That the World Class Stratford 2009/10 Outturn report be noted and that a further report on action to be taken to offset the proposed overspends be reported to a future meeting of The Cabinet. NOTE: This item is not subject to call-in as no decision has been taken other than to note the report
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
Subject: World Class Stratford – Update Report Lead Officer: Paul J Ogden / Andrew Lovegrove Contact on 01789 260611 / 260425 Lead Member/ Portfolio Holder: Councillor J Appleton
Summary To receive and note a report on the World Class Stratford (WCS) Phase 1 programme, for which SDC is the accountable body, reporting on income and expenditure to 31 March 2010 and a financial projection to the end of the project. Recommendation
That the report be noted.
1 Background/Information 1.1 Stratford-on-Avon District Council (SDC) is in contract with Advantage West Midlands (AWM) for Phase 1 of WCS and has various responsibilities as the ‘accountable body’. This report provides details of the income and expenditure in relation to the spending of £5.385m Phase 1 grant from AWM, which, together with capital budgets from Warwickshire County Council (WCC), SDC and other partners, provides combined totals, as summarised below, and detailed in Appendix 1. 1.2 SDC, as the accountable body for Phase 1 of WCS, is responsible for securing ‘match funding’ in the form of ‘other contributions’ to projects. SDC does not have control over expenditure by its partners but WCS is required in its contract with AWM to collate the evidence and report on progress. WCS is on target to achieve these totals.
AWM SDC -WCS Other Total contributions Original bid 4,990,000 1,074,000 1,475,000 7,539,000 Revised AWM Contract 5,385,000 2,682,171 8,067,171 Spend reported to AWM 31 March 2010 4,297,502 1,092,481 779,392 6,169,374 Forecast spend to end of contract 1,087,498 274,114 976,943 2,338,555 Total Forecast to end of contract 5,385,000 1,366,594 1,756,335 8,507,929 1.3 Phase 1 includes budgets for all staff costs, professional services, construction, etc., for completing existing project commitments and the outstanding projects agreed with AWM funded from reallocated Bridge grant. Appendix 2 provides a summary of progress.
2 Options available to the Cabinet 2.1 To note the progress report for WCS or to request further details.
3 Evidence Base 3.1 The bid to AWM included significance evidence of the decline in visitor numbers and decreasing spend by visitors. It also recognised the value of the visitor economy to the District and the Region, prompting AWM to provide the financial backing to the Phase 1 programme.
4 Implications of the proposal 4.1 Legal 4.1.1 SDC is in contract with AWM and is responsible as the accountable body for the WCS Phase 1 activities. 4.2 Financial 4.2.1 Provision for the current and forecast costs to SDC of WCS Phase 1 is included in SDC’s Capital Programme for WCS. 4.2.2 The project has already exceeded the required match funding from the private sector. The remaining public sector funding is anticipated to be met from existing committed capital projects e.g. WCC contributions to the Waterside & Southern Lane scheme. 4.3 Environmental 4.3.1 The environmental impact of each scheme within the programme is considered as each project progresses. 4.4 Corporate Strategy 4.4.1 This project is consistent with Aim 3 of the Corporate Strategy: A District where business and enterprise can flourish – facilitate delivery of the WCS programme. 4.5 Equality Impact Assessment 4.5.1 The schemes will be of benefit to all sectors of the community.
5 Risk assessment 5.1 The risks associated with the Programme are managed via a risk and issues report which is also routinely reported to AWM. At the conclusion of each financial year a statement of expenditure is produced and is subsequently subject to external audit. The first three years of the Phase 1 Programme have all received good audit reports.
6 Conclusion 6.1 The WCS programme is continuing as planned and the progress report should be noted.
Andrew Lovegrove SECTION 151 FFICER Appendix 1
AWM AWM revised Reported Total Variation to Variation to Expenditure: Forecast Bid Contract 31/03/2010 forecast Bid Contract
Bancroft Gardens,Rec Ground&Wayfinding:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.