Stratford-on-Avon District Council
The Cabinet, Tuesday 9 February 2021

Wellesbourne Airfield Update

Noted Executive 1 paper

The Cabinet noted this item on Tuesday 9 February 2021. Below is the council's own wording, with the papers it was decided on.

Item546

Resolved

That the report be noted and that the budget to fund the Compulsory Purchase Order be maintained. NOTE: This item is not for call-in to the OSC as it is for noting only.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 3 pages

Summary

This report provides The Cabinet with an update on the progress of the ongoing work to secure the future of aviation at Wellesbourne Airfield.

Recommendation

That the report is noted and that the budget to fund the Compulsory Purchase Order is maintained.

Background

1.1The Cabinet, at its meeting on 11 March 2019, resolved to use CPO powers to implement the Council Core Strategy policies AS.9 and CS.27 and ensure the retention and enhancement of flying functions and aviation related facilities at Wellesbourne Airfield.

1.2Following this decision, officers of the Council have entered into negotiations with the current owners of the airfield and their agents to explore the potential to bring about the Council’s Core Strategy aspirations without the need for an Order. This is a requirement of the CPO process.

1.3As part of these negotiations a Memorandum of Understanding (MoU) has been put in place between the Council and the owners of the airfield. This has ensured that aviation has continued at the site whilst negotiations continue and all but one of the businesses operating from the airfield have been granted new tenancies.

1.4The MoU has not been without controversy and there have been a number of allegations that the terms of the MoU have been breached. Determining this has been further complicated by the restrictions that have arisen as a result of the COVID19 pandemic which have affected the ability to operate and the appetite to enjoy general aviation. 1.5 Officers have considered the situation in respect the MoU and have taken legal advice. On balance, we are currently of the opinion that the MoU is serving its purpose in that aviation is continuing at the site and to terminate the MoU would likely bring about an early demise of the airfield which would be against the public interest.

1.6Alongside the MoU, negotiations have been ongoing with the owners of the airfield and their agents. These centre around the repositioning of the runway and aviation facilities to provide a more sustainable airfield whilst releasing parts of the site for development. Our aviation advisors have confirmed that the emerging proposals have the potential to meet the Policy requirements of the Core Strategy.

1.7The Department for Transport (DFT) have shown a keen interest in the future of Wellesbourne airfield, they see Wellesbourne as a key part of the secondary airfield network and are working with us to secure its long term future.

1.8Under the MoU the Council gave an undertaking to pause the CPO process whilst constructive negotiations were ongoing, providing that aviation was continuing. To date this has been the case and we are actively engaging with the owners and their agents to find a mutually acceptable solution for the long term future of the site. However, if it is not possible to agree a solution it will be necessary to progress with CPO proceedings.

1.9The Council has kept up a dialogue with potential delivery partners with a view to maintaining aviation on the site should further CPO proceedings prove necessary.

1.10A budget of £1M was set aside to fund the necessary CPO work, at this stage it is recommended that this should be maintained to support further CPO proceedings should they prove necessary.

2 Options available to The Cabinet

2.1To note the report and maintain the current budget.

2.2To request an alternative course of action.

3 Members’ Comments

3.1Included within the report.

4 Implications of the proposal

4.1Legal/Human Rights Implications

4.1.1 Compulsory Purchase is a defined legal process. The Council is being supported through this process by CPO Lawyers Burgess Salmon. 4.2 Financial

4.2.1 The current budget to support the CPO is £1M, this was set in 2019. It is proposed that this budget should be maintained.

4.3Environmental/Climate Change Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Wellesbourne Airfield UpdateReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Wellesbourne Airfield UpdateThis decision
  2. Update on Wellesbourne AirfieldAgreed
  3. Wellesbourne Airfield Memorandum of Understanding 2Noted
  4. Wellesbourne Mountford Airfield: Compulsory Acquisition of Third Party InterestsDecided
  5. Wellesbourne Mountford AirfieldDecided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies