FORMATION OF THE IMPLEMENTATION TEAM AND PROGRAMME STRUCTURE
AgreedCommittee2 papers
AI summaryWest Surrey Joint Committee agrees formation of a single Implementation Team to coordinate Surrey's local government reorganisation. Estimated pre-vesting costs are £35,300,000, with Surrey County Council covering 80%.
Money£35,300,000Estimated pre-vesting day costs, 80% Surrey County Council, 20% Districts and Boroughs
What happens nextFebruary meetingInitial Workstream breakdown to be brought
Who it affectsAll 12 Surrey councilsPlus residents, ahead of two new unitary councils forming 1 April 2027
What was decided
The West Surrey Joint Committee agreed to form a single team of officers (the Implementation Team) in line with the anticipated requirements of the draft Structural Changes Order. Report P2
The committee noted the programme structure arrangements set out in Annex 1, covering 11 thematic work areas led by named theme sponsors. Report P2, P21, P23
An action was set for an initial Workstream breakdown to be brought to the February meeting.
Why
The draft Structural Changes Order will require a single Implementation Team to be formed within 21 days of the Order coming into force, and the team must include officers from the county council and West Surrey councils. Report P3, P9, P56, P57
Setting the team up voluntarily ahead of the statutory deadline allows early planning and coordination within tight timescales for the transition. Report P3, P11
Officers warned that not forming the team now would delay critical transition work and risk the new councils being unable to meet their statutory duties on vesting day. Report P5, P48
What happens next
Following endorsement by both Joint Committees, the Implementation Programme Board will be stood up, with the Senior Responsible Officer as chair. Report P20, P64
Work will proceed at pace to develop an Implementation Plan, covered in a separate report on the same agenda. Report P12, P64
Theme sponsors will review discovery findings and agree resourcing requirements, and an initial Workstream breakdown will come to the February meeting. Report P64
The money
£35,300,000 Estimated pre-vesting day cost of creating two unitary councils, set out in the two unitary business case Report P51
80% Share of LGR Implementation Reserve to be contributed by Surrey County Council Report P51
20% Share of LGR Implementation Reserve to be contributed by District and Borough councils Report P51
Options considered
Chosen: Form a voluntary Implementation Team ahead of the Structural Changes Order coming into force. Enables planning at pace and a safe, legal transition; meets MHCLG expectation that Surrey County Council and supporters of the two-unitary model take a lead Report P5, P11, P18, P19
Rejected: Wait until after the Structural Changes Order is enacted before forming the team. Would delay implementation planning, risk critical transition work not being completed before vesting day, and leave the new councils potentially unable to meet statutory duties Report P5, P48
Implications
Legal: Once the Surrey Structural Changes Order is enacted, there will be a legal duty to form the Implementation Team, and all councils must co-operate and release officers as reasonably required. Report P47, P57
Financial: All 12 councils will pay their share of a single LGR Implementation Reserve into a dedicated code held by Surrey County Council, with implementation costs accruing from 1 January 2026. Report P51, P52
Staffing: Implementation Team members will perform the role alongside their substantive sovereign council duties and receive no additional pay; no backfilling is proposed at this stage, though this will be kept under review. The Programme Director role is proposed to be funded through the Implementation Reserve. Report P17, P59
Risk: Not forming the team now could put service delivery at risk and leave the new councils unable to meet their statutory duties on vesting day; approval mitigates this risk. Report P5, P48, P49
Equalities: There are no direct equality implications from agreeing the recommendation, but the team will set out how equality analysis will inform decisions as part of the Implementation Plan. Report P60, P61
Other: The Senior Responsible Officer is Surrey County Council's Chief Executive, with the Deputy Chief Executive as acting SRO; deputies represent the West and East Surrey footprints. Report P14, P15, P28, P29, P30
Who and where
All 12 Surrey councils, who will pay into the LGR Implementation Reserve and release officers to the team Report P51, P57
The West Surrey Joint Committee, which the team will support in discharging its functions Report P9, P56
Future East and West Surrey shadow unitary authorities and their Interim Heads of Paid Service (to be designated May 2026) Report P9, P45
Surrey residents, members and partners, who will continue to be engaged on emerging plans Report P64
Timeline
28 October 2025: Secretary of State announced decision to proceed with two unitary councils in Surrey and MHCLG shared the draft Structural Changes Order Report P7, P8
6 November 2025: All Chief Executives agreed to appoint Nicola Kilvington as Programme Director for devolution and LGR Report P17
1 December 2025: Prospective members of both Voluntary Joint Committees briefed on next steps for LGR transition Report P46
1 January 2026: Implementation costs begin to accrue against the LGR Implementation Reserve Report P52
16 January 2026: West Surrey Joint Committee endorsed the Implementation Team and programme structure
February 2026 meeting: Initial Workstream breakdown to be brought to the Joint Committee
March 2026 (anticipated): Draft Surrey Structural Changes Order expected to come into force Report P1
May 2026: First meetings of the Shadow Authorities, including designation of Interim Heads of Paid Service to be reflected in the team Report P45
1 April 2027: Vesting day on which the two new unitary councils take over responsibility for local government functions and powers Report P8
Plain English for the jargon
LGR: Local Government Reorganisation, the restructuring of councils in Surrey into two unitary authorities
SCO: Surrey (Structural Changes) Order, the draft statutory instrument setting out transitional arrangements for the reorganisation
SRO: Senior Responsible Officer, the lead of the Implementation Team, held by Surrey County Council's Chief Executive
PMO: Programme Management Office, which coordinates programme governance, planning and delivery assurance
MHCLG: Ministry of Housing, Communities and Local Government, the UK government department overseeing the reorganisation
Section 151 Officer: The local authority chief finance officer with statutory responsibility for financial administration
DASS / DCS: Director of Adult Social Services / Director of Children's Services, statutory director roles on councils
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
RESOLVED that: 1. the arrangements for the formation of a single team of officers (“the Implementation Team”) as detailed in Annex 1 of the report, in line with the anticipated requirements set out in the draft Structural Change Order, be agreed. 2. the programme structure arrangements as set out in Annex 1 of the report be noted. ACTION: An initial Workstream breakdown to be brought to the February meeting.
Word for word from the decision Surrey published for this meeting.Source: mycouncil.surreycc.gov.uk
This report proposes the formation of an Implementation Team and the arrangements for the structure of the implementation programme in preparation for Local Government Reorganisation (LGR) in Surrey. This reflects requirements in the draft Surrey (Structural Changes) Order (SCO), which is anticipated to come into force in March 2026.
Recommendations
It is recommended that the Voluntary West Surrey Joint Committee: 1. Agrees the arrangements for the formation of a single team of officers (“the Implementation Team”) as detailed in Annex 1, in line with the anticipated requirements set out in the draft SCO. 2. Notes the programme structure arrangements set out in Annex 1.
Reason for recommendations
Under the draft SCO, it will be a statutory requirement for the joint committees to form a single Implementation Team. Given the tight timescales for implementing LGR in Surrey, it is proposed that a voluntary Implementation Team is formed ahead of the SCO coming into force in March 2026. This will enable early planning and effective coordination by officers to support a safe and legal transition to the East Surrey and West Surrey councils.
Options, including alternatives (if any)
This report proposes the establishment of an Implementation Team ahead of the SCO coming into force, which will allow planning and coordination work to progress at pace, ensuring readiness for the LGR transition. Choosing not to form the Implementation Team as set out here and at this stage would delay implementation planning, which is not recommended given the limited time available to progress LGR. This could result in critical transition work not being completed before vesting day, putting service delivery at risk and potentially leaving the new councils unable to meet their statutory duties.
Page 31 Executive Summary:
Context 1. On 28 October 2025 the Secretary of State announced his decision, subject to Parliamentary approval, to move forwards with the implementation of the proposal to abolish all existing councils across Surrey and replace them with two unitary councils.
2. At the same time, the Ministry of Housing, Communities and Local Government (MHCLG) shared a draft Surrey (Structural Changes) Order (SCO). This outlined the transitional arrangements which are expected to be put in place to ensure that the new unitary councils are ready to take over responsibility for local government functions and powers on 1 April 2027.
3. The draft SCO specifies that a single team of officers (“the Implementation Team”) must be formed no later than 21 days after the Order comes into force. The purpose of the Implementation Team is to support the joint committees to discharge their functions, and the shadow authorities once they are in place.
4. While local authorities across Surrey are not required to set up the Implementation Team until after the SCO comes into force, MHCLG officials wrote to councils on 28 October 2025 stating: “We hope that seeing the draft Structural Changes Order will enable you to put arrangements in place voluntarily, ahead of the Order being made, to progress local government reorganisation, such as the Joint Committees and the Implementation Team. This will support the preparatory work that can be progressed prior to the Order coming into force, recognising that the Order will place duties on your councils to cooperate.”
5. As with the early establishment of the Joint Committees, setting up the Implementation Team on a voluntary basis will allow preparatory work to be completed ahead of the SCO being formally enacted, supporting a swift and smooth transition.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of chair and vice chairRESOLVED that Councillor Ann-Marie Barker be elected Chair of the Voluntary West Surrey Joint Committee. Meeting Adjo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.