That Planning Application 14/00262/OUT be REFUSED for the following reasons (the detailed wording of which be delegated to Officers): 1. The proposed development will result in additional traffic movements that are considered to require mitigation measures via off-site highway improvements on the local highway network. A scheme (the ‘Tiddington Road – Shipston Road Traffic Signal Scheme’) to mitigate additional traffic has been designed and submitted as part of the planning application. The Highway Authority has identified issues with the Scheme that it considers require alterations to make it acceptable. The Highway Authority has also identified that required alterations are in turn likely to lead to unacceptable queuing on Clopton Bridge interfering with the flow of traffic on the Gyratory system and other parts of the network. Such problems will therefore require further mitigation but a scheme to achieve this is not currently available or part of the planning application. Therefore in the absence of an acceptable scheme to mitigate traffic generated by the proposed development the District Planning Authority considers that unacceptable impacts of congestion on the local highway network would arise with consequent harm to local businesses, the local community and the environment, including but not limited to air quality. Such adverse impacts are considered to be contrary to sustainability objectives of the Stratford on Avon District Local Plan Review 1996-2011, including Saved Policy DEV.4 and contrary to the objectives ... view the full minutes text for item 586.
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
A Members Site Visit (MSV) was arranged to take place on 18th December 2014 between the hours of 14.00-16.00. The MSV was expected to be attended by the case officer, Planning Manager and officers representing SDC Environmental Health and WCC Highway Authority. The itinerary for the MSV included:- Explanation of off-site highway improvements works in the vicinity of Clopton Bridge and including noting impacts on the setting of Heritage Assets; Explanation of air quality matters at Tiddington Road; Observation of application site and proposals including noting the implications for the landscape character and views and impacts on neighbours; Observation of the location of microlight airstrip; Observation of potentially contaminated land area; General observation of traffic in the vicinity; Explanation of highway access points off Loxley Road and off-site highway works at Loxley Road and Knights Lane; Observation of Boundary Lane route and nature.
Highway and Traffic Issues
WCC Highway Authority revised consultation response and recommendation received 18.12.14 – Raise OBJECTION to the proposals for the following reasons. Identify that the proposals will result in increased queuing on Banbury Road at peak periods and other delays on the local highway network and that such impacts require mitigation. State that a scheme to mitigate traffic problems (the ‘Tiddington Road – Shipston Road Traffic Signal Scheme’) was promoted by WCC which the developer agreed to part fund. Highlight that following further consideration of the mitigation scheme several issues have been identified which result in the scheme not being deliverable. These are:- 1. Right turning manoeuvres from Tiddington Road and Swans Nest Lane could not achieved a satisfactory non-hooking manoeuvre 2. At Tiddington Road, the ahead land and right turn lane was a single lane and therefore any vehicle waiting to turn right would block the ahead movement 3. Swans Nest Lane is a single lane and therefore any vehicle waiting to turn right would block the ahead and left movements 4. The primary signal head at Swan Nest needs to be associated with its stop line 5. The road alignment through the junction is considered poor for some movements. 6. There were concerns about the arrangement of the pedestrian crossing at Tiddington Road with regard both the staging and the stagger of the crossing.
Highlight that alternative layouts have been considered but these in turn lead to a major issue of increasing queuing traffic on Clopton Bridge in the morning peak which would have knock on impacts on the functioning of the gyratory and other issues around the network. Therefore, at this stage, state it is simply not possible for the Highway Authority to fully assess the impact of the development on the network, and be in a position to advice the LPA on what any final mitigation may or may not look like. Without adequate mitigation the impact of the proposed development is considered unacceptable. Therefore object for the following reason:-
“The current proposed mitigation scheme known as Tiddington Road/ Shipston Road Traffic Signal Scheme cannot be made to work at this present time. The Highway Authority are not in a position, with the available data, to agree a final layout for the proposed mitigation.” The Highway Authority state that they will continue to work with the applicants and their consultants with a view to looking at revised Tiddington Road/ Shipston Road Traffic Signal Scheme and a signalised gating scheme covering the Bridgefoot Gyratory. The Highway Authority state that they are confident that such a scheme could be shown to provide mitigation for the development and also ensure that the operation of the gyratory is not compromised.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.