AGREED: That the report be received. Environmental Services The Head of Environmental Services updated the Committee on the current position in relation to the Waste Management contract specification. In addition Members raised a number of issues, which included; · Grass cutting arrangements · Tip restrictions to farmers · Licensing – notification to parish councils AGREED: That the report be received. Planning Services Members were informed that the Urban Design Framework had been agreed by the Executive and was being referred to Council for adoption. An update was given on the planning restructure. Members noted the success of the parish council training. AGREED: That the report be received. Resources AGREED: That the report be received. World Class Stratford AGREED: That the report be received It was requested that Paul Ogden (Project Leader) be asked to provide Members with an Information Sheet updating members on funding issues in relation to the Challenge Years
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
ITEM NO: 2A OVERVIEW & SCRUTINY COMMITTEE B DATE:4 JULY 2007 ENVIRONMENT SERVICES QUARTERLY REPORT
Service Plan High Level Actions High Level Action Targets or Outcome 2005/06 2006/07 2007/08 2008/09 Lead Officer Decision Supporting Task Maker Corporate Strategy Aim 1 HLA5 Identify Improved the health N/A Resource N/A N/A Head of Approval by resource and well being of the review by Environment Executive implications of new community through August 2006 licensing, greater enforcement of Report to Health & Safety, statutory duties Exec. by Food Safety September Requirements and 2006 the Housing Act 2004. Milestone to 1. Resource review August 2006 Update: Achieved achieve HLA5 2. Report to September Executive 2006 Corrective Action: None
HLA7 Review the Improve performance N/A Review Act To be To be Head of Approval by powers available in in areas such as noise, – May 2006 confirmed confirmed Environment Executive the Clean litter, graffiti, fly as part of Neighbourhood and tipping and dog Agree Plan the service Environment Act control, abandoned by August planning 2005 and plan to vehicles. 2006 process introduce the ones Resource 2007/08 with greatest implications strategic benefit. to be considered as part of
OVERVIEW & SCRUTINY COMMITTEE B 4 JULY 2007 ITEM NO 2A Page 10 ITEM NO: 2A OVERVIEW & SCRUTINY COMMITTEE B DATE:4 JULY 2007 ENVIRONMENT SERVICES QUARTERLY REPORT
Service Plan High Level Actions High Level Action Targets or Outcome 2005/06 2006/07 2007/08 2008/09 Lead Officer Decision Supporting Task Maker budget setting process for 2007-8 Milestone to 1. Review Act May 2006 Update: Act reviewed and achieve HLA7 Action Plan reported to 2. Agree Plan August 2006 Management Team June 2006. 3. Resource October October To be Action Plan amended in light implications to be 2006 2007 confirmed of no additional resources considered as part of made available to deliver budget setting process these new provisions. for 2007-8 Corrective Action: None at this time HLA 8 Re-tender New contract delivers N/A Start April Award Head of Approval by Council’s Street improved refuse, 2006, contract Environment Council Cleaning Contract recycling and street Interim October HLA 12 Review re- cleaning services to agreement 2007 cycling and waste residents of Executive management by August contracts 2006. Final decision on contract and procurement
OVERVIEW & SCRUTINY COMMITTEE B 4 JULY 2007 ITEM NO 2A Page 11 ITEM NO: 2A OVERVIEW & SCRUTINY COMMITTEE B DATE:4 JULY 2007 ENVIRONMENT SERVICES QUARTERLY REPORT
Service Plan High Level Actions High Level Action Targets or Outcome 2005/06 2006/07 2007/08 2008/09 Lead Officer Decision Supporting Task Maker October 2007 Milestone to 1.Begin Process of April 2006 Update: Tender for achieve HLA8 & reviewing new contract consultants help with in- 12 2.Interim agreement of August 2006 house bid completed. Executive OJEU procurement commence 3.Final Decision on 22 Feb 2007. On target for contract and award of October Contract completion by October 2007. Contract 2007 start Corrective Action: None HLA9 Prepare and Improved appearance, N/A Final draft Implement Head of Approval by implement Green accessibility, facilities to Executive actions Environment Council Spaces Strategy and attractions for in from the green spaces. September strategy 2006 Milestone to 1.Final draft of strategy Final draft of Implement Update: Strategy agreed. achieve HLA9 to Executive strategy to strategy No additional resources made September 2006 Executive April 2007 available for implementation 2. Implement actions October from strategy April 2006 Corrective Action: None at 2007 this time High Level Action Targets or Outcome 2005/06 2006/07 2007/08 2008/09 Lead Officer Decision Supporting Task Maker Corporate Strategy Aim 2 HLA 11 Recycle or Increased % of 36% 39% 40% 40% Head of Adopted by
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Committee B at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
Exception Reporting on Service Areas(1) That the report be noted. Planning Services Members felt that the Council needed to have a policy in place to dea...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.