(1) That ‘in principle’ support be given towards making a financial contribution to BDUK contract 2 (phase 2) which would maximise the coverage of superfast broadband across Stratford-on-Avon District; and, (2) That a further report be provided for consideration in the budget setting process for 2016/17. NOTE: This item is subject to call-in to the OSC.
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
(1) That ‘in principle’ support is given towards making a financial contribution to BDUK contract 2 (phase 2) which will maximise the coverage of superfast broadband across Stratford-on-Avon District.
(2) That subject to (1) above, a further report is provided for consideration in the budget setting process for 2016/17 in the Autumn.
1 Background/Information 1.1 Following a Notice of Motion in relation to High Speed Broadband at the meeting of Cabinet on 16 March 2015, it was agreed that a report should be brought back to The Cabinet in relation to the issue. This initial report provides context to the debate and seeks at this stage an “in principle” decision, ahead of formal consideration later in the year. 1.2 In 2011, the government set out to increase the availability of Superfast Broadband to a figure of 90%. This was done via their own Broadband Delivery UK (BDUK) programme. 1.3 The initial BDUK/CSW Contract was signed in May 2013 and is referred to as Contract 1. Prior to Contract 1, Superfast Broadband availability was 73% across Warwickshire. 1.4 The aspiration for Contract 1 was to achieve 91% Superfast availability. However, it is now apparent that failure within BT’s commercial rollout will reduce this figure and CSW now believes that at the end of Contract 1 in March 2016, Warwickshire will achieve 89% Superfast Broadband coverage, which is still a very significant uplift. Superfast Broadband Pre Contract 1 Post Contract 1 Availability 2013 2016
North Warwickshire 48% 85%
Nuneaton and Bedworth 95% 98%
Rugby 79% 90%
Stratford-on-Avon 45% 75%
Warwick 86% 94%
Warwickshire 73% 89%
1.5Stratford-on-Avon District Council, together with North Warwickshire District Council, was prioritised for delivery of Superfast Broadband within the CSW project. At the end of January 2015, the THP number (Total Homes Passed) within Stratford-on-Avon District was 9937. This is marginally behind North Warwickshire but significantly more than any other partner authority. 1.6 At the start of the CSW project, in 2012, Analysys Mason was commissioned to undertake a cost modelling exercise in order for CSW to understand the increasing costs to achieve 100% coverage of Superfast Broadband for the sub-region. 1.7 For Warwickshire, the following chart was produced to illustrate the manner in which costs rise when trying to reach the most rural areas of the county. (Please note the vertical axis is marked in £m). 1.8 The chart indicates that costs for Stratford-on-Avon District Council are significantly higher than the other Districts and Boroughs, over four times more expensive. The underlying factor here is that Stratford-on- Avon District Council has received the highest level of funding from the WCC/BDUK capital funding.
2 BDUK Contract 2 (Part1)
2.1BDUK Contract 2 was signed on 30th January 2015. The contract includes a contractual commitment to enable 17,247 premises to access fibre broadband with 14,610 premises at Superfast Broadband speeds of 24Mbs or greater. This should raise the overall Superfast coverage to 94% for Warwickshire.
Pre Contract Post Contract Post Contract Superfast Broadband 1 1 2 Availability 2013 2016 2018 North Warwickshire 48% 85% 93% Nuneaton and Bedworth 95% 98% 98% Rugby 79% 90% 94% Stratford-on-Avon 45% 75% 89% Warwick 86% 94% 96% Warwickshire 73% 89% 94%
2.2BT proposes to contribute £984.000 towards the capital costs with £556,000 in the deployment period and £1,600,000 deployment costs and ongoing operating costs towards the project over the contract term of circa 10.25 years, in addition to the £8,120,000 subsidy provided by CSW and BDUK for Contract 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.