(1) To authorise Officers to enter into the Joint Working Agreement (2) with the Partner Councils in order to facilitate the delivery of the Materials Recycling Facility. (2) To delegate authority to the Interim Chief Executive following consultation with the Leader of the Council and the Head of Governance and Democracy to finalise the terms and make such variations as is deemed necessary to the terms of the Joint Working Agreement (2) with the Partner Councils. (3) Following the completion of the business case and Joint Working Agreement (2) by all the Partner Councils, approve the commencement of a competitive procurement process on behalf of the Partner Councils with Coventry City ... view the full minutes text for item 293.
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
Subject: Materials Recycling Facility Lead Officer: David Buckland / Tony Perks Contact on 01789 260425/260620 Lead Member/ Portfolio Holder: Councillor I Shenton
Summary This report sets out an opportunity to invest in a regional recycling facility. Recommendation: The recommendations are set out in Section 4 of the report below.
1. Background/Information 1.1 Stratford-on-Avon District Council (SDC) collects approximately 15,000 tonnes of dry recycling each year. Currently this is delivered to a Materials Recycling Facility in Ettington where it is sorted and distributed for reprocessing. 1.2 The existing arrangements are procured through the Waste and recycling contract with Biffa which runs until 2022. Under this contract we are charged a fixed gate fee for each tonne of recyclate delivered, this price is protected under the terms of the contract. 1.3 When this contract expires SDC will need to make new arrangements for the reprocessing of material and evidence from recent procurement exercises in both Coventry and neighbouring authorities shows that this upward trend of cost is likely to continue with substantial rises as the private sector continue to move the risk of end market prices and legislation more and more to local authorities. 1.4 In anticipation of this in 2017/18 a feasibility study was undertaken to consider the technical and economic viability of developing a Material Recycling Facility (MRF) to serve Coventry City Council (CCC), neighbouring authorities, and commercial businesses across the region. This study indicated a positive business case, subject to more detailed information. 1.5 During the last 12 months a detailed Business Case has been developed to determine the viability of a Materials Recycling Facility. This Business case has concluded that a facility with a capacity of between 120,000 and 175,000 tonnes would be commercially viable. 1.6 To make the construction of a MRF financially viable and in order to share the risks and benefits of this project a formal agreement has been formed with five other local authorities, namely: Nuneaton and Bedworth Borough Council North Warwickshire Borough Council Rugby Borough Council Solihull Metropolitan Borough Council Walsall Council
1.7Each Partner Council will become shareholders in the MRF and SDC have been offered the opportunity to become a Partner Council.
1.8The business case considered by this report has been developed assuming the recyclable materials from each of the Partner Councils will be committed to the Project, this makes the facility cost effective, whilst leaving some tonnage headroom for commercial growth and the future needs of the Partner Councils, or the addition of more Partner Councils.
1.9To date the costs of producing the business case have been shared by the partners based on the ratio of their likely tonnage inputs. Along with an investment proposal, this report seeks authority to further strengthen these arrangements through a second Joint Working Agreement which will cover the work up to financial close, including but not limited to the costs of procurement, advisors, and the submission of a planning application for the construction of a new Material Recycling Facility.
1.10At the financial close of the build project, the Partner Councils would be required to establish jointly an arms-length company (AssetCo) to enter into contracts and to deliver the recycling solution, funded through loans from the Partner Councils.
2. Location of the Proposed Materials Recycling Facility
2.1The existing Local Plan has made provision for future waste management facilities in Coventry by allocating the site adjacent to the current Energy from Waste plant on Bar Road. The project described within this report proposes to use approximately 50% of this site to develop the Material Recycling Facility.
3. Commercial Considerations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.