Resolved
That Planning Application 21/03992/FUL be GRANTED subject the following conditions/notes and for the reason, detailed below (the detailed wording of which be delegated to Officers): Conditions · Time Limit of 3 years · Approved Plans · Materials Schedule · Hard and Soft Landscaping · Land Contamination (pre-commencement) · Remedial Strategy · Details of Security Fencing · Make good any damage to the Public Right of Way · EVCPs · Water Butts · Broadband · Climate Change Checklist · Bespoke Specialised Workers Tie of both the existing and new dwelling to the business of Red Horse Vale Ltd. Notes · NPPF · WCC Fire and Rescue · Public Rights of Way Note Reason for Grant In the opinion of the Local Planning Authority, t he reason for granting Planning Permission was that due to the large, unique and vulnerable location of the site, Members felt that a particular security need was required.