Resolved
(i) That the report be noted; and (ii) Fiona Lander and the Planning Department be thanked for the report.
Carshalton and Clockhouse Area Committee noted this item on Wednesday 14 December 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) That the report be noted; and (ii) Fiona Lander and the Planning Department be thanked for the report.
1.1At the Strategic Planning Strategy Committee Advisory Group of 21 March 2005 members agreed to a change in the way the progress and performance of the Planning Enforcement Service is reported to Members. It was agreed that reports should be submitted twice yearly to Area Committees and Development Control Committee and cover statistically all enforcement action for the relevant period.
1.2This report concerns the period from 1 March 2005 to 1 September 2006.
2. Six Month Period 1 September 2005 to 1 March 2006
2.1In the six month period from 1 March 2005 to 1 September 2005 162 new enforcement cases were received. These divided into the four areas as follows: Page 16
Area Priority One Priority Two Priority Three Cheam and Worcester 2 14 20 Park Sutton 5 15 21 Carshalton and 3 18 26 Clockhouse Beddington and 3 16 19 Wallington
2.297 cases remain outstanding from before 1 March 2005 (as at 1 September 2005) . A total of 176 cases are currently being investigated (as at 1 September 2005).
2.3Over this six month period the initial site visit was made within the agreed time period in 86.4% of the cases. 92% of the priority one cases were investigated within two days of receiving the complaint, 78% of the priority two cases within five working days and 92% of the priority three cases within ten working days. 106 of the total number of cases received concerned a breach of planning control.
2.4In the six month period from 1 March 2005 to 1 September 2005 a total of 133 cases have been closed, for the following reasons:
Permitted Development 26 No Breach of Planning Control 39 Breach Ceased 33 Planning Permission Granted 11 No Further Action 24
2.5A total of 23 Enforcement Notices, Breach of Condition Notices and Planning Contravention Notices have been issued. 5 Enforcement Notices are currently the subject of appeals. 1 appeal decision has been received, in which the Inspector found in favour of the appellant.
3. Financial Implications Not applicable.
4. Influence of the Council’s Core Values Not applicable.
5. Contribution to the Achievement of the Council’s Policy Aims Not applicable.
6. Background Papers Agreed Priorities – included as an appendix to this report Page 17
Agreed Priorities
Priority One Cases: Site visit within 2 working days of date complaint letter received.
Demolition of buildings, erection of new buildings, unauthorised works to Listed Buildings and protected trees, cessation of building works or use, which would otherwise become immune from enforcement by reason of the statutory time limits. Development within Conservation Areas.
Priority Two Cases: Site visit within 5 working days of date complaint letter received.
Development causing significant nuisance to the occupiers of nearby residential properties.
Cases considered under this priority would include the following:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 04 Planning EnforcementReport | 20 KB | DownloadRead as text |
Follow Carshalton and Clockhouse Area Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jun 2007 | Update from the metropolitan police(i) To note the presentation from Inspector Pendleton. (ii) That the Safer Neighbourhood Team be congratulated on the... | Noted | Open |
| 13 Jun 2007 | Steps zone 29(i) That Environment and Leisure provide a ward bulletin. (ii) That the above schemes be noted. | Noted | Open |
| 13 Jun 2007 | References from the northern wards forumResolved : To note the above. (ii) Parking issues in Tweeddale Road The Forum had highlighted concerns about the park... | Noted | Open |
| 13 Jun 2007 | References from carshalton forumResolved : (i) That a meeting between the Planning Department, Environment and Leisure and Transport for London be ar... | Decided | Open |
| 13 Jun 2007 | Section 106 funds - shopfront renewal scheme at rosehill(i) That the above Progress Reports be noted. (ii) That the proposed scheme of a match-funding shop front uplift sche... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies