Resolved
AGREED: The report was noted.
Overview and Scrutiny Committee B agreed this item on Wednesday 17 October 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED: The report was noted.
OVERVIEW AND SCRUTINY COMMITTEE DATE: 17 OCTOBER 2007
Report of the Members’ Working Group - S106 Agreements 26.9.2007
Councillors Barnes (Chair), Bowring and James plus honorary member Councillor Appleton (Chairman of OSC B)
TERMS OF REFERENCE AND SCOPE
Terms of To consider how the council can ensure that S.106 reference/objectives of agreements regarding planning obligations the Review (a) deliver to the local community the most effective mitigation for development, in an open and transparent way, and (b) are produced in the most efficient way possible to avoid causing delays in the planning process.
Scope To consider 1. The need for a clear and effective policy and process with regard to S.106 agreements so that the reason for the obligation is obvious and developers can work out what would likely be expected of them and when. 2. The need to ensure that income due under s.106 agreements is collected and for Members and officers to be aware of each S.106 agreement and have access to information regarding the commitment agreed, so that they can monitor the delivery and use of funds due. 3. The need to ensure that s.106 agreements are not causing delays in the issue of planning permission.
During the Group’s deliberations it has been supported by SDC officers from the Planning, Legal and Finance teams. It has also been assisted by officers from the Development Group at Warwickshire County Council.
SUMMARY OF KEY FINDINGS AND ACTIONS
A. Monitoring S106 agreements
Key Findings
1. Although considerable information regarding S106 agreements exists within the Council, it is not kept in a comprehensive manner and responsibility for different functions in relation to S106 agreements is split between different Council Services.
2. There are strong concerns that this may lead to failure to collect and/or spend monies owed through S106 agreements. 3. A comprehensive database, administered by a single officer (with appropriate back up) is required. This is the key to improved performance in monitoring.
4. Best practice of other Councils should be followed.
5. The monitoring officer could be based either at SDC or at WCC, who already have a functioning system for monitoring the financial aspects of S106 agreements. WCC would charge £8,000 per year to administer SDC’s S106 financial contributions chase-ups, receipt and reminders to the spending services.
6. The possibility of funding monitoring through S106 contributions should be explored.
7. It would be useful for regular quarterly reports to be made regarding S.106 agreements so that all Members were kept informed of the position.
Actions
8. The acknowledged best practice authority for monitoring S106 agreements is Colchester BC, which has developed a bespoke database. This database has recently been obtained free of charge and an officer has been trained in its use. The database is an excellent tool which, once fully populated and implemented, will enable substantial improvements in the whole S106 monitoring process. It will also make it much easier to supply information about S106 agreements to Members, parish councils and the public.
9. In view of the acquisition of the Colchester database, officers have been progressing the option of S106 monitoring in-house, rather than contract WCC to carry out the work. It was considered that carrying the work out in-house would:
• retain control with SDC and allow closer working with various SDC services; • enable full range of S106 information to be provided to Members and the public; enable monitoring of other, non-monetary S106 issues for information and compliance purposes; and • be more cost effective than contracting WCC to do the work. (cont’d) Comparative costs and benefits of in-house v. WCC monitoring
In-house County Council provided
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Final reports from OSC Task GroupsReport | 5 pages | DownloadRead as text |
Follow Overview and Scrutiny Committee B at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2010 | Focus on - The Future Committee Structure and OSC MeetingsThat the presentation be noted and the Committee’s comments be referred to the Committee Structure Working Group for ... | Noted | Open |
| 24 Mar 2010 | Exception Reporting on Service Areas(1) That the report be noted. Planning Services Members felt that the Council needed to have a policy in place to dea... | Noted | Open |
| 24 Mar 2010 | State of the District Report(1) That the report be noted; (2) That Officers ensure that all previous comments made by the Committee given in Appe... | Noted | Open |
| 24 Mar 2010 | Planning Committee - Update(1) That minutes 336, 483 and 696 be noted. | Noted | Open |
| 24 Mar 2010 | Warwickshire Overview & Scrutiny BoardThat the Warwickshire Overview and Scrutiny Board report of 3 March 2010 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.