Resolved
That the progress report, as presented, be received and adopted.
Audit and Standards Committee approved this item on Monday 26 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the progress report, as presented, be received and adopted.
That the progress report be noted.
1 Background/Information 1.1 Internal Audit continues to carry out a programme of work in accordance with the approved Audit Plan and this report details progress to date.
2 Progress against the Audit Plan 2.1 The current progress for the 2017/18 Internal Audit plan is as follows:
Service Activity Current Level of Direction of Status Assurance Travel1 provided by controls Executive Economic Complete Substantial Director A Development & Tourism1
Technical Car Parking Draft and Community Services ICT and Business Continuity1 Complete Limited Revenues Cyber Risks Draft
1 Completed audits previously reported to Committee in January 2018.
1 Service Activity Current Level of Direction of Status Assurance Travel1 provided by controls Database Admin and In Progress Security Housing Benefits In Progress
Planning and Emergency Planning1 Complete Moderate Housing Planning In Progress
Executive Bank Reconciliation - In Progress Director B Advisory HR & Payroll1 Complete Substantial
Strategic, financial & In Progress business planning Performance Complete Substantial Management1
Corporate In Progress Governance / Decision making / AGS - Advisory Governance Freedom of Complete Substantial and Information1 Democracy Licensing1 Complete Moderate
2.2Although progress is behind what we would usually expect at this time of the year we still anticipate substantially achieving the plan by 31 March. As agreed at the last meeting, the Corporate Governance audit will now be advisory.
3 Options available to the Audit and Standards Committee 3.1 To note the content of the Internal Audit progress report.
4 Implications of the Proposal 4.1 Legal/Human Rights Implications 4.1.1 There are no legal or human rights implications of the proposal. The requirement for an internal audit function is contained in The Accounts and Audit Regulations 2015 which require the Authority to: “undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance”.
2 4.2 Financial 4.2.1 There are no financial implications of the proposal. 4.3 Environmental 4.3.1 There are no environmental implications of the proposal. 4.4 Corporate Strategy 4.4.1 There are no corporate strategy implications of the proposal. 4.5 Analysis of the effects on Equality 4.5.1 There are no equality impact assessment implications of the proposal.
5 Risk Assessment 5.1 None.
6 Conclusion 6.1 That the Internal Audit progress report be noted.
David Buckland EXECUTIVE DIRECTOR AND S151 OFFICER
Background papers: None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportReport | 54 KB | DownloadRead as text |
Follow Audit and Standards Committee at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Update on Standards Issues(1) That the information in Appendix 1 to the agenda report be noted; and (2) That the information in Appendix 2 of t... | Noted | Open |
| 9 Nov 2026 | CCTV Code of Practice and Evaluation 2026That the CCTV Code of Practice 2026 and the CCTV Evaluation Report 2026, together with the actions taken to ensure th... | Noted | Open |
| 9 Nov 2026 | Proposal to Review the RIPA Corporate Procedure DocumentThat the Regulation of Investigatory Powers Act 2000 (RIPA) Corporate Procedure, set out in Appendix 1 to the agenda ... | Agreed | Open |
| 9 Nov 2026 | Internal Audit Progress ReportThat the progress report be noted. | Noted | Open |
| 9 Nov 2026 | Urgent Business - Azets: External Audit Plan 2025/26 and Audit Build Back Plan 2025/26 - 2027/28That the Auditor’s Annual Report for 2025/26 be noted. Azets : Audit Build Back Plan 2025/26 - 2027/28 At the invitat... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.