Resolved
To note the report reviewing the progress of the Planning Enforcement Service for the period 1 September 2005 to 1 March 2006.
Beddington and Wallington Area Committee noted this item on Wednesday 7 June 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the report reviewing the progress of the Planning Enforcement Service for the period 1 September 2005 to 1 March 2006.
1.1At the Strategic Planning Strategy Committee Advisory Group of 21 March 2005 members agreed to a change in the way the progress and performance of the Planning Enforcement Service is reported to Members. It was agreed that reports should be submitted twice yearly to Area Committees and Development Control Committee and cover statistically all enforcement action for the relevant period.
1.2This report concerns the period from 1 September 2005 to 1 March 2006.
2. Six Month Period 1 September 2005 to 1 March 2006
2.1In the six month period from 1 September 2005 to 1 March 2006 162 new enforcement cases were received. These divided into the four areas as follows: Page 36
Area Priority One Priority Two Priority Three Cheam and Worcester 4 29 10 Park Sutton 2 24 10 Carshalton and 6 17 22 Clockhouse Beddington and 3 11 24 Wallington
2.2105 cases remain outstanding from before 1 September 2005 (as at 1 March 2006). A total of 172 cases are currently being investigated (as at 1 March 2006).
2.3Over this six month period the initial site visit was made within the agreed time period in 93.8% of the cases. 86.6% of the priority one cases were investigated within two days of receiving the complaint, 91.5% of the priority two cases within five working days and 98.5% of the priority three cases within ten working days. 112 of the total number of cases received concerned a breach of planning control.
2.4In the six month period from 1 September 2005 to 1 March 2006 a total of 160 cases have been closed, for the following reasons:
Permitted Development 23 No Breach of Planning Control 26 Breach Ceased 57 Planning Permission Granted 20 No Further Action 34
2.5A total of 11 Enforcement Notices, Breach of Condition Notices and Planning Contravention Notices have been issued. 3 Enforcement Notices are currently the subject of appeals. 1 appeal decision has been received, in which the Inspector found in favour of the appellant. 3 appeal decisions have been received where the Inspector found in favour of the Council.
3. Financial Implications Group Finance comments
3.1None
Strategic/Corporate Finance comments
3.2None Page 37
4. Influence of the Council’s Core Values The enforcement of planning regulations touches on our value of respect; to engender respect there is a need to ensure that people’s privacy and well being are treated fairly and seriously. Changes to the built environment can have an impact on the quality of life of local people if they feel affected by a planning permission or development close to them. For this reason the enforcement of planning control affects how people feel about their neighbourhood and so goes to the heart of part of the Council’s vision of creating a borough in which all can take pride.
5. Contribution to the Achievement of the Council’s Policy Aims Enforcing planning control goes to the heart of the corporate goal of promoting community well being because of the impact on individuals and families affected by developments.
6. Background Papers Agreed Priorities – included as an appendix to this report Page 38
Agreed Priorities
Priority One Cases: Site visit within 2 working days of date complaint letter received.
Demolition of buildings, erection of new buildings, unauthorised works to Listed Buildings and protected trees, cessation of building works or use, which would otherwise become immune from enforcement by reason of the statutory time limits. Development within Conservation Areas.
Priority Two Cases: Site visit within 5 working days of date complaint letter received.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Enforcement ServiceReport | 21 KB | DownloadRead as text |
Follow Beddington and Wallington Area Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jul 2007 | References from other committeesTo inform the Executive that the committee approve in principle the proposed land swap between the Council and the Su... | Approved | Open |
| 11 Jul 2007 | petition - traffic calming, queenswood avenue, Wallington(i) That Alan Carroll and Sgt Waddington arrange for speed/volume tests to be undertaken, in Queenswood Avenue, after... | Decided | Open |
| 11 Jul 2007 | petition - request for CCTV at the broadway, beddington(i) That Sgt Waddington be requested to treat this as a matter of urgency and push for a rapid deployment camera at T... | Decided | Open |
| 11 Jul 2007 | Wallington green conservation area – draft management planThat members forward any comments to Matthew Robson before the 17 July. | Decided | Open |
| 11 Jul 2007 | shotfield health centre(i) To thank Andrew Grimes and Steve Grant for attending the ... view the full minutes text for item 663. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.