borough spending plan 2006/07 transport settlement
NotedCommittee1 paper
Cheam and Worcester Park Area Committee noted this item on Wednesday 22 February 2006. Below is the council's own wording, with the papers it was decided on.
(i) To note the 2006/2007 BSP settlement and programme and that the Strategy Committee have released financial provision for the schemes identified in the settlement. (ii) To agree the list of schemes relevant to this Area Committee. (iii) That delegated authority be given to the Executive Head Planning & Transportation, in consultation with the Chair and ward councillors, agree details of individual schemes. (iv) That any comments from members be sent to the Executive Head of Traffic and Transport.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Carshalton and Clockhouse Area Committee – 15 February 2006 Cheam and Worcester Park Area Committee – 22 February 2006 Beddington and Wallington Area Committee – 22 March 2006 Sutton Area Committee – 29 March 2006
Report of the Principal Engineer (Transport & Projects)
BOROUGH SPENDING PLAN 2006/2007 TRANSPORT SETTLEMENT
Ward Location: Not Applicable Author(s) and Contact Phone Numbers: Area Served: Borough-Wide Peter Wardill 020 8770 6440
Lead Councillor Councillor Colin Hall
Executive Decision Report
Summary Transport for London (TfL) has advised the Council of the Borough Spending Plan (BSP) settlement for 2006/07. Sutton has been allocated a grant of £2,933,950 for 2006/07, plus £216,000 for SWELTRAC, towards transport schemes. Commitments of £476,000 for 2007/08 of which £8,000 relates to SWELTRAC and £196,000 for 2008/09 are also made. Recommendations I recommend the Committee to : a. Note the 2006/2007 BSP settlement and programme and that the Strategy Committee have been recommended to release financial provision for the schemes identified in the settlement. b. Agree the list of schemes relevant to this Area Committee. c. Delegate to the Executive Head Planning & Transportation, in consultation with the Chair and ward councillors to agree details of individual schemes. 1. Background 1.1 The Council submitted its BSP for 2006/07 to TfL last July in accordance with guidance issued earlier in the year. The BSP system is used as the basis for allocating capital funding to London local authorities for roads, transport, traffic and other highway related matters. The Council were required to prioritise its proposals in various topics and categories as part of the bid. 1.2 Package bids were submitted on a London-wide basis for the London Bus Priority Network (LBPN) and the London Cycle Network (LCN+). A package bid for strategic Page 62
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.