AUDIT COMMITTEE 25 March 2013
Subject: Internal Audit Progress Report Lead Officer: Garry Rollason Contact on 01926 412679 Lead Member/ Portfolio Holder: Councillor P Seccombe
Summary To receive a progress report from Internal Audit. Recommendation That the progress report be noted.
1 Background/Information 1.1 Internal Audit continues to carry out a programme of work in accordance with the approved Audit Plan and this report details progress to date.
2 Progress against the Audit Plan 2.1 Progress to date against the 2012/13 Internal Audit Plan is as follows:
Service Activity Current Status1 Level of Direction assurance Of provided Travel2 by controls Business, Housing benefits Completed * Substantial Housing & Revenues Corporate Performance In progress Support management Customer Information Completed * Limited First audit Access Governance Cash collection Completed * Full and banking Land charges Completed Moderate IT Strategy Scheduled for
1 Audits completed since the previous report to the committee are marked with * 2 This information is given to provide a broad indication of the direction of travel but needs to treated with caution since previous audits have not have comparable scope and opinion ratings were changed in April 2010. Some audits were undertaken in 2012/13 for the first time.
1 Service Activity Current Status1 Level of Direction assurance Of provided Travel2 by controls March
PCI Compliance In progress
Backup and Draft report issued disaster recovery – awaiting comments from Manager Remote access Scheduled for March start Self-service In progress kiosks Environment Section 106 In progress & Planning Development Draft report issued control & – awaiting enforcement comments from Manager Emergency In progress planning Pathlow Completed Moderate Resources Human Completed * Substantial First audit Resources Health and Completed Substantial safety Debtor invoicing In progress Cheque control Completed Moderate First audit Corporate Completed Substantial property Technical Car Parking In progress Services Shopmobilty Completed Moderate First audit Public In progress Conveniences Waste & Completed Moderate recycling (Recycling credits)
2.2The agreed protocol is for audits with a limited opinion (the lowest level) to be reported in detail to the committee. Since the last report to the Committee one audit has resulted in a limited opinion – Information Governance. A copy of this report is attached for information / comment at Appendix A.
2 2.3 In additional to routine assurance work, the workplan includes provision for providing advice on system changes / new developments. This work has focussed on advising on: • changes to processes to address the issues arising from the last car parking audit ,and • procedures for the collection of charges for use of public conveniences.
2.4No investigations into financial irregularities have been required to date this year.
3 Options available to the Committee 3.1 To note the content of the Internal Audit progress report. 4 Implications of the proposal 4.1 Legal/Human Rights Implications 4.1.1 There are no legal or human rights implications of the proposal. 4.2 Financial 4.2.1 There are no financial implications of the proposal. 4.3 Environmental 4.3.1 There are no environmental implications of the proposal. 4.4 Corporate Strategy 4.4.1 There are no corporate strategy implications of the proposal. 4.5 Equality Impact Assessment 4.5.1 There are no Equality Impact Assessment implications of the proposal. 5 Risk Assessment 5.1 There are no risks involved in agreeing/not agreeing the recommendations contained in the report. 6 Conclusion 6.1 That the Internal Audit progress report be noted.
David Buckland ASSISTANT CHIEF EXECUTIVE Background papers: None.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Report: progress updateReport | 44 KB | DownloadRead as text |
PDF |
March Appendix AAppendix | 130 KB | Download |
Follow Audit Committee at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2015 | Internal Audit Report - progress updateThat the 2014/15 Internal Audit Plan progress report be noted. | Noted | Open |
| 23 Mar 2015 | Annual Certification Report 2013/14That the Annual Certification Report for 2013/14, incorporating Appendices A and B, be noted. | Noted | Open |
| 23 Mar 2015 | PricewaterhouseCoopers External Audit Plan 2014/15That the External Audit Plan for 2014/15, as presented, be received and adopted. At this point of the meeting, the Ch... | Approved | Open |
| 23 Mar 2015 | Scale of Fees for District and Town/Parish ElectionsThat the scale of fees attached as Appendices to these Minutes be approved, subject to the Chief Executive continuing... | Approved | Open |
| 12 Jan 2015 | Internal Audit Report - progress updateThat the report, as presented, be received and noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.