The Cabinet, Monday 16 January 2012

Environmental Quality and Climate Control Panel

Noted Executive 1 paper

The Cabinet noted this item on Monday 16 January 2012. Below is the council's own wording, with the papers it was decided on.

Item558

Resolved

That the Minutes, as presented, be received and noted. NOTE: This item is not subject to call-in to the OSC
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet

ENVIRONMENTAL QUALITY AND CLIMATE CHANGE PANEL

29 November 2011

Held at Council Chamber, Elizabeth House, Church Street, Stratford-upon-Avon Meeting commenced: 3.00 pm Meeting ended: 4.35 pm

MINUTES

Present: Councillor Mike Gittus (Chairman), Councillors S Adams, M Brain, J Fradgley, S Juned, L Organ and D Wise

Apologies: Councillor Sir William Lawrence Bt Councillor Beverley Mann

Officers in P Chapman, T Perks, R Weeks Attendance:

79. Disclosure of Interests

None were received.

80. Minutes

The minutes of the meeting held on 27 September 2011 were confirmed and signed.

81. Friends of the Earth

The Chairman welcomed Bob Bearman and Dave Passingham from Friends of the Earth to the meeting. They spoke to a paper that was tabled at the meeting and which was entitled “Local Authority and Carbon Reduction Targets”. (See Committee Services for a copy.)

[name removed] highlighted to the Panel that the Government would soon be looking to local government to take firm action in support of meeting ambitious CO2 reduction targets and to signing up to an updated version of the Nottingham Declaration. The Nottingham Declaration was described as being a voluntary pledge by councils to address the issues of climate change and demonstrate their support for action to reduce carbon dioxide emissions from their own activities and those within the community that contribute to climate change.

The Panel agreed that, with all the other pressures that the economy is facing, it would be hard to hold firm to any target set but the Chairman was grateful for the encouragement and forewarning from the Friends of the Earth participants.

The Chairman extended a standing invitation to Messrs Bearman and Passingham to attend all future EQCC Panel meetings.

82. Work Plan

Stratford Visitor and Leisure Centre Boiler Replacement

Tony Perks presented a short paper on this matter (as tabled at the meeting), explaining that the two leisure centre boilers were now due for replacement. The options available were as follows: biomass; solar collectors; combined heat and power; and high efficiency condensing gas boilers. An analysis of each option was given with the high efficiency gas boilers appearing to be the most efficient way of replacing the heating infrastructure of the leisure centre.

After some discussion, the Panel was in agreement with the Officer’s conclusion that high efficiency gas boilers appeared to be the most logical choice and felt an option to add solar collectors (as a supplement to the main system) at a later date would be appropriate. Officers advised that they were keeping this matter under review for the time being and that the boilers were due to be replaced in March 2012.

Elizabeth House Photo Voltaic (PV) Array Installation

Tony Perks updated the Panel on the progress of the PV installation on the roof of Elizabeth House. The matter was currently out for tender with tenders due back by 9 December 2011. Assuming an acceptable tender is submitted, it was anticipated the installation should be in place and operational by mid March 2012.

Some disappointment was expressed that this installation hadn’t been completed in time to benefit from the current feed-in tariff (that was soon to be reduced) although the tariff would still be beneficial to the Council and the community.

The Chairman requested that Officers compile an assessment of other Council properties that might be suitable for similar PV installations and report back to the next meeting.

The Carbon Trust Project

The District Council was taking part in the Carbon Trust Carbon Management Programme which would hopefully provide focus and assistance to the authority in addressing the Corporate Strategy commitment of reducing the Council’s own carbon footprint.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Environmental Quality and Climate Control PanelReport 42 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Environmental Quality and Climate Control PanelThis decision
  2. Local Environmental Quality Enforcement PolicyApproved
  3. Environmental Quality and Climate Change PanelDecided
  4. Environmental Quality and Climate Change Panel - Work ProgrammeApproved
  5. Environmental Quality and Climate Change PanelDecided
  6. Environmental Quality and Climate Change PanelDecided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies