Flooding

Decided Executive 1 paper

Executive decided this item on Tuesday 21 August 2007. Below is the council's own wording, with the papers it was decided on.

Item342

Resolved

That, in respect of the £600,000 funding received from the Government o a payment of £250 be made to every known household affected by the July 2007 flooding; o £50,000 be allocated to meet costs incurred in collecting bulky goods; and o £50,000 be retained as a Contingency Fund. NOTE : This item is subject to call-in to Overview and Scrutiny B. 343. Exclusion of the Public That, pursuant to Section 100A (4) of the Local Government Act 1972 (as amended), the public be excluded from the remaining business of the meeting in view of the fact that the nature of the proceedings will be such that, if the public were present, there would likely be disclosure to them of exempt information under Paragraph 1 of Part I of Schedule 12A to the said Act (as amended).
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to Executive

URGENT ITEM EXECUTIVE DATE: 21 AUGUST 2007 ST

SUBJECT: SUPPORT FOR RESIDENTS FOLLOWING FLOODING JULY 2007 LEAD OFFICER: ROBERT WALSH CONTACT ON 01789 260106

LEAD MEMBER/ PORTFOLIO HOLDER: COUNCILLOR CHRIS WILLIAMS (PORTFOLIO HOLDER FOR COMMUNITY SERVICES)

SUMMARY The Government has committed funds to help residents affected by the recent floods. The report proposes a Residents Recovery Plan to direct the distribution of this grant.

RECOMMENDATION (1) That the Chief Executive, in consultation with the Leader of the Council, determines the support to be made available for each identified activity in the Residents Recovery Plan, subject to the estimated overall expenditure being within the budget available under the flooding recovery grant scheme.

1 INTRODUCTION 1.1 The Department of Communities and Local Government (DCLG) announced on 16th August 2007 funding to help victims of the flooding in June and July 2007. £600,000 (£300,000 capital and £300,000 revenue) was paid into the District Council’s bank on 17th August. This report considers how the Council may choose to use this funding to help victims of the floods across Stratford-on-Avon

2 BACKGROUND 2.1 This Grant is completely separate to the Bellwin scheme which helps local authorities recover their costs in responding to an emergency. It is paid to local authorities to distribute to those residents who need help the most as a result of the floods. Within this general philosophy the Government has announced that “Local authorities will decide how best to spend the money allocated in their communities" though only residents whose homes have been entered by floodwater or sewage as a result of the floods will be eligible for help. 2.2 Officers have provided the DCLG with information on the floods which affected the District 20-22 July 2007. An estimated 2,000 homes will meet the definition for support set by the DCLG.

3 OPTIONS 3.1 The Council needs to respond swiftly following the DCLG announcement. A draft Residents Recovery Plan is attached at Appendix A, and the Executive has the Options of (a) Adopting the Plan as presented; or (b) Adopting an amended version of the Plan. 3.2 The Plan will need to be adjusted to reflect conditions and funding announced by HM Government. Subject to this caveat option (a) is recommended.

4 CONSULTATION 4.1 The policies and plan presented in Appendix A have been developed following consultation with members of the Executive.

5 IMPLICATIONS OF THE PROPOSAL 5.1 Legal – The Civil Contingencies Act 2004 places a legal obligation on the Council to prepare for, and respond to, emergency situations. This includes work on the recovery phase for major emergencies. 5.2 Financial 5.2.1 The £600,000 provided to the Council through the Flood Recovery Scheme Grant was paid into the Council’s bank account on 17th August 2007. 5.3 Environmental 5.3.1 Work to mitigate environmental damage caused by the July 2007 floods is one of the options that can be included in the Residents Recovery Plan. 5.4 Corporate Strategy 5.4.1 Decisions made by the Council on how to distribute the Flood Recovery Scheme Grant may impact on community cohesion. This will affect achievement of Aim 3 of the Corporate Strategy ‘The development of inclusive communities’. 5.5 Human Rights Act and Equality Impact Assessment 5.5.1 The conditions of Grant include that it is targeted at groups most in need of support. This will lead to inequality in provision of funding, but this inequality is considered to be justifiable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FloodingReport 396 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. FloodingThis decision
  2. Notice of Motion - Flooding ReportDeferred

More from Stratford-on-Avon Executive

All decisions
MeetingDecisionOutcome
28 Jul 2008 Service Excellence StatementsRESOLVED : 1) That the progress made in 2007/08 be noted; and, 2) That the updated Statements of Service Excellence a... Noted Open
28 Jul 2008 State of the DistrictThat the foregoing actions in response to the comments made by Council on the report be endorsed. NOTE: This item is ... Decided Open
28 Jul 2008 Request from Audit Committee - Change of NameThat the Executive be renamed as ‘Cabinet’. NOTE: This item is not subject to call-in. Decided Open
28 Jul 2008 Fundamental Budget ReviewRESOLVED : 1) That the proposal to create a Budget Working Group to oversee the Budget Review, as summarised in the p... Approved Open
28 Jul 2008 Interim Procurement Strategy1) That the interim Procurement Strategy 2008 - 2012, as presented, be received and adopted; and, 2) That progress on... Approved Open