Item476
Resolved
That Planning Application 17/03258/REM be GRANTED, subject to: 1. Finalising a phasing strategy, including an overall phasing plan, in accordance with the requirements of conditions 30 (phasing) and 18 (programme of implementation of open space/equipped play space) of outline application 14/03579/OUT and; 2. The completion of a legal agreement securing: I. The level and tenure of affordable housing to be provided on site; II. Cross boundary integration between the application site and the wider proposed LMA site; III. Changes to the s106 (relating to the outline planning permission) as a result of the agreed phasing strategy including the payment triggers for education contributions for any specific phases; and subject to the following (the detailed wording of which be delegated to Officers): · 24 conditions contained in the report; and · 11 notes contained in the report.
Word for word from the decision Stratford-on-Avon published for this meeting.
Source: democracy.stratford.gov.uk