(i) To reaffirm the decision by Minute 818/04 to use £20,792 of the Bellway Homes Planning Agreement to fund part of the cost of the borough-wide Employment Study; (ii) To agree that the remainder of the uncommitted funds from the Agreement be used for environmental improvement works within the Rosehill District Centre.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
London Borough of Sutton Strategy Committee – 10 July 2006
Report of the Interim Executive Head of Planning, Transport and Highways THE USE OF S. 106 FUNDS FROM BELLWAY HOMES PLANNING AGREEMENT, ROSEHILL Ward Location: St Helier Author: Jeff Wilson (x6258) Area Served: All Wards Lead Councillor: Lyn Gleeson
Report For Decision Summary This Report considers the use of the developer contribution in connection with the Bellway Homes development at Rosehill to fund the Council’s Employment Study. Recommendation I recommend that Strategy Committee: a. re-affirms its decision to fund part of the cost of the Employment Study from £20,792 from the Bellway Homes Planning Agreement; b agrees the use of the remaining funds from the Agreement for environmental improvement works within Rosehill District Centre. 1. Introduction 1.1 Following referral of a Report on the S106 Local Area Investment Programme from the Carshalton and Clockhouse Area Committee meeting on 14 December 2005 to Strategy Committee on 6 February 2006, the Committee resolved (Minute 165/06) to note the concerns about how the Rosehill Avenue S106 money was used and ask the Executive Head of Legal and Democratic Services to discuss the matter with the Executive Head of Planning Transport & Highways to ensure all the issues are being dealt with properly and appropriately including, if thought necessary, seeking Counsel’s advice. 1.2 This matter and, in particular, appropriateness of the expenditure of funds from the Bellway Homes Planning Agreement for the purposes of funding the borough-wide employment study, was discussed in a meeting between the Executive Head of Legal and Democratic Services and the Executive Head of Planning Transport & Highways on 6 April 2006. 1.3 This Report set out the background information concerning the use of funds from the Bellway Homes Planning Agreement. A concurrent Report of Executive Head of Legal Services is attached. 2. Bellway Homes Planning Agreement 2.1 Section 5.1 of the Bellway Homes Planning Agreement specifies that “a sum amounting to £180,000 as a contribution towards economic development and/or regeneration initiatives and environmental improvements to include a contribution towards the cost of providing public toilet facilities within Rosehill District Centre”. Having regard to this, the only limitation on the scope for pooling funds from this contribution arises from the requirement for public toilet facilities at the Rosehill District Centre, for which £50,000 has already been committed towards the Page 148
construction of new toilets at the Co-op store under an agreement made with the Co-op on 13 April 2006. It is expected that these will become operational within six months. Apart from this restriction, the remainder of the contribution can rightfully be spent on borough-wide benefits. In the light of this, the legal advice is that Section 5.1 can be interpreted in this way and the use of some of the money to fund the borough-wide industrial land study was proper. 2.2 The authority to pool developer contributions for employment generation purposes for projects of major strategic significance was given by the Strategy Committee on the 15 September 2003 (Minute 817/03(i)). Details of the proposal to use some of the funding from the pool of developer contributions set aside for employment generation to commission the industrial land study from consultants was agreed by Strategy Committee on 14 September 2004 (Minute 818/04). Therefore there is no doubt that the appropriate committee authority was obtained to fund the study from S106 resources set aside for this purpose. 2.3 As well as the Bellway Homes Planning Agreement, two other developer contributions were “pooled” for expenditure on borough-wide employment generating projects and these were: • Scheme 8454 (M959) (£10,000) Station Road, Belmont; • Scheme 8486 (M994) (£27,000) Mill Lane, Carshalton.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.