CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Stratford-on-Avon District Council
The Cabinet, Monday 3 November 2025

Strategic Risk Register

Noted Executive 3 papers

AI summaryStratford-on-Avon Cabinet endorses its October 2025 Strategic Risk Register, noting a new risk on local government reorganisation. No direct financial, legal or staffing implications arise.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAmendments noted, register approved as Appendix 1
MoneyNo direct financial implications
What happens nextFurther Cabinet review in six monthsRegister also reviewed quarterly by Management Team
Who it affectsCouncil operations and prioritiesCovers key projects, finances, staffing, reorganisation

What was decided

The Cabinet endorsed the Strategic Risk Register at Appendix 1 with the amendments noted, and noted the item is not a key decision so is not subject to call-in to the Overview and Scrutiny Committee. Report P5

Members accepted the officer recommendation to review the register and consider whether further mitigating actions were needed. Report P5, P7

Why

The Strategic Risk Register records all significant risks to the council's operations, key priorities and major projects, and aids effective governance. Report P6, P9

The Management Team has fundamentally reviewed the register and a new corporate risk on local government reorganisation has been added, also linked to the financial sustainability and staff retention risks. Report P6

What happens next

The Management Team will continue to review the register quarterly and the Cabinet will review it again in approximately six months. Report P6

Individual services will keep their own service risk registers within their 2025/26 service plans. Report P6

Options considered

  • Chosen: Endorse the Strategic Risk Register and agree to the mitigating actions. Recommended by officers as the standard approach following Management Team review Report P5, P7
  • Rejected: Endorse the Strategic Risk Register and agree alternative mitigating actions Report P7
  • Rejected: Reject the Strategic Risk Register Report P7

Implications

  • Legal: No direct legal or human rights implications arise from the report. Report P9
  • Financial: No direct financial implications, though financial impact of risks has been used in assessing individual risk levels. Report P9
  • Equalities: Initial screening assessed all equalities strands as low or no relevance; the Equalities Section in the report covers this. Report P12, P27, P31
  • Climate: No direct environmental or climate change implications arise from the report. Report P9
  • Staffing: No direct human resources or staffing implications, although staff retention is one of the corporate risks covered. Report P6, P9
  • Other: No direct data protection, health and wellbeing implications arise from the report. Report P9

Who and where

  • Stratford-on-Avon District Council as an organisation, including its operations, key priorities and major projects Report P6
  • Council staff, via the staff retention risk linked to local government reorganisation Report P6
  • Council finances, via the financial sustainability risk linked to local government reorganisation Report P6

Timeline

  • June 2025: Strategic Risk Register last considered by the Cabinet Report P6
  • October 2025: Latest version of the Strategic Risk Register produced following Management Team review Report P5, P6
  • 3 November 2025: Cabinet reviews and endorses the register Report P1
  • Quarterly: Management Team reviews the Strategic Risk Register Report P6
  • Twice a year: Cabinet reviews the Strategic Risk Register Report P6

Plain English for the jargon

  • Strategic Risk Register: A record of all significant risks to the council's operations, key priorities and major projects, scored on a 4 by 4 matrix with a maximum score of 16.
  • Net remaining risk: The level of risk left after the council's mitigating measures are taken into account. Risks with a green net remaining risk are excluded from the register.
  • OSC (Overview and Scrutiny Committee): The committee that would normally be able to call in key decisions; this decision is not a key decision and so is not subject to call-in.
  • Call-in: A process allowing scrutiny members to challenge a key decision before it takes effect; not applicable to this item.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item306

Resolved

That the , attached as Appendix 1 to the agenda report, amended as noted above, be endorsed. Note: This item is not subject to call-in to the OSC as it is not a key decision
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 5 pages

The Cabinet 3 November 2025

Title: Strategic Risk Register

Lead Officer: David Buckland, Chief Executive (01789 260425)

Portfolio Holder/ Lead Member: Councillor S Juned

Summary This report sets out the latest version of the Council’s Strategic Risk Register (October 2025) for review by The Cabinet. It has been drafted following review by the Council’s Management Team and has been prepared in line with the Council’s Risk Management Strategy. Recommendation That the Strategic Risk Register attached at Appendix 1 be reviewed and consideration given if any further actions should be taken to manage the risks facing the organisation.

1 Background/Information 1.1 The Strategic Risk Register records all significant risks to the Council’s operations, key priorities, and major projects. Individual services also have their own service risk registers which are included within the individual service plans for 2025/26. 1.2 The Strategy identifies that the Strategic Risk Register should be reviewed quarterly by the Council’s Management Team and then twice a year by The Cabinet. The Cabinet last considered the Strategic Risk Register in June 2025. 1.3 A summary of all the risks and their position on the risk matrix, as currently assessed, is set out as Appendix 1. 1.4 The assessments of risk are to a degree subjective, however, are based on an assessment of the likelihood of something occurring and the impact that might have. The register identifies the gross risk that the Council is facing, the mitigating measures that the Council has in place and then the net remaining risk. Any risk that has been considered and has a remaining risk which is green has been excluded from this register. 1.5 Following announcements surrounding local government reorganisation a new corporate risk has been included on this subject. This risk is also referred to within the financial sustainability risk and staff retention risk. 1.6 Appendix 2 identifies the guidance that the Council has adopted in considering risk and the impact of such risks for the Council. The matrix is based on a 4 x 4 grid with the maximum score available to any risk being 16. 1.7 The Management Team has recently fundamentally reviewed the Strategic Risk Register, and this is now presented to The Cabinet for review.

2 Options available to The Cabinet 2.1 The options available to The Cabinet are as follows: 2.1.1 Endorse the Strategic Risk Register at Appendix 1 and agree to the mitigating actions; 2.1.2 Endorse the Strategic Risk Register at Appendix 1 and agree alternative mitigating actions; or 2.1.3 Reject the Strategic Risk Register at Appendix 1.

3 Consultation and Members’ comments 3.1 The report has been considered by the Management Team and Councillor comments have been incorporated into the report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20251103: Cabinet: Risk Register: Appendix 1Appendix 16 pages Download
PDF
20251103: Cabinet: Risk Register: Appendix 2Appendix 1 pages Download
PDF
Strategic Risk RegisterReport 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 18 attended
SJ
Councillor Susan JunedLeader, present
GC
Councillor George CowcherDeputy Leader, present
LA
Councillor Louis AdamPortfolio Holder, apologies
LC
Councillor Liz ColesPortfolio Holder, present
DC
Councillor David CurtisPortfolio Holder, present
NG
Councillor Natalie GistPortfolio Holder, present
LG
Councillor Lorraine GrocottPortfolio Holder, apologies
AC
Councillor Andrew CrumpObservers, present
KR
Councillor Kate RolfeObservers, present
DP
Councillor Dave PassinghamObservers, apologies
DP
Councillor Daren PembertonObservers, present
DB
David BucklandOfficer, expected

All 18 on the meeting page

On this subject at Stratford-on-Avon

Search all
  1. Strategic Risk RegisterThis decision
  2. Strategic Risk RegisterDecided
  3. Strategic Risk RegisterDecided
  4. Strategic Risk RegisterDecided
  5. Strategic Risk RegisterDecided
  6. Strategic Risk RegisterDecided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies