BRIDGE ROAD, WALLINGTON - CYCLE AND PEDESTRIAN WAY
ApprovedCommittee1 paper
Beddington and Wallington Area Committee approved this item on Wednesday 10 January 2007. Below is the council's own wording, with the papers it was decided on.
Resolved : (i) That the scheme as presented for consultation be approved. (ii) That a consultation with residents in the locality on the scheme be approved. (iii) That subject to no material variations being received to delegate the Executive Head of Planning, Transport and Highways to make the appropriate traffic orders, subject to the funding from TfL and Network Rail being secured.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Beddington and Wallington Area Committee
Page 41 Agenda Item 11
London Borough of Sutton
Beddington & Wallington Area Committee January 2007
Report of the Interim Head of Transport Planning & Works
BRIDGE ROAD, WALLINGTON CYCLE AND PEDESTRIAN WAY
Ward Location: Wallington North Author(s) and Contact Phone Number(s): Alan Carroll - Telephone 8770 6462 Area Served: Wallington North Lead Councillor: Cllr Colin Hall
Key Decision Report
Summary This report proposes a new pedestrian and cycle route to be located across the railway bridge at Bridge Road, Wallington. Recommendations I recommend the Committee to : i) Approve the scheme as presented for consultation; ii) Agree to a consultation with residents in the locality on the scheme, and iii) Subject to no material variations being received to delegate the Executive Head of Planning, Transport, and Highways to make the appropriate traffic Orders, subject to the funding from TfL and Network Rail, being secured.
1. Background Bridge Road was closed in 2004 to facilitate the bridge strengthening works undertaken by Network Rail. This work was undertaken, but Network Rail were still concerned about the integrity of the bridge and requested that the bridge be given a weight limit and a width restriction to limit the size of vehicles able to use it. They agreed that they would contribute to the costs to achieve this. 2. Issues While the bridge was closed, it was noted that traffic levels along Woodcote Road appeared to be increasing, and complaints were received from residents in Clarendon Road and Elgin Road about increased through traffic.
1 Agenda Item 11 Page 42
If Bridge Road were to be reopened, there is concern that traffic wishing to avoid Woodcote Road and destined for Stafford Road, would find this route particularly attractive. Consideration was given to alternative solutions to limit this prospect and from discussions it was considered that Bridge Road could provide a very useful and attractive cycle route, which would provide a safe alternative to the use of the main road. A design has therefore been drawn up, which limits traffic onto the bridge to only service vehicles for the future maintenance of the bridge, but gives preference to cyclists and pedestrians. Whilst the London Fire Brigade Station is located in Belmont Road, the fire brigade would not be able to use the bridge, because the tenders significantly exceed the weight restriction that was proposed. It is hoped that this link would eventually form part of the borough wide network and is an important addition to the provision of safe cycling in the borough. The design incorporates improved lighting and surfacing and clear indications of the route. It is proposed that this be consulted upon in the locality and with the cycling groups. 3. Financial Implications The estimated cost of this scheme is £25,000. Network Rail have agreed to make a contribution to the scheme, and TfL cycling unit is likely to meet the remainder of the cost. Whilst the implementation costs will not be a call upon the Council’s revenue or capital resources, any ongoing maintance costs will need to be contained within Environment and Leisure’s budget allocation. 4. Influence of the Council’s Core Values As this scheme is focussed on those who do not have a private vehicle and are required to cycle or walk, it meets the council’s core value in “promoting equality where everyone is treated fairly but taking account of the special needs of people who lack resources or face disadvantage”. 5. Contribution to the Achievement of the Council’s Priorities for Change This scheme contributes to the achievement of the Council’s priority in being part of developing a renewal strategy for the borough.
22/12/06 Committee Rep 2006 V2.0
2 Page 43 Agenda Item 11
3 Page 44
This page is intentionally left blank
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
References from other committeesTo inform the Executive that the committee approve in principle the proposed land swap between the Council and the Su...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.