Climate Change Panel

Noted Executive 1 paper

AI summaryCabinet noted Climate Change Panel minutes from 5 May 2026, setting out proposals to hold a climate forum twice a year and opening round four of a £200,000 community climate fund.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet received and noted panel minutes
Money£200,000Round 4 total, £50,000 up on round 3
What happens nextConstitution report to Audit and StandardsReport on constitutional changes to Panel format
Who it affectsNot stated

What was decided

The Cabinet received and noted the minutes of the Climate Change Panel meeting of 5 May 2026, without amendment or debate. Report P9

Why

The Cabinet acts as the parent body receiving the Panel's minutes, and the recommendation was a procedural noting of the record. Report P1, P2

What happens next

Officers will draft a report for the Audit and Standards Committee proposing constitutional changes to create twice yearly internal member briefings, twice yearly progress updates on the Climate Change and Nature Recovery Strategy for Overview and Scrutiny, and twice yearly in person Climate Change Forums held partly outside working hours. Report P18, P22, P23

Constitutional changes will need approval by the Audit and Standards Committee and then full Council before a Climate Change Forum can be held. Report P18

Round four of the Community Climate and Nature Fund is open for applications, with quarterly appraisal meetings releasing around £50,000 each, subject to demand, on 29 July 2026, 14 October 2026, 13 January 2027 and 7 April 2027. Report P26, P27, P28

The money

  • £200,000 Total round four budget for the Community Climate and Nature Fund Report P26
  • £50,000 Increase in the round four budget compared with round three Report P26
  • £50,000 Approximate sum to be released each quarter in round four, depending on demand Report P27

Implications

  • Governance: Changing the Panel into a Forum requires amendments to the Council's Constitution, with sign off from Audit and Standards Committee and then full Council. Report P18, P22
  • Climate: Twice yearly strategy progress reports would go to Overview and Scrutiny, and to Cabinet where necessary, embedding climate monitoring in the scrutiny cycle. Report P23
  • Financial: Round four of the Community Climate and Nature Fund opens with £200,000 available, £50,000 more than round three, increasing the Council's annual climate grant commitment. Report P26
  • Equalities: The proposed Forum would run partly outside working hours to widen attendance, and would draw on the Climate Assembly model that included schoolchildren. Report P18, P23

Who and where

  • Town and Parish Councils, who are eligible to apply to round four of the Community Climate and Nature Fund and were the focus of the Local Climate Engagement Programme Report P19, P26
  • Sports clubs, charity and community groups eligible to apply for round four of the Community Climate and Nature Fund Report P26
  • Residents who took part in the consultation on the future of the Climate Change Panel, 54 of whom responded Report P17
  • Schoolchildren, whose engagement at the Climate Assembly was singled out as particularly important Report P18
  • Heart of England Community Energy, mentioned in a disclosure of interest by a Panel member Report P8

Timeline

  • 5 May 2026: Climate Change Panel meeting held in the Council Chamber at Elizabeth House, Stratford-upon-Avon, 4.00 p.m. to 4.33 p.m. Report P4
  • 29 July 2026: First quarterly appraisal of round four Community Climate and Nature Fund applications Report P28
  • 14 October 2026: Second quarterly appraisal of round four Community Climate and Nature Fund applications Report P28
  • 13 January 2027: Third quarterly appraisal of round four Community Climate and Nature Fund applications Report P28
  • 7 April 2027: Fourth quarterly appraisal of round four Community Climate and Nature Fund applications Report P28

Plain English for the jargon

  • CCNF: Community Climate and Nature Fund, the Council's grant scheme for local climate and nature projects.
  • LCEP: Local Climate Engagement Programme, a practically focused programme of support for Town and Parish Councils and community organisations.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item55

Resolved

That the Minutes, as presented, be received and noted.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet, 4 pages

Climate Change Panel

05 May 2026

Minutes

Held at Council Chamber, Elizabeth House, Church Street, Stratford-upon-Avon Meeting commenced: 4.00 p.m. Meeting ended: 4.33 p.m.

Present: Councillor Susan Juned (Chair) Councillors B Fleming, J Fradgley, O Hatch, S Keighley, D Passingham and L Petrovic

680. Disclosures of Interest

The standard disclosures on the agenda were noted.

Councillor Passingham disclosed that he was a director for Heart of England Community Energy (a community benefit society) which ran a solar farm outside of Stratford-upon-Avon. This position was a voluntary role.

681. Minutes

The Minutes of the meeting held on 3 March 2026 were confirmed and signed.

682. Matters Arising

No matters were raised.

683. Public Participation

No questions were received from the public.

684. Climate Change Panel Consultation

Councillor J Fradgley joined the meeting during this item.

The Chair introduced the item, advising members that a consultation with residents and local councils had been conducted regarding the proposals to change the format of the Climate Change Panel. 54 responses had been received, with 98% of respondents favouring that a twice-yearly Climate Change Forum take place.

The Climate Change Project Manager advised members that any change to the Climate Change Panel would take time as these changes would need to be reflected in the Council’s Constitution, which would require approval by the Audit and Standards Committee and then full Council. Once approved, a Climate Change Forum would be organised as soon as possible. It was noted that the proposed Climate Change Forum would take a similar format to the previously held Climate Assembly event, which had been well attended. Engagement with schoolchildren through the event had been particularly important.

The Forum would be planned as a more accessible and open event than the Local Climate Engagement Programme (LCEP), which was a more practically driven programme of support for Town/Parish Councils and community organisations.

In response to Members’ questions, the Climate Change Project Manager advised that, in regard to Local Government Reorganisation, she would benchmark against other local authorities who had recently gone through the process to examine how climate change matters were integrated into the new authority.

The Chair noted her thanks to all respondents for participating in the public consultation on the future of the Climate Change Panel.

Following this, it was agreed that a report would be drafted for consideration by the Audit and Standards Committee which would present the following changes to the Constitution on how the Climate Change Panel would be conducted in the future:

 Twice-yearly internal meetings held to brief members;  Twice-yearly updates on the progress of the Council’s Climate Change and Nature Recovery Strategy, which would be considered by the Overview and Scrutiny Committee and, where necessary, The Cabinet; and  Twice-yearly in-person Climate Change Forum, which would run partly outside of working hours to enable a wide range of attendees.

685. Community Climate and Nature Fund

At the invitation of the Chair, the Project Officer (Climate Change) presented an update on the third round of the Community Climate and Nature Fund (CCNF), reporting which projects had been successful in their applications for funding.

The Project Officer then advised that round four of the CCNF had opened to applications, with a total overall budget of £200,000 available which was an increase of £50,000 on the round three budget. Town/Parish Councils, sports clubs and charity and community groups were invited to apply for grant funding through the CCNF.

Officers were due to meet quarterly to appraise the applications, with approximately £50,000 released in each quarter, depending on demand for funding. The assessment dates for round four were:

 29 July 2026;  14 October 2026;  13 January 2027; and  7 April 2027.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Climate Change PanelReports_pack 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stratford-on-Avon

Search all
  1. Climate Change PanelThis decision
  2. Minute 140 - Constitution Review - Climate Change Panel Terms of ReferenceAgreed
  3. Climate Change PanelNoted
  4. 2026/2027 Climate Change and Nature Recovery Delivery Plan and Progress ReportApproved
  5. Climate Change PanelNoted
  6. Delivery of Climate Change Adaption Audit ProgrammeDecided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open