. Report 9.2, 9.3, P18
  • Climate: The scheme is expected to support modal shift from cars, reducing congestion, improving air quality and cutting greenhouse gas emissions, with lower energy use than equivalent private vehicle journeys. Report 9.4
  • Risk: Key risks include procurement or approval delays, weak market response, underperformance by the operator, inappropriate parking or anti-social behaviour, lower than forecast demand, and negative media coverage linked to illegal e-bikes. Report 5.0
  • Staffing: The report states no direct human resources implications for the Council, but the Council will need to consider the Transfer of Undertakings (Protection of Employment) Regulations 2006 on expiry of the concession. Report 9.1, P17

Who and where

  • All wards across Stoke-on-Trent Report P24
  • Residents and visitors seeking short-distance transport options Report 2.0
  • Households and individuals without access to a private vehicle Report 9.3, P26
  • Pedestrians, wheelchair users, people with visual impairments, and those with pushchairs or mobility aids Report 3.0, P18
  • Town centres, transport hubs, employment sites and visitor attractions as key destinations Report 3.0

Timeline

  • Tuesday, 11 August 2026: Cabinet decision to approve procurement of an e-bike hire scheme Report P2
  • During 2026: Officers to commence the competitive procurement process Report 3.0
  • Spring or summer 2027: Anticipated launch of the e-bike hire scheme, subject to procurement and regulatory approvals Report 3.0
  • Five years: Proposed length of the concession contract with the appointed operator Report 8.1

Plain English for the jargon

  • E-bike: Electrically assisted bicycle, which the rider still has to pedal but with motor assistance.
  • Concession-style delivery model: Arrangement where an external operator provides, operates and maintains the service, with the Council setting standards and oversight.
  • Traffic Regulation Order (TRO): Legal order under the Road Traffic Regulation Act 1984 used to control or restrict traffic on a road.
  • Geo-fencing: Use of location technology to define virtual boundaries, here used to control where e-bikes may be parked or ridden.
  • TUPE: Transfer of Undertakings (Protection of Employment) Regulations 2006, which can transfer staff when a service changes provider.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item50

Resolved

Agreed (i) - That Cabinet approve the procurement of an e-bike hire scheme for Stoke-on-Trent through a competitive procurement exercise. Agreed (ii) - That Cabinet support a concession-style delivery model, whereby the appointed operator will be responsible for the provision, operation and maintenance of the e-bike hire scheme. Agreed (iii) - That Cabinet delegate authority to the Corporate Director of Housing, Regeneration and Operations, in consultation with the Cabinet Member for Transport, Infrastructure, Planning and Regeneration, to undertake the procurement process and take all necessary actions to progress the procurement, award and mobilise the contract to deliver an e-bike hire service in Stoke-on-Trent.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet

Cabinet

Tuesday, 11 August 2026

Open

Procurement of an E-Bike Hire Scheme for Stoke-on-Trent

Report of Corporate Director of Housing, Regeneration and Operations - Carol Gibbs Cabinet Member for Transport, Infrastructure, Planning and Regeneration

Purpose of Report To seek Cabinet approval to undertake a competitive procurement exercise to appoint an operator to deliver, manage and maintain an e-bike hire scheme in Stoke-on-Trent and to delegate authority to award the subsequent contract.

1.0Recommendations 1.1 That Cabinet approve the procurement of an e-bike hire scheme for Stoke-on-Trent through a competitive procurement exercise. 1.2 That Cabinet support a concession-style delivery model, whereby the appointed operator will be responsible for the provision, operation and maintenance of the e-bike hire scheme. 1.3 That Cabinet delegate authority to the Corporate Director of Housing, Regeneration and Operations, in consultation with the Cabinet Member for Transport, Infrastructure, Planning and Regeneration, to undertake the procurement process and take all necessary actions to progress the procurement, award and mobilise the contract to deliver an e-bike hire service in Stoke-on-Trent.

2.0Background and Introduction 2.1 Stoke-on-Trent City Council is seeking to provide residents and visitors with a wider range of sustainable, accessible and affordable transport choices, particularly for short journeys. Encouraging more active travel supports local and national policy objectives relating to decarbonisation, air quality improvement and public health outcomes. 2.2 A significant proportion of car trips are short in length, national evidence indicates that c.70% of car journeys are under five miles, and c.25% are less than one mile, and 60%+ of car journeys have no passengers. Many of these trips could be actively travelled, if convenient, reliable and attractive options are made available, releasing the capacity on the road network for critical users. 2.3 In Stoke-on-Trent, factors such as topography, perceived travel time, and accessibility barriers can limit the uptake of traditional cycling. Electrically assisted bicycles (e-bikes) offer a practical solution to these challenges by reducing physical effort, extending feasible travel distances, and making cycling more inclusive for a broader range of users, including those with lower fitness levels or mobility constraints. 2.4 The introduction of an e-bike hire scheme presents an opportunity to address these barriers and support modal shift by:  Providing a flexible and convenient alternative to private car use for short trips  Enhancing connectivity between key destinations, including town centres, transport hubs, employment sites and visitor attractions  Supporting first- and last-mile journeys as part of integrated transport networks  Contributing to improvements in air quality and reductions in carbon emissions  Promoting healthier, more active lifestyles 2.5 By offering a publicly accessible e-bike hire scheme, the Council aims to create a step- change in how people move around the city, supporting a more sustainable, inclusive and efficient local transport system.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of an E-Bike Hire Scheme for Stoke-on-Trent (Notice of Decisions Reference: 2454)Decisions 185 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 21 attended
JH
Julie HarveySecretary, expected
JA
Councillor Jane Ashworth OBEChair, present
AW
Councillor Amjid Wazir OBECabinet Member, apologies
SJ
Councillor Sarah Jane ColcloughCabinet Member, apologies
FG
Councillor Finlay Gordon-McCuskerCabinet Member, apologies
SH
Councillor Sarah HillCabinet Member, present
MK
Councillor Majid KhanCabinet Member, present
DW
Councillor Duncan WalkerCabinet Member, present
LW
Councillor Lynn WatkinsCabinet Member, present
LD
Councillor Lauren DavisonCabinet Support Member, apologies
WA
Councillor Waseem AkbarCabinet Support Member, in attendance
CR
Councillor Chris RobinsonCabinet Support Member, in attendance

All 21 on the meeting page

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies