Minute 374 - Task and Finish Group: Privately Managed Public Open Spaces, Flood Alleviation Schemes, and Estate Roads
NotedCommittee1 paper
AI summaryThe Council granted the Task and Finish Group an additional three months to finish its work, with its final report due at the Overview and Scrutiny Committee meeting on 8 April 2026, then to Cabinet and Council [D]
Written from the decision and the officer reportPDF Pro
OutcomeNotedFinal report due 8 April 2026 [D]
MoneyNot stated
What happens nextSubmit final report [D]8 April 2026, then Cabinet and Council [D]
Who it affectsLocal councils and residents [P6]Surveys and in person meetings [P6][D]
What was decided
The Council noted the progress made by the Task and Finish Group so far.
The Group received an additional three months to complete its outstanding work.
The Group will submit its final report to the Overview and Scrutiny Committee meeting on 8 April 2026, then to Cabinet and Council.
Why
The Chair of the Task and Finish Group updated members on its work and explained why an extension was sought. Report P5
The Group's main remit had concluded, and the extension would continue evidence collection from local councils and residents through surveys and in person meetings. Report P6
A proposed and seconded amendment changed the final report meeting from 4 March 2026 to 8 April 2026. Report P7
What happens next
The Group will complete its outstanding work during the additional three months.
The Group will submit the final report to the Overview and Scrutiny Committee meeting on 8 April 2026.
The final report will then go to Cabinet and Council.
Options considered
Chosen: Grant the Group an additional three months. The main remit had concluded, and the extension would allow evidence collection from local councils and residents to continue. Report P6
Chosen: Consider the final report on 8 April 2026. A proposed and seconded amendment changed the date from 4 March 2026 to 8 April 2026. Report P7
Rejected: Consider the final report on 4 March 2026. The amendment replaced 4 March 2026 with 8 April 2026. Report P7
Implications
Other: Evidence collection from local councils and residents will continue through surveys and in person meetings. Report P6
Other: Final report consideration moved from 4 March 2026 to 8 April 2026. Report P7
Other: The final report will proceed from the Overview and Scrutiny Committee to Cabinet and Council.
Other: The Group's subject area is privately managed public open spaces, flood alleviation schemes and estate roads. Report P4
26 November 2025: The Overview and Scrutiny Committee considered the item and referred it to the Council for determination. Report P2, P3
8 December 2025: The Council noted the Group's progress and granted an additional three months. Report P1
Additional three months: Time allowed for the Group to complete its outstanding work.
4 March 2026: Originally planned date for consideration of the final report, changed by amendment. Report P7
8 April 2026: The final report will be considered by the Overview and Scrutiny Committee. Report P7
Thereafter: The final report will go to Cabinet and Council.
Plain English for the jargon
Task and Finish Group: Group whose minute concerned privately managed public open spaces, flood alleviation schemes and estate roads [P4]
Overview and Scrutiny Committee: Committee that considered Minute 374 and is due to receive the final report [P3][D]
Main remit: The Group's main area of work, which members were told had concluded [P6]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item419
Resolved
(1) That the progress achieved to date by the Group be noted; and (2) That the Group be allowed an additional three months to complete its outstanding work and to submit its final report to the Overview and Scrutiny Committee meeting to be held on 8 April 2026, and thereafter to The Cabinet and Council.
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
Report of: Overview and Scrutiny Committee Date: 26 November 2025 Chair: Councillor A Crump
A meeting of the Overview and Scrutiny Committee was held on 26 November 2025 at which the following item had been considered and referred to the Council for determination. Copies of the relevant report are available from Democratic Services (telephone 01789 260245; email committeemanagers@stratford- dc.gov.uk) or can be viewed at Overview and Scrutiny Committee
Minute 374 - Task and Finish Group: Privately Managed Public Open Spaces, Flood Alleviation Schemes, and Estate Roads
At the invitation of the Chair, Councillor Johnston, the Chair of the Task and Finish Group, provided an update on the work of the Group, and outlined the reasons for the Group requesting an extension of time.
Members were advised that the main remit of the Group had been concluded, but that an additional three months was being requested to continue to collect evidence from local councils and residents, via surveys and in-person meetings.
An amendment to the recommendation set out in the report was proposed and seconded, so that the final report of the Group would be considered at the meeting of the 8 April 2026, rather than 4 March 2026.
Following this, it was
RECOMMENDED to Council:
(1) That the progress achieved to date by the Group be noted; and
(2) That the Group be allowed an additional three months to complete its outstanding work and to submit its final report to the Overview and Scrutiny Committee meeting to be held on 8 April 2026, and thereafter to The Cabinet and Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Political Balance Calculation(1) That the size of the Overview and Scrutiny Committee be increased to 13 Members, and the Monitoring Officer be de...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.