(1) That the proposed procurement process, as detailed in Section 2 of the agenda report, be endorsed; (2) That the proposed evaluation criteria for determining the suitability of contractors to tender, as set out in Appendix 2 to the agenda report (amended as above), be approved; and (3) That the Head of Technical and Community Services, in consultation with the Portfolio Holder for Operations, be authorised to advertise and award the Contract in accordance with the approved budget and evaluation criteria. NOTE: This item is subject to call-in to the OSC
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
The existing building cleaning service is due for renewal. The service includes the cleaning of Elizabeth House Council Offices and opening, cleaning and closing of Council public conveniences and the Council’s sports pavilion.
This report sets out the proposed process for procuring a new contract.
Recommendations
(1) That the proposed procurement process, as detailed in Section 2 is endorsed and that the proposed evaluation criteria for determining the suitability of contractors to tender, shown in Appendix 2, is approved.
(2) That the Head of Technical and Community Services, in consultation with the Portfolio Holder for Operations is authorised to advertise and award the contract in accordance with the approved budget and evaluation criteria.
1 Background 1.1 The current building cleaning contract, provided by Kingdom Services Group Ltd was awarded in 2016.
1.2Whilst the Council has the discretion to extend the existing contract, the Cabinet is advised not to apply this but to retender this contract. This is, in part, due to concerns with the current standard of cleaning and allows the Council the opportunity for the contract details to be amended to ensure that the Council provides a fit for purpose and value for money service. 2 Proposed Procurement Process 2.1 The contract will be procured through the OJEU procedure as the total contract cost is above the OJEU threshold.
2.2The timeframe for the procurement process is set out in Appendix 1. 2.3 It is proposed that the contract with be let for four years with the option of a further four year extension.
2.4The new service will be based on the specification as described in the summary.
2.5The procurement exercise will be carried out in accordance with the Public Contracts Regulations 2015 in so far as they are applicable. A Prior Information Notice will be posted to advertise the contract tender opportunity, prior to the commencement of the formal procurement process, and to seek expressions of interest. Subject to the agreement of The Cabinet, an appropriate OJEU Contract Notice will be posted. Subject to an acceptable bid being received and approved as appropriate, the indicative date for the contract to be awarded is February/March 2020 and will commence on 2nd June 2020 following a stand-still (Alcatel) and mobilisation period.
2.6A Supplier Selection Questionnaire will be sent out to all contractors who express an interest in the contract. Returned submissions will then be evaluated.
2.7Providing that sufficient bidders qualify, it is proposed that between four and six bidders will then be short-listed and invited to the Invitation to Tender stage. Submitted Tenders will then be evaluated and scored to ascertain the winning bid. Bids will be evaluated on cost (40%) and quality (60%) to establish the most economically advantageous Tender. A scoring matrix will be developed, based on the evaluation criteria set out in Appendix 2, which will ensure that bids are evaluated on an equitable basis. The scoring is weighted to ensure that the Council’s key requirements are achieved. 3 Options available to The Cabinet 3.1 The Cabinet may approve the procurement process as set out above; 3.2 The Cabinet may award a four year extension to the existing contract; or 3.3 The Cabinet may propose an alternative process subject to any legal implications. 4 Implications of the proposal 4.1 Legal/Human Rights Implications 4.1.1 The contract procedure process must comply with the Public Contract Regulations and OJEU procurement requirements. 4.2 Financial 4.2.1 The indicative cost for the life of the contract (i.e. four years plus the optional four year extension) exceeds the OJEU threshold therefore the procurement process will be carried out in accordance with the OJEU procedure.
4.2.2 The current cost of the Contract is £220k p.a.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.