The Cabinet, Monday 2 December 2024

Performance Monitoring Report for Q2 2024/25

Decided Executive 4 papers

The Cabinet decided this item on Monday 2 December 2024. Below is the council's own wording, with the papers it was decided on.

Item377

Resolved

That the position in relation to the Quarter 2 Performance Monitoring Report 2024/25 be received. NOTE: This item is not subject to call-in to the OSC as it is not a key decision
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 5 pages

The Cabinet 2 December 2024

Title: Quarter 2 Performance Monitoring Report

Lead Officer: Simon Purfield, Performance, Consultation & Insight Manager (01789 260118)

Portfolio Holder/ Lead Member: Councillor S Juned

Summary This report presents performance achieved during Quarter 2 (July to September 2024) monitoring delivery of the Council Plan Actions and Key Performance Indicators. Recommendation That the position in relation to the Quarter 2 Performance Monitoring Report 2024/25 is received, and any issues identified for further consideration be addressed by: (1) A further report to The Cabinet; and (2) The Portfolio Holder.

1 Background/Information 1.1 The Council Plan was approved by Council on 11 December 2023. The Council plan includes six key themes and a total of nineteen objectives which are split over three distinct groups.

1.2Following the approval of the Council Plan, this report presents a summary of performance during Quarter 2 of the year 1 plan (2024/25) providing the Cabinet with a high-level report on the delivery of the Council Plan Actions and Key Performance Indicators. 2 Council Plan Actions 2.1 There are 66 actions included in the plan for Year 1. Of these, 30 are due to be reported this quarter. 2.2 Performance against target: Of the 30 actions, 24 (80%) have been achieved, one (3%) is ongoing with no set target, and five (17%) actions were not achieved. 2.3 Full details are presented in Appendix 1 to this report.

3 Key Performance Indicators 3.1 There are 23 Key Performance Indicators set to monitor performance in Year 1. 18 of these are related to the Council Plan objectives and 5 are Corporate Health Indicators. 3.2 Performance against target: 15 (72%) indicators are on target for this quarter. Six (28%) indicators are not currently on target. Corrective actions will be put in place to bring performance back on track where possible. Two indicators have not been reported:  Major planning applications: Percentage of Major applications overturned on appeal.  Non-Major planning applications: Percentage of Non-Major applications overturned on appeal.  Both indicators rely on data which we currently can not confirm as reliable. Investigative work is underway to identify how we can obtain accurate data. 3.3 Residents Survey results were reported in Quarter 1, Appendix 2 on a separate table. The survey is undertaken every two years and is reported in the relevant quarter when results are available. 3.4 Full details are presented in Appendix 2 to this report and Appendix 3 summarises the results in an infographic format, which also benchmarks the data and compares with previous years.

4 Options available to The Cabinet 4.1 Note performance achieved. 4.2 Request further information. 5 Evidence Base 5.1 This report presents achievement against Key Performance Indicators. 6 Consultation and Members’ comments 6.1 I thank the officers for all the work done to achieve these results. This data will assist us in measuring our performance going forward. 7 Implications of the proposal 7.1 Legal Implications 7.1.1 There are no legal or human rights implications arising from this report. 7.2 Financial 7.2.1 There are no new financial implications arising from this report. 7.3 Council Plan 7.3.1 This report monitors delivery of the Council Plan Actions and Key Performance Indicators. 7.4 Environmental/Climate Change Implications 7.4.1 There are no environmental/climate change implications arising from this report. 7.5 Analysis of the effects on Equality 7.5.1 There are no equality implications arising from this report. 7.6 Data Protection 7.6.1 There are no data protection implications arising from this report. 7.7 Health and Wellbeing 7.7.1 There are no health and wellbeing implications arising from this report. 7.8 Human Resources/Staffing 7.8.1 There are no staffing implications arising from this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Plan Actions Q2 24-25Appendix 1 21 pages Download
PDF
Key Performance Indicators Quarter 2 2024-25Appendix 2 3 pages Download
PDF
Dashboard Q2 2024-25Appendix 3 4 pages Download
PDF
Performance Monitoring Report for Q2 2024/25Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Performance Monitoring Report for Q2 2024/25This decision
  2. Performance Monitoring Report for Quarter 1 2026/27Noted
  3. Quarter 4 End of Year Performance Monitoring Report 2025/26Noted
  4. Quarter 3 Performance Monitoring ReportDecided
  5. Quarter 2 Performance Monitoring ReportDecided
  6. Performance Monitoring Report for Quarter 1 2025/26Noted

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies