That Planning Application 10/00988/FUL be GRANTED subject to the following conditions: 1. Three year timescale for commencement; 2. Materials to match existing building; 3. No open storage; 4. Contamination condition; 5. Associated standard contamination condition if contamination found during works; 6. Soft landscaping scheme; 7. Energy measures implemented; 8. Surface water scheme; 9. Control over erection of scaffolding near to rail line; 10. No external lighting unless scheme submitted; 11. Ancillary to existing authorised uses on site; 12. Provision of turning space within site.
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
Site Address Station Works, Station Road, Claverdon
Proposals Proposed erection of new storage unit
Presenting Case Officer Dan Charles Jayne Cashmore Officer Audit and Type of Regulation 25 August 2010 Full Planning Application Committee Date
Applicant [name removed] Member(s) Cllr Horner Claverdon Council
Previous Yes, West Area Planning Committee Committee 8 July 2010
Erection of new B8 Storage Unit External footprint of 385m2 Description of Height to ridge of 5.7m Proposals Elevations 13.1m and 29.4m wide External materials are a mixture of grey profile cladding and cedar boarding to match the adjacent building Reason for Referral West Area Planning Committee’s support of an application to Audit and which is contrary to policy (PR.2 – Green Belt) Regulation Green Belt Planning Open Countryside Constraints Substandard access onto the A4189 road Planning History Green Belt Access and highway safety Impact on rural character/landscaping Key Issues Impact on neighbouring uses/amenity Impact on railway line Energy conservation
Recommendation REFUSE REASON FOR REFERRAL TO AUDIT & REGULATION COMMITTEE
Having considered the application and the representations made at the West APC held on 8 July 2010, the Committee, by 4 votes to 5 votes with 1 abstention did not support the officer’s recommendation to refuse the application. In order to refer the application to the Audit and Regulatory Committee for approval the Committee was required to identify very special circumstances to support the application.
The Committee in overturning the Officers recommendation considered there were special circumstances in granting the application, namely,
• Environmental and visual enhancement of the site; • Maximisation of use of previously developed land; • Scale of development is modest in relation to the overall size of the site; • Maintaining commercial viability of an existing local business; • Retention of site as a viable business; • Maintaining employment opportunities in rural parts of the district; and • Retention of existing employment in the local area.
Since the previous committee, I have revisited the site. I saw several large advertising boards erected on the boundaries of the site facing the railway advertising “storage land to let” and “secure yard to let”. In addition, I observed that the existing storage unit contained a large quantity of performance cars. It would therefore appear that the unit is not being used for storage in association with the MCS Group.
On further investigation, one of the buildings on site appears to be used for the sale of motor vehicles under the business name of Castello Cars as well as for use as offices for a business known as Driving Adventures.
The current use of the site therefore does not correspond with the information given by the applicant in the submitted Design and Access statement.
As a consequence, I have requested further information from the applicant as to the exact activities currently being carried out within the site and buildings and the proposed purpose of the new building. These details will be reported on the update sheet.
If the present uses that I witnessed on site are confirmed, it would appear that the business is not local and the proposed new building is not required to support the existing business and local community.
RELEVANT PLANNING HISTORY
Reference Number Proposal Decision and date
10/00251/FUL Erection of new storage unit (B8) Withdrawn 12 April 2010
08/01178/FUL Proposed refurbishment and re- Granted 25 June 2008 cladding of existing workshop building and re-siting of existing building with no increase in floor area
07/02320/FUL Revised over cladding proposal to Granted 16 October 2007 existing building 07/01581/FUL Over cladding existing elevations Granted 18 July 2007
06/03487/FUL Minor changes to existing elevations, Granted 26 February 2007 expansion of internal office space.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit and Regulatory Committee at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
Annual Certification Report 2010/11That the report be noted. Since the meeting, the Head of Business, Housing and Revenues has provided the following ad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.