Planning Services

Decided Scrutiny 1 paper

Overview and Scrutiny Committee decided this item on Wednesday 7 July 2010. Below is the council's own wording, with the papers it was decided on.

Item154

Resolved

That the report be received and the Planning Service be encouraged to progress the points referred to above.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Improving Planning Services using Systems Thinking

Background As part of the Council’s ongoing journey of continuous improvement, and in recognition of the tightening financial constraints on the Council, Systems Thinking is being used as a method to improve quality and reduce costs, thereby achieving greater value for money for customers and citizens.

Systems Thinking is not new but is being promoted through the government’s National Improvement strategy, and part funding has been achieved from the West Midlands Regional Improvement and Efficiency partnership (RIEP) to undertake an intervention in Planning.

What is Systems Thinking? Systems Thinking is a method that looks at the whole process from end to end (the system), from a customer perspective. It seeks to improve the customer experience whilst reducing the amount of waste in the system. It is founded on the premise that the system we work in drives peoples behaviour and that changing the system achieves improvement. It’s about new ways of working and managing too, so that over time sustainable improvement is achieved.

Planning Services The first intervention has been in the Planning service, because Planning underpins most of our Corporate Strategy, has the greatest opportunity for Place Shaping, it touches on most other services in the Council, interfaces with many customers, and is an identified area for improvement in terms of value for money.

Our Planning Staff Say …..

“We have tried changing parts of the planning system before without having the time to fully appreciate the impacts on the system as a whole. As a result, previous changes have often proven unsustainable in the long term. The Systems Thinking approach offers the chance to change things for the better for the long term and this is the first time that I have been convinced that lasting change can be achieved if we see the process through.”

“We have been blindly striving to meet Government targets for too long without realising the effects that this has on officer behaviour and morale. A target driven culture based on dates does not measure the quality of decision making. As a professional planner I want to achieve the best quality development not the fastest decision possible. Reducing the emphasis on meeting target dates and concentrating more on the outcomes of applications should help achieve a better quality environment and foster better relationships with our customers and stakeholders.” Householder applications Receipt Validation Consultation Site Visit Decision

Receipt to Validation was 7.5 days is now 24 hours

Receipt to consultations was 21-32 days now averages 9 days

Validation to Site Visit was a minimum of 42 days now averages 13 days

Validation to Decision (NI) was 62.8% in 09/10 within 56 days is now 78.2%

Receipt to Decision (whole customer experience) was 123 days is now 70 days

Whole Customer Experience

Between May and July 2009 the Planning team undertook a thorough review of the system, which involved detailed analysis of around 200 planning applications:

Waste (work that is of no value or could have been avoided, that uses capacity and therefore has a cost):

1. 50% of planning applications are processed but found to be invalid and have to wait for the customer/agent to do further work;

2. It was taking between 21-32 days to process applications through all the administrative stages and get the consultation process started;

3. As a consequence of trying to achieve government targets (a decision in 8 weeks/56 days) a third of applicants were asked to withdraw their application (often on day 55 or 56) when a decision could not be made within target. When those applications are re-submitted they are processed for a 2nd time, free of charge.

4. Late responses from consultees added to the delay in being able to make a decision within the target time (see 2 above).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Planning ServicesReport 797 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Planning ServicesThis decision
  2. Call-in of decision by the Environmental Services Portfolio Holder on 1 December 2015 - Coventry and Warwickshire Local Enterprise Partnership Planning ProtocolDecided
  3. Call-in of decision by the Environmental Services Portfolio Holder on 1 December 2015 - Coventry and Warwickshire LEP Planning ProtocolDecided
  4. Planning Services – Proposed StructureApproved

More from Stratford-on-Avon Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
28 Oct 2026 Urgent BusinessThat, pursuant to Section 100A (4) of the Local Government Act 1972 (as amended), the public be excluded from the rem... Noted Open
2 Sep 2026 Cost of LivingThat, in principle, a Task and Finish Group on the Cost of Living would be formed at the next meeting of the Overview... Decided Open
2 Sep 2026 Urgent Business - The Three TunsThat, pursuant to Section 100A (4) of the Local Government Act 1972 (as amended), the public be excluded from the rem... Noted Open
27 May 2026 Start time of meetingsThat the meetings of the Overview and Scrutiny Committee during 2026/27 commence at 10.00 a.m. Decided Open
27 May 2026 The Cabinet Meeting - 13 April 2026It was agreed that the Climate Change Project Officer would be asked to provide an assessment of the project. It was ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies