Revenue Budget Monitoring Period 1 - 4 2026/27

Noted Executive 5 papers

AI summaryStratford-on-Avon District Council Cabinet received the Period 4 2026/27 revenue position showing a favourable estimated outturn of £159,000 and approved two non-domestic rate write-offs of £26,495 and £111,358.50.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTwo NNDR write-offs over £10,000 approved
Money£159,000 favourable estimated outturnAfter net transfer from reserves of £6,946,243
What happens nextFurther Cabinet report if neededIssues may go to Portfolio Holder for clarification
Who it affectsCouncil tax and business rate accountsIncluding a small business affected by VOA error

What was decided

Cabinet received the Period 4 actual net variance and the estimated 2026/27 revenue outturn, showing an unfavourable Period 4 position of £52,545 and a favourable estimated outturn of £159,000. Report P6, P7

Cabinet noted write-offs over £1,000 already approved: Council Tax £70,008.50 over 81 accounts, and NNDR £47,766.11 over 23 accounts. Report P6

Cabinet approved two NNDR write-offs: £26,495 for a property removed from the rating list after a fraudulently signed lease, and £111,358.50 for a small business affected by a VOA rateable value error. Report P6

Why

The report is a high-level summary using the Period 4 position as a base, with further known and estimated items applied to reach the outturn position. Report P6, P13

The £26,495 write-off is needed because the Valuation Office Agency cannot retrospectively remove liability for the 2021 and 2022 rating years, and the property was originally listed on the basis of a fraudulently signed lease. Report P6

The £111,358.50 write-off is recommended because the VOA acknowledged a significant error in the rateable value but cannot apply the correction to earlier closed rating lists, and pursuing the liability against a small business would not be just or equitable. Report P6

What happens next

Any issues identified for further consideration may be addressed by the relevant Portfolio Holder for clarification, with a further report to Cabinet if required. Report P5, P12

The money

  • £52,545 Unfavourable Period 4 net variance Report P6
  • £159,000 Favourable estimated revenue outturn for 2026/27 Report P6, P16
  • £70,008.50 Council Tax write-offs over £1,000 already approved (81 accounts) Report P6
  • £47,766.11 NNDR write-offs over £1,000 already approved (23 accounts) Report P6
  • £26,495 NNDR write-off approved for Account 1 Report P6
  • £111,358.50 NNDR write-off approved for Account 2 Report P6
  • £20,640,526 Opening General Reserve balance 1 April 2026 Report P10
  • £13,853,283 Estimated General Reserve balance 31 March 2027 Report P10, P16
  • £27,597,076 Estimated Council Funds earmarked reserves 31 March 2027 Report P11
  • £8,995,680 Estimated earmarked reserves from external funding 31 March 2027 Report P11

Options considered

  • Chosen: Receive the expected revenue outturn position and address issues via the relevant Portfolio Holder or a further Cabinet report. Provides oversight while allowing flexibility for clarification Report P5, P12
  • Chosen: Note the write-offs contained within paragraph 3.1. These write-offs have already been approved and are reported to Cabinet for noting Report P6
  • Chosen: Approve the write-offs contained within paragraph 3.2. Over £10,000 and require Cabinet approval; recommended due to VOA error and unjust liability for a small business Report P6

Implications

  • Financial: Estimated General Reserve balance of £13,853,283 at 31 March 2027, after a net transfer from reserves of £6,946,243. Report P10, P16
  • Financial: Major Period 4 variances include Investment Interest favourable £274,698 and Policy and Economic Development unfavourable £352,584 (funded from earmarked reserves and recharged to Warwick District Council). Report P7
  • Financial: Estimated 2026/27 outturn variances include Property unfavourable £400,000 (new cleaning contract) and Investment Interest favourable £500,000. Report P7
  • Legal: No legal implications identified for the report itself, but write-offs relate to debts considered unrecoverable. Report P14, P6
  • Other: No implications for equalities, environment or climate change, data protection, health and wellbeing, or human resources and staffing. Report P14

Who and where

  • Small business ratepayers, including a ratepayer in Account 2 protected from unjust liability arising from a VOA error Report P6
  • Warwick District Council, recharged for its share of South Warwickshire Local Plan costs and use of legal services Report P7
  • Council tax account holders subject to debt collection action, including 81 accounts written off at £70,008.50 Report P6
  • Non-domestic rate account holders, including 23 accounts written off at £47,766.11 Report P6

Timeline

  • 1 April 2026 - 31 July 2026: Period 4 covered by the revenue budget monitoring report Report P5, P6
  • 7 September 2026: Cabinet meeting date Report P1, P5
  • 31 March 2027: Estimated year end for the 2026/27 revenue outturn and reserve balances Report P10, P11

Plain English for the jargon

  • NNDR: National Non-Domestic Rates, the business rates paid by occupiers of non-domestic properties
  • VOA: Valuation Office Agency, the government body that assesses rateable values
  • Period 4: The first four months of the financial year, from 1 April to 31 July
  • Extended Producer Responsibility Grant: A grant paid to councils to cover the cost of managing packaging waste, funded by producers
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item201

Resolved

(1) That the actual net variance as at Period 4, and the estimated revenue outturn for 2026/27, be received; (2) That the write-offs contained within paragraph 3.1 of the agenda report be noted; and (3) That the write-offs contained within paragraph 3.2 of the agenda report be approved. Note: This item is not subject to call-in to the OSC as it is not a key decision
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet

The Cabinet 7 September 2026

Title: Revenue Budget Monitoring Period 1 - 4 2026/27

Lead Officer: Jessica Lail, Financial Services Manager ([email protected])

Portfolio Holder/ Lead Member: Councillor D Curtis

Summary To update The Cabinet on the position of the Council’s revenue expenditure and income as at Period 4 (31 July 2026) together with an estimated net outturn position for each service for 2026/27. Recommendations (1) That the actual net variance as at Period 4 and the estimated revenue outturn for 2026/27 are received and any issues identified for further consideration be addressed by:  The relevant Portfolio Holder for a point of clarification; and  And if required, a further report to The Cabinet. (2) That the write-offs contained within paragraph 3.1 be noted; and (3) That the write-offs contained within paragraph 3.2 be approved.

1 Background/Information 1.1 This report provides an analysis of revenue expenditure and income compared to the profiled budget as at Period 4 (31 July 2026) and reports an estimated end of year outturn position. 1.2 The report is a high-level summary which identifies variances at service level. The Period 4 position has been used as the base to which further known and estimated income and expenditure items have been applied to arrive at an estimated outturn position. 1.3 Items specifically mentioned below are the services that currently show, or are anticipated to have, the greatest variances. A full breakdown of the Council’s services is included within Appendix 1. A further breakdown by category of expenditure is included within Appendix 2. Appendix 3 shows the amendments agreed to the original budget by The Cabinet to arrive at the current budget. Appendix 4 lists the current earmarked reserves. 2 Budget Monitoring – Estimated Outturn 2.1 The Period 4 position is an unfavourable £52,545. The estimated outturn position for the Council at the end of the year is expected to be a favourable position of £159,000. 3 Notification of Write Offs 3.1 There have been the following write-offs over £1,000 that have been approved and that are required to be reported to The Cabinet. The details of these are:  Council Tax totalling £70,008.50 over 81 accounts.  NNDR totalling £47,766.11 over 23 accounts. 3.2 It is recommended that the following write-off over £10,000 in respect of Non-Domestic Rate be approved by The Cabinet:  Account 1 £26,495 - This property was removed from the rating list in 2023. However, the Valuation Office Agency (VOA) is unable to retrospectively remove the liability for the 2021 and 2022 rating years. The property was originally entered into the list based on a lease that was fraudulently signed.  Account 2 £111,358.50 - There was a significant error in the rateable value assessed by the VOA. The VOA has acknowledged this mistake and issued a Regulation 16 Certificate; however, because earlier rating lists are now closed, the correction can only be applied from 2023 onwards. Had the rateable value been assessed correctly, it would have been £3,650 in the 2017 Rating List rather than £37,750, and the property would have qualified for Small Business Rates Relief. In these circumstances, pursuing this level of liability against a small business as a consequence of an error by a government agency would not be just or equitable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revenue Budget Monitoring Appendix 1.xlsx Period 1-4Appendix 139 KB Download
PDF
Revenue Budget Monitoring Appendix 2.xlsx Period 1-4Appendix 92 KB Download
PDF
Revenue Budget Monitoring Appendix 3.xlsx Period 1-4Appendix 48 KB Download
PDF
Revenue Budget Monitoring Appendix 4.xlsx Period 1-4Appendix 177 KB Download
PDF
Revenue Budget Monitoring Period 1: 4 2026/27Report 447 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 20 attended
SJ
Councillor Susan JunedLeader, present
GC
Councillor George CowcherDeputy Leader, present
LA
Councillor Louis AdamPortfolio Holder, present
LC
Councillor Liz ColesPortfolio Holder, present
DC
Councillor David CurtisPortfolio Holder, present
NG
Councillor Natalie GistPortfolio Holder, present
LG
Councillor Lorraine GrocottPortfolio Holder, present
TH
Councillor Trevor HarveyObservers, present
MR
Councillor Mike RiceObservers, present
DP
Councillor Dave PassinghamObservers, present
DP
Councillor Daren PembertonObservers, present
SW
Councillor Sarah Whalley-HogginsObservers, apologies

All 20 on the meeting page

On this subject at Stratford-on-Avon

Search all
  1. Revenue Budget Monitoring Period 1 - 4 2026/27This decision
  2. Revenue Budget Monitoring Period 1 - 6 2026/27Noted
  3. Revenue Budget Monitoring Period 1 - 2 2026/27Approved
  4. Revenue Budget Monitoring - Period 1 - 10 2025/26Noted
  5. Revenue and Capital Budget 2026/27Approved
  6. Revenue Budget Monitoring Period 1 - 8 2025/26Noted

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open