Resolved
That Planning Application 18/01458/FUL be REFUSED for the following reasons (the detailed wording of which be delegated to Officers): The reasons for refusing Planning Permission were that, in the opinion of the Planning Committee, the proposal was contrary to Policy CS9 insomuch as it was an overdevelopment of the site including, by the necessary removal of a green buffer. The proposal was therefore considered to be out of keeping with the character and local distinctiveness of the area. Furthermore, the harm to the character of the area was not considered to be outweighed by the benefit of an additional dwelling given that the Council could demonstrate a 5 year housing land supply. A short adjournment was taken at this point.