(1) That the progress made on the 2009/10 Vision for Southam Projects be noted; and (2) That the 8 applications for funding from the 2010/11 Vision for Southam Budget, as summarised in the preamble to this Minute, be supported at the level of funding indicated.
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
Subject: Vision for Southam Project Funding Lead Officer: Katherine Geddes on 01789 260102 Portfolio Holder: Councillor M Brain
Summary This report provides updated information on the progress of the Vision for Southam projects and suggests funding allocations for the 2010/11 budget of the 2020 Vision Action Plan Recommendation That Committee considers and agrees to the allocation of funds as requested and detailed below.
1 Background/Information 1.1 In its budgets for 2010/11 the Council has allocated £25,000 to be spent in support of the projects identified in the 2020 Vision Action Plan for Southam. This is the third year of Vision funding and the community led Vision for Southam group have delivered on all 2009/10 projects agreed by the East Joint Committee last year and delivery against outcomes for 2009/10 is given below. The group have also identified the projects they wish to be funded in the 2010/11 financial year and their findings are presented here together with requests for the allocation of the identified funds. 1.2 The control and management of these funds will remain with officers of the Council in conformance with standing orders 2 Vision for Southam 2009/10 Projects – Outcomes achieved 2.1 Community Technology Bank Launched October 2008. Outcomes achieved: • Increased number of community groups accessing IT training and skills development. • Increased usage of the Graham Adams Centre as a central community base. • Provision of editorial centre for ‘Town Village Voice’ news-page (news-page advertising upcoming community group developments and events in the surrounding area.) • Improved local awareness of, and attendance at, activities, events and support offered by local community groups. 2.2 Stockton Village Hall Facility Upgrade Completed January 2010. Outcomes achieved: • Increased usage of Stockton Village Hall as a central community base. • Enabled and increased the range of leisure and social activities taking place in a local community setting. • Improved facilities to support financial viability and sustainability of a community hall. • Improved facilities for disabled users 2.3 Park Lane Recreation Ground improvements Completed February 2010. Outcomes achieved: • Provision of a safe and secure recreational facility. • Reduced opportunity and fear of anti-social behaviour by enclosing an area regularly used by young people. • Improved appearance of a local community space. • Removal of opportunities for criminal activities to take place. 2.4 Harbury Village Hall Facility Upgrade Completed March 2010. Outcomes achieved: • Extended opportunities for active recreation by making the hall accessible to all members of the community. • Information and advice services brought closer to the community by providing a facility suitable for staging public and community events in a rural location. • Reduced unnecessary energy consumption. 2.5 Community Café Equipment Completed January 2010. Outcomes achieved: • Provision of a viable community café in a central, accessible community building. • Health and safety requirements met. • Increased the capacity of the café to ensure ongoing sustainability. • Provision of skills and knowledge to young mums on how to prepare healthy meals. • Improved awareness of healthy eating in the community. 3 Financial Implications 3.1 Budget The Council has made available a budget of £25,000 which is to be allocated during 2010/11 and is available in support of the identified agreed projects. There have been no allocations to date and new requests are shown below:-
Applications to be considered for 2010/11 Allocation
Application 1 - Insulation of Stockton village hall roof £1,800
Application 2 - Modernisation of Harbury village hall £2,000
Application 3 - Stockton’s News equipment £5,300
Application 4 – Ufton Cycle Path £3,000
Application 5 – Heritage Project £3,000
Application 6 – Forgotten Southam £1,500
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Public - AgendaThat, pursuant to Section 100A (4) of the Local Government Act 1972 (as amended), the public be excluded from the rem...
Southam to Stockton Cycle Track(1) That the report be noted and the preferred route from Stockton to Southam as outlined by Warwickshire County Coun...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.