Resolved
RESOLVED : 1) That the progress report be noted; and 2) That the Procurement and Remote Working audits be deferred until the next financial year.
Audit and Standards Committee noted this item on Monday 16 March 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : 1) That the progress report be noted; and 2) That the Procurement and Remote Working audits be deferred until the next financial year.
AUDIT AND STANDARDS COMMITTEE 16 MARCH 2020
Subject: Internal Audit Progress Report Lead Officer: Paul Clarke Contact on 01926 412897 Portfolio Holder: Councillor T Harvey Chairman: Councillor P-A O’Donnell
Summary To receive a progress report from Internal Audit. Recommendations 1) That the progress report be noted; and 2) That the Procurement and Remote Working audits be deferred until the next financial year.
1 Background/Information 1.1 Internal Audit continues to carry out a programme of work in accordance with the approved Audit Plan. This report details progress to date. 2 Progress against the 2019/20 Plan 2.1 The current progress for the 2019/20 Internal Audit plan is as follows:
Level of Current Assurance Direction Service Activity Status provided of Travel by controls
Completed Audits previously reported to Committee:
Grounds Technical and Complete Full Maintenance Community Services Building Control Complete Substantial
ICT and Council Tax Complete Substantial Revenues Governance Land Charges Deferred and Democracy Level of Current Assurance Direction Service Activity Status provided of Travel by controls
Audits Completed since last Committee:
Insurance Complete Substantial Financial Services and Payroll Complete Full S151 Officer Treasury Complete Substantial Management Homelessness and Planning and Temporary Complete Substantial Housing Accommodation
Status of remaining Audits:
Corporate In Progress Governance Economic Growth Chief Executive inc. Capital In Progress and Head of Expenditure Paid Service Safeguarding Draft
Strategic, financial In Progress & business planning
Financial Bank Reconciliation Draft Services and S151 Officer Procurement Defer
GDPR Draft
ICT and PCI-DSS In Progress Revenues Compliance
Remote Working Defer
2.2It is pleasing to report that of the four audits completed since the last committee meeting, three have a Substantial opinion and one has achieved the highest opinion of Full Assurance. 2.3 The Procurement and Remote Working audits were planned for Q4 of this financial year. It is now thought that conventional audits would be of limited value at present as it is acknowledged that there are some unresolved issues that need to be sorted out. Instead, it is proposed that the Audit team works with the areas in an advisory role during the remainder of the year. It is recommended that these audits be deferred until the new financial year. 2.4 Where a report is at draft stage, it is with the relevant senior manager. We are awaiting their action plan before the report is then finalised. 2.5 It is anticipated that the plan will be substantially complete by the end of the financial year.
3 Options available to the Audit and Standards Committee 3.1 To note the content of the Internal Audit progress report.
3.2To approve the request to defer the Procurement and Remote Working audits to the 2020/21 financial year.
4 Implications of the Proposal 4.1 Legal/Human Rights Implications 4.1.1 There are no legal or human rights implications of the proposal. The requirement for an internal audit function is contained in The Accounts and Audit Regulations 2015 which require the Authority to: “undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance”. 4.2 Financial 4.2.1 There are no financial implications of the proposal. 4.3 Environmental/Climate Change Implications 4.3.1 There are no environmental/climate change implications of the proposal. 4.4 Corporate Strategy 4.4.1 There are no Corporate Strategy implications of the proposal. 4.5 Analysis of the effects on Equality 4.5.1 There are no equality impact assessment implications of the proposal. 4.6 Data Protection 4.6.1 There are no data protection implications arising from the recommendations within this report. 5 Risk Assessment 5.1 None. 6 Conclusion 6.1 That the Internal Audit progress report be noted.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportReport | 162 KB | DownloadRead as text |
Follow Audit and Standards Committee at Stratford-on-Avon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Update on Standards Issues(1) That the information in Appendix 1 to the agenda report be noted; and (2) That the information in Appendix 2 of t... | Noted | Open |
| 9 Nov 2026 | CCTV Code of Practice and Evaluation 2026That the CCTV Code of Practice 2026 and the CCTV Evaluation Report 2026, together with the actions taken to ensure th... | Noted | Open |
| 9 Nov 2026 | Proposal to Review the RIPA Corporate Procedure DocumentThat the Regulation of Investigatory Powers Act 2000 (RIPA) Corporate Procedure, set out in Appendix 1 to the agenda ... | Agreed | Open |
| 9 Nov 2026 | Internal Audit Progress ReportThat the progress report be noted. | Noted | Open |
| 9 Nov 2026 | Urgent Business - Azets: External Audit Plan 2025/26 and Audit Build Back Plan 2025/26 - 2027/28That the Auditor’s Annual Report for 2025/26 be noted. Azets : Audit Build Back Plan 2025/26 - 2027/28 At the invitat... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.